Resolved 1. That the draft specification attached at appendix A to the report be approved 2. That the reduction in budget provision for this contract as part of the decision taken in February 2017 - this will mean an upper limit of £300k p.a. in line with our council savings plans, be noted 3. That authority be delegated to the Chief Executive, in consultation with the Lead Member for the Voluntary Sector, to award a 5 year contract (with an option to extend for a further 2 years) to the successful bidder according to the outcomes of the procurement process.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1The council entered into a contract (The Voluntary Sector Infrastructure & Capacity Building Fund - VSICBF) in April 2015 for 4 years with Sutton Centre for the Voluntary Sector (SCVS). This contract provides support to the voluntary sector against the following themes:
● An effective and efficient voluntary sector infrastructure offer
● The integration of the voluntary and community sector in Sutton Borough strategic developments
● The effective development of the voluntary and community sector market
● A robust and sustainable voluntary and community sector offer that meets community needs
● The voice of community members are heard in strategic decision making and operational developments
1.2These themes were reset as part of a range of measures set out in a paper agreed by this committee in February 2017, which looked at refreshing how the Council and the voluntary sector work together more broadly, particularly given the direction of the Sutton Plan. The contract has been managed against these areas since April 2017 with the agreement of the current providers. Agenda Item 9 Page 160
1.3The contract is currently delivered by Community Action Sutton (formerly SCVS) who subcontract elements of it to Volunteer Centre Sutton, Sutton Carers Centre, Age UK Sutton, Bio Regional and Citizens Advice Sutton. The value of the contract is £342k p.a.
1.4The council considers the current contract to have been successfully delivered given the monitoring information provided and feedback from the local voluntary sector, however the contract ends on 31 March 2019 with no option to extend it.
Recommendations
The Strategy & Resources Committee is recommended to:
2.1Agree the draft specification attached at appendix A
2.2Note the reduction in budget provision for this contract as part of the decision taken in February 2017 - this will mean an upper limit of £300k p.a. in line with our council savings plans.
2.3Delegate authority to the Chief Executive, in consultation with the Lead Member for the Voluntary Sector, to award a 5 year contract (with an option to extend for a further 2 years) to the successful bidder according to the outcomes of the procurement process.
Background
3.1Sutton has an active and vibrant local Voluntary, Community & Social Enterprise (VCSE) sector. There are about 400 organisations registered with Community Action Sutton as our current provider and national data suggests there could be as many as a 1000 once micro enterprises are taken into account. The purpose of infrastructure support is to aid those organisations across a range of areas, regardless of their size and composition. The Council is particularly keen to ensure smaller community groups receive an appropriate offer of support to enable them to be successful and well governed.
3.2It would be fruitless to try and list the range of needs supported by the entire local VCSE sector and would likely not do it full justice. However, for the purposes of this contract it should be noted that the breadth of need is significant to ensure organisations that are critical to the success of a healthy borough maintain and develop their activity during challenging times.
3.3The council’s support to the sector’s infrastructure has changed over the years from a more traditional grant funded arrangement, to a strategic partner programme and now a single fund that is bound by a contract. The budget for this is located within the Customers, Commissioning & Governance division.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.