RESOLVED : 1. The updated Risk Management Strategy and Guidance (Appendix A) be agreed. 2. The Council’s updated risk statement (Appendix B) and updated corporate risk register (Appendix C) as part of the ongoing management of risk across the Authority be noted.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report sets out the annual review of the Council’s risk management strategy and guidance. and provides an overview of the current corporate risk register which has been updated for September 2020.
Recommendations
1.1To agree the updated Risk Management Strategy and Guidance (Appendix A)
1.2To note and comment on the Council’s updated risk statement (Appendix B) and updated corporate risk register (Appendix C) as part of the ongoing management of risk across the authority.
Background
3.1The Council’s risk management strategy and guidance was re-written in 2017 following a review carried out by internal audit of the Council’s procedures and oversight of risk. The strategy and guidance has now been in place since September 2017 and is reviewed annually. Agenda Item 11 Page 72
4. Issues
4.1An annual review of the Council’s Risk Management Strategy and Guidance (appendix A) has been carried out incorporating learning from the last year and minor amends recommended by internal audit.
4.2The overall risk statement (Appendix B) summarises the key risks to the organisation and actions required to mitigate these.
4.3The Corporate Risk Register (Appendix C) has been reviewed and updated to reflect the current key risks being managed by the authority. The register also sets out those inherent risks associated with the running of the local authority. The following changes have been made to the risk register since it was last reviewed by Audit and Governance Committee in January 2020 :-
● Risks where the current risk likelihood has changed
i) Risk: Response to Catastrophic Incident
The current risk likelihood has been reduced due to the detailed plans we have in pace to deal with major incidents
● Risks where the current risk impact has changed
i) Risk: Welfare Reform impact
The current risk impact has been reduced as the original risk was around the implementation of Universal Credit has been rolled out. In addition the resources in the Welfare reform team have increased to meet current levels of demand.
● New Risks
i) Risk: Second Wave of Covid-19
Reason for addition: Risk that LBS will not have adequate infrastructure, resources and plans in place to manage during a potential second wave. Extensive learning from the initial outbreak has meant that the Council is much better prepared for a second wave. Lessons learnt have been captured and plans are being developed for each workstream as part of the response.
ii) Risk: Medium Term Financial Plan / Financial Sustainability
Reason for change: A new risk has been created by combining the risks around financial pressures and increased demand for services. The new risk covers both areas that will impact upon the Council’s MTFP and financial sustainability going forward. Page 73 Agenda Item 11
iii) Risk: HRA Repairs Service
Reason for addition: SHP are bringing in house the response repairs contract for council tenants and leaseholders following Mears giving notice. This is a significant change in how repairs are managed and has inherent risks that could lead to reputational, health and safety, financial, legal and customer service adverse impacts.
● Removed Risk
i) Risk: Fail to deliver requirements on Ofsted WSOA
Reason for removal: In our last inspection the Council passed all three areas and no longer have a written statement of action, the Council will continue to focus on delivering high quality SEND services to children, parents and carers within the borough.
● Risk updated
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingthat the minutes of the meeting held on 23 October 2025 be agreed as an accurate record. The independent member (Audi...
2024/25 Final Accounts and AuditTo note the 2024/25 Independent Auditors Report (Appendix A), 2024/25 Year End Report (Appendix B) and the 2024/25 Le...
Operation of the Code of ConductTo note the action taken by the Monitoring Officer in relation to code of conduct complaints. To agree that the Chair...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.