Resolved
Consideration and comment given on the progress report (item 10 of the agenda). Councillor Nick Mattey joined the meeting at 8.11pm.
Audit and Governance Committee decided this item on Thursday 24 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Consideration and comment given on the progress report (item 10 of the agenda). Councillor Nick Mattey joined the meeting at 8.11pm.
1.1In June 2020, the Audit and Governance Committee agreed to an Annual Audit Plan comprising a total of 640 chargeable days. This report summarises Internal Audit’s progress in delivering the Annual Audit Plan up to August 2020.
2.1To consider and comment on the attached progress report.
3.1The Accounts and Audit Regulations 2015 require an adequate and effective internal audit of accounting records and the system of internal control in accordance with proper practices. This task has been delegated to the responsible finance officer under Section 151 of the Local Government Act 1972. At Sutton, the role of the responsible finance officer is fulfilled by the Strategic Director – Resources and the internal audit requirement is met through the South West London Audit Partnership (SWLAP), which Sutton joined in April 2016.
3.2Internal Audit follows the Public Sector Internal Audit Standards (PSIAS). These standards comprise the public sector interpretation of existing standards set by the Chartered Institute of Internal Auditors. As supplementary guidance, specific to the local government sector, an application note has been issued by CIPFA/IIA; this guidance establishes the requirement for interim reporting [of Internal Audit activity] during the year and the attached report is designed to meet that requirement. Agenda Item 10 Page 62
4. Issues
Internal Audit Progress
4.1The table shown below summarises the planned and actual audit activity during the period in question.
2020/21 Audit Plan Audits Days
Number of audits on the plan 35
Audit Days Delivered * 280
Number of audits at final stage 10
Number of audits at draft stage 1
Number of audits in progress 7
* Audit days on plan 640
4.2At the time of writing this report, 44% of the planned days had been completed at the end of August.
4.310 audit assurance opinions were issued since April 2020, categorised as following:
● 0 (0%) Full Assurance audit opinion ● 9 (90%) Substantial Assurance audit opinions ● 1 (10 %) Limited Assurance audit opinions ● 0 (0%) No Assurance audit opinions. 65 audit recommendations were issued to management, of which: ● 2 (3%) were Priority 1 ● 48 (74%) were Priority 2 ● 15 (23%) were Priority 3
4.4Appendix A includes details of the results of all individual audit assignments that were initiated during the period up to September 2020.
4.5Each audit is given an opinion based on 4 levels of assurance depending on the conclusions reached and the evidence to support those conclusions. Members and management should note that the assurance level is an opinion of controls in operation at the time of the audit. The auditor will agree with management a number of recommendations which, when implemented, will result in a reduction of the exposure to risk. Each recommendation is given a priority ranking and an implementation date and these are monitored on a regular basis by the Internal Audit team. Priority 1 recommendations are those where major issues have been identified for the attention of senior management. Page 63 Agenda Item 10
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(10) Internal Audit Progress Report 2020_21Report | 91 KB | DownloadRead as text |
PDF |
(10a) Appendix A: Internal Audit Assurance OpinionsAppendix | 64 KB | Download |
PDF |
(10b) Appendix B: Follow up on Priority 1 actionsAppendix | 66 KB | Download |
Follow Audit and Governance Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jan 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 23 October 2025 be agreed as an accurate record. The independent member (Audi... | Agreed | Open |
| 15 Jan 2026 | 2024/25 Final Accounts and AuditTo note the 2024/25 Independent Auditors Report (Appendix A), 2024/25 Year End Report (Appendix B) and the 2024/25 Le... | Noted | Open |
| 15 Jan 2026 | Internal Audit Progress ReportTo note the Internal Audit progress report. | Noted | Open |
| 15 Jan 2026 | Operation of the Code of ConductTo note the action taken by the Monitoring Officer in relation to code of conduct complaints. To agree that the Chair... | Noted | Open |
| 15 Jan 2026 | Member Development UpdateTo note the Member Development programme update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.