1.1This report presents the 2018-21 Sutton Decentralised Energy Network (SDEN) Business Plan as an annual report to the Sutton Shareholdings Board. The report outlines the strategic plan to provide low-carbon energy to the London Borough of Sutton through the council-owned company, thereby delivering one of the council’s ambitions for the borough.
2.1To approve the Sutton Decentralised Energy Network 2018-21 Business Plan.
3.1Following the London Borough of Sutton’s (the council) decision in July 2014 to establish an Energy Services Company (ESCo), a detailed business model was prepared to demonstrate the commercial viability of the proposed company. The initial business plan was approved by the Opportunity Sutton Ltd Sub-Committee (now the Sutton Shareholdings Board) on 4 August 2015, along with the Shareholder Agreement, enabling Sutton Decentralised Energy Network Limited to be established. Agenda Item 5 Page 10
3.2Since the approval of the original Business Plan at the Opportunity Sutton Ltd Sub-Committee (now the Sutton Shareholdings Board) on 22 February 2016, a revised Business Plan, updating the progress made on Phase 1 and Phase 2 of the network was approved at the Sutton Shareholdings Board on 27 June 2018.
4. Issues
4.1The business plan has been updated, including Section 5 - Financial Plan, which has been updated for the 2019/20 budgeted position.
4.2A report on SDEN’s COVID-19 response is enclosed in Appendix B and includes details of measures adopted to support its customers, including offering circumstance-specific payment plans. SDEN has worked to ensure that eligible residents receive an annual paperless statement discount and/or direct debit discount.
5.1The SDEN Shareholder Agreement stipulates that a business plan should be circulated on an annual basis. An option of ‘not circulating an approved business plan’ would preclude members from exercising the shareholder function on behalf of the council. Therefore, this option has been rejected. Page 11 Agenda Item 5
6. Impacts and Implications
Financial
6.1In July 2013, the Council’s Strategy and Resources Committee (S&R) approved the Conceptual Business Case for the development of a district heating network in Sutton, with funding of £4.5m.
6.2A detailed Financial Model for the Phase 1 Scheme was presented to the Housing, Economy and Business Committee in March 2015. This demonstrated a positive cash flow of £1.54m from delivery of the Scheme.
6.3Now that the construction of the heat infrastructure is reaching completion, and SDEN has nearly two years of operational income and expenditure data, a thorough review of the financial model has been undertaken to review and update the estimated company financial position over the next 25 years. This included an assessment of costs and expenditure, unit numbers and mix in the financial model and resulted in a reduction of the projected cumulative cash flow to £1.14m. This is set out in Appendix A - SDEN Business Plan.
Legal
6.4There are no legal implications. The purpose of this report is to seek approval of the SDEN 2018-21 Business Plan from the Sutton Shareholdings Board as this is a reserved matter under the Shareholders Agreement dated 4 August 2015. Agenda Item 5 Page 12
7. Appendices and Background Documents
Appendix letter Title
A (EXEMPT) Sutton Decentralised Energy Network (SDEN) Ltd Business Plan 2018-21
B SDEN Ltd COVID-19 Response
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
6 REPORT _ SDEN Ltd Business Plan 2020-21 _ SSB 20200630 (1)Report | 134 KB | DownloadRead as text |
PDF |
6A Appendix A _ EXEMPT _ SDEN Business Plan 2020-21 _ SSB 20200630Appendix | 1.4 MB | Download |
PDF |
6B Appendix B _ SDEN Ltd COVID-19 response _ SSB 20200630Appendix | 118 KB | Download |
Follow Sutton Shareholdings Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2026 | MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. | Agreed | Open |
| 10 Mar 2026 | Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... | Approved | Open |
| 10 Mar 2026 | Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... | Noted | Open |
| 10 Mar 2026 | Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThat Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved.... | Approved | Open |
| 4 Nov 2025 | MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.