Resolved
RESOLVED : that 1. The performance update set out in section 4 and actions proposed to deliver projects by the Company, including mitigating development risk, be noted. 2. The Quarter 4 financial update be noted.
Sutton Shareholdings Board noted this item on Wednesday 1 May 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : that 1. The performance update set out in section 4 and actions proposed to deliver projects by the Company, including mitigating development risk, be noted. 2. The Quarter 4 financial update be noted.
1.1This report presents for comment the performance update for Sutton Living Limited (“the Company”), and includes the financial update for Quarter 4.
The Sutton Shareholdings Board is recommended to:
2.1Note the performance update set out in section 4 and actions proposed to deliver projects by the Company, including mitigating development risk.
2.2Note the Quarter 4 financial update.
3.1Background information has been provided in previous performance updates relating to progress on the acquisition of various sites for development by Sutton Living Limited, and operations relating to the Company. Agenda Item 7 Page 44
3.2The projects currently being considered for development are Council owned sites and require timely liaison between the Company and Council Directorates.
4. Performance update
Wallington Public Hall
4.1The Company’s first major development, comprising a mixed tenure development of 31 units of homes for market rent and affordable housing is still waiting for a number of outstanding matters to be resolved before building works can start on site.
4.2The current position is:
● Purchase negotiations need to be concluded. Most matters are minor but still need to be agreed between the Council’s solicitor’s Bevan Brittan Solicitors, and the Company’s Lawyers Devonshires, as until completed a building contract cannot be let. The last report referred to the need to close a footpath running along the boundary of the site from the retained car park to Stafford Road. This is the responsibility of the Council to resolve, but the Company has offered to agree the risk sharing of this matter, providing any cost of delays are deducted from the purchase price.
● The funding agreement with the Council still needs to be completed for this project to enable finance to be drawn down to pay the contractor. Sutton Living engaged development finance experts to put forward a funding proposal that satisfies the Council and is currently awaiting for this to be approved. Until it is agreed, the purchase of the site cannot take place, nor can a building contract be let. Review of the site funding and development will have an impact on the Company’s Business Plan see separate report on the agenda).
● Works contract. Negotiations are concluding with the successful contractor and a contract needs to be let by 30th April. This, however, cannot be done until the purchase is complete, and funding for acquisition and works is agreed.
Alexandra Gardens
4.3The Council’s Strategy and Resources Committee has approved the disposal of land on Alexandra Gardens Estate to Sutton for a scheme of 23 units (35% affordable), subject to planning. An application was validated in mid-September 2018 and it was anticipated that it would be reported to April or May Planning Committee. However, there is no meeting of the Planning Committee in May and so the application has been delayed until at least June, which, from the Company’s perspective, is unsatisfactory as this delays the start of the scheme until the autumn. The Company and its planning consultants have expressed their concern at the delay. Page 45 Agenda Item 7
Old Rectory Carshalton
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sutton Living Limited: Performance Update: ReportReport | 146 KB | DownloadRead as text |
Follow Sutton Shareholdings Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. | Agreed | Open |
| 10 Mar 2026 | Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... | Approved | Open |
| 10 Mar 2026 | Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... | Noted | Open |
| 10 Mar 2026 | Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThat Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved.... | Approved | Open |
| 4 Nov 2025 | MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.