Throwley Yard - Operator Selection

Agreed Committee 1 paper

Strategy and Resources Committee agreed this item on Monday 14 February 2022. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

That the company listed in exempt Appendix A as the ‘preferred delivery partner’ for the Throwley Yard scheme be appointed and that capital funding of up to £0.975m of Council investment and £1.26m of FHSF funding to deliver the project be confirmed. That the Strategic Director of Resources (Section 151 Officer) be authorised to enter into the legal agreements to contract with the preferred operator to design, construct and operate the scheme.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Strategy and Resources Committee

Summary

1.1In its work to produce the Town Centre Masterplan (2016) and Local Plan (adopted 2018) the Council identified the need to diversify occupiers/uses to create a more culturally viable and sustainable High Street.

1.2The Council identified the opportunity to bid for MHCLG Future High Street Funding (FHSF) to help deliver the Town Centre regeneration and in the case of the Chicago Rock provide funding to regenerate an existing asset. In December 2020 the Council secured £11.35m of FHSF funding for four projects on Sutton High Street. Throwley Yard, formerly known as the Chicago Rock Nightclub, is the first project to be delivered through the funding.

1.3The Throwley Yard regeneration scheme will turn the former defunct Chicago Rock building into a Cultural Hub. The building will house an independent cinema, alongside hospitality uses and a flexible space for a variety of cultural uses. Agenda Item 14 Page 68 Throwley Yard - Operator Selection

1.4In accordance with the bid proposal the Council commenced a selection process to identify a delivery partner. At the outset of the procurement it was expected that the construction element of any bid would be undertaken in-house. However after consideration of the preferred bidder’s offer it became clear that transferring this responsibility to the delivery partner offered the best route to delivery as set out in Appendix A. The delivery partner will be responsible for the design, construction and operation of the Throwley Yard scheme for a minimum of 15 years.

1.5This report seeks approval from the Strategy and Resources Committee to appoint the preferred delivery partner. The selection exercise and outcome, including the preferred delivery partner’s proposal are set out in Appendix A which is restricted, under Paragraph 3, Schedule 12A, of the Local Government Act 1972, as it contains commercially sensitive information.

Recommendations

2.1To agree to appoint the company listed in exempt Appendix A as the ‘preferred delivery partner’ for the Throwley Yard scheme and to confirm capital funding of up to £0.975m of Council investment and £1.26m of FHSF funding to deliver the project.

2.2To authorise the Strategic Director of Resources (Section 151 Officer) to enter into the legal agreements to contract with the preferred operator to design, construct and operate the scheme.

3. Background and Key Information

3.1The Council adopted the Sutton Town Centre Masterplan in 2016, setting out its ambitions for the regeneration of Sutton Town Centre. COVID has exacerbated a situation in which retailers are leaving many High Streets. In Sutton, the Council is seeking to safeguard the vibrancy of the High Street by using purchasing powers, funding and regeneration opportunities to diversify the offer.

3.2Throwley Yard is one of four schemes for which the Council secured funding from the Future High Streets Fund. The scheme submitted for funding was to develop a financially viable Cultural Hub within the former Chicago Rock nightclub, and received £1.42m of FHSF funding. In return the Council committed to investing match funding to deliver the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Throwley Yard: Operator Selection: ReportReport 281 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 19 attended
RD
Councillor Ruth DombeyChair, present
JM
Councillor Jayne McCoyVice-Chair, apologies, sent representative
JB
Councillor Jenny BattCommittee Member, present
SG
Councillor Sunita GordonCommittee Member, present
AH
Councillor Amy HaldaneCommittee Member, present
MJ
Councillor Marian JamesCommittee Member, present
SP
Councillor Steve PenneckCommittee Member, present
BL
Councillor Barry LewisCommittee Member, present
TD
Councillor Tom DrummondCommittee Member, present
NG
Councillor Neil GarrattCommittee Member, present
PN
Councillor Param NandhaCommittee Member, present
JM
Councillor James McDermott-HillCommittee Member, present

All 19 on the meeting page

On this subject at Sutton

Search all
  1. Throwley Yard - Operator SelectionThis decision
  2. Selection of tenant - Throwley YardApproved

More from Sutton Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 MinutesRESOLVED : that the minutes of the meeting held on 16 February 2026 be agreed as an accurate record. Agreed Open
22 Jun 2026 Strategy and Resources Committee: Policy and Strategy OverviewThat the role and remit of the Strategy and Resources Committee as set out in the report be noted. Noted Open
22 Jun 2026 Financial Performance and Outturn 2025/26That the general fund revenue outturn service overspend of £0.46m,which is offset by £2.00m use of contingency and a ... Noted Open
22 Jun 2026 Selection of tenant - Throwley YardThat the grant of a lease for up to 15 years to Bidder A, as identified in the accompanying Appendix A be approved. Approved Open
22 Jun 2026 Electric Vehicle Charging Point (EVCP) ProcurementThat the award of the contract for an electric vehicle charging supplier following the procurement process, be delega... Decided Open