London Borough of Sutton
Strategy and Resources Committee, Monday 8 June 2020 at 7.30pm

London Cancer Hub - Update

Approved Committee 1 paper

Strategy and Resources Committee approved this item on Monday 8 June 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the direct delivery of the next phase of development at the London Cancer Hub, as set out in the report, be approved. That authority be delegated to the Strategic Director of Resources to award all contracts necessary to deliver the next phase of development at the London Cancer Hub, including demolition and public realm works on site and construction works to convert Cumbrian House into an innovation hub, in collaboration with local ward councillors, local residents and the local resident associations That the sealing of the Strategic Investment Pot grant agreement between the City of London Corporation and the Council, for the London Cancer Hub award of £8.38m, be approved. That Officers be required to bring forward further information relating to the transport issues on the site together with the potential sources of finance available.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Strategy and Resources Committee

Summary

1.1The London Cancer Hub is a key project for the Council and an important part of our ‘Ambitious for Sutton’ vision. This report seeks authority to proceed with the proposed next phase of development at the LCH, focused on the direct delivery by the Council of a new innovation hub in an existing, Council owned building on the site. The report also describes how the Council is taking forward the learning from the procurement process initiated in 2019 and explains how the project has been adapted in response to changing circumstances.

Recommendations

2.1To approve the direct delivery of the next phase of development at the London Cancer Hub, as detailed in this report.

2.2To delegate authority to the Strategic Director of Resources to award all contracts necessary to deliver the next phase of development at the London Cancer Hub, including demolition and public realm works on site and construction works to convert Cumbrian House into an innovation hub.

2.3To approve the sealing of the Strategic Investment Pot grant agreement between the City of London Corporation and the Council, for the London Cancer Hub award of £8.38m. Agenda Item 8 Page 64

Background

3.1The London Cancer Hub (LCH) is a partnership between the Institute of Cancer Research (ICR) and the London Borough of Sutton (LBS), supported by the Royal Marsden, the Mayor of London, Epsom and St Helier University Hospitals NHS Trust and One Public Estate. The partnership was established to transform Sutton’s existing life-science site into a world-leading campus specialising in cancer research, treatment, education and enterprise.

3.2The fully developed cancer hub has been estimated to contribute c.£1.2bn each year to the UK economy and deliver substantial benefits for the borough. It will create opportunities for sustainable economic growth and local employment in the key STEM (science, technology, engineering and maths) sector. It is expected to create more than 13,000 jobs in total – 7,000 permanent jobs at the Sutton site and 6,200 jobs during construction. It will generate new revenue for the borough, including a projected £13m in additional business rates, and act as a catalyst for broader changes that will benefit Sutton residents, such as local transport improvements.

3.3In 2017 the Council appointed commercial advisors and began to assemble the site for the LCH including the acquisition of a 4.8ha plot of land in 2018. The LCH is a unique project within a specialised sector and it was therefore decided to seek a private sector investor/developer partner to secure the funding and expertise needed to deliver the next phase of development. As a unique scheme, with a mix of commercial development alongside a specific cancer research and drug discovery focus, the Council recognised that there would be a limited number of potential partners with the experience and skills across the full range of requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
London Cancer Hub: Update: ReportReport 182 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 17 attended
RD
Councillor Ruth DombeyChair, present
JM
Councillor Jayne McCoyVice-Chair, present
MA
Councillor Manuel AbellanVice-Chair, present
JB
Councillor Jenny BattCommittee Member, present
SG
Councillor Sunita GordonCommittee Member, present
AH
Councillor Amy HaldaneCommittee Member, present
MJ
Councillor Marian JamesCommittee Member, present
SP
Councillor Steve PenneckCommittee Member, present
MS
Councillor Mo SaqibCommittee Member, present
TC
Councillor Tim CrowleyCommittee Member, present
TD
Councillor Tom DrummondCommittee Member, present
NG
Councillor Neil GarrattCommittee Member, present

All 17 on the meeting page

On this subject at Sutton

Search all
  1. London Cancer Hub - UpdateThis decision
  2. London Cancer Hub UpdateAgreed
  3. APPLICATION NO. DM2025/00336 The London Cancer Hub Cotswold Road Sutton SM2 5NGAgreed
  4. London Cancer Hub Leasehold SaleApproved
  5. Update on the London Cancer HubAgreed
  6. London Cancer Hub Delivery Options AppraisalApproved

More from Sutton Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 MinutesRESOLVED : that the minutes of the meeting held on 16 February 2026 be agreed as an accurate record. Agreed Open
22 Jun 2026 Strategy and Resources Committee: Policy and Strategy OverviewThat the role and remit of the Strategy and Resources Committee as set out in the report be noted. Noted Open
22 Jun 2026 Financial Performance and Outturn 2025/26That the general fund revenue outturn service overspend of £0.46m,which is offset by £2.00m use of contingency and a ... Noted Open
22 Jun 2026 Selection of tenant - Throwley YardThat the grant of a lease for up to 15 years to Bidder A, as identified in the accompanying Appendix A be approved. Approved Open
22 Jun 2026 Electric Vehicle Charging Point (EVCP) ProcurementThat the award of the contract for an electric vehicle charging supplier following the procurement process, be delega... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies