Environment and Sustainable Transport Committee approved this item on Thursday 13 October 2022. Below is the council's own wording, with the papers it was decided on.
To approve the proposed plan and capital investment of £4,085,468 (in addition to the current budget) to complete the column replacement programme, LED rollout and introduction of Central Management System over 4 years, which will be subject to the further approval by the Council’s Strategy and Resources committee when it considers the Council’s proposed capital programme later this year.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Environment and Sustainable Transport Committee
Summary
1.1This report makes a recommendation to drawdown Capital funding on an invest to save basis for the proposed Borough-wide replacement of all non Light Emitting Diode (LED) street Lighting to LED, as well as the installation of a Central Management System (CMS), and to complete the Borough’s Street Lighting Column Replacement Programme.
1.2As part of the Ambitious for Sutton Corporate Plan, Sutton Council is committed to maintaining and improving the physical environment for all residents and visitors. The Council’s highway network is the most visible, used and valuable physical asset for which the Council is responsible and plays a critical role in the economic growth of Sutton. A very important aspect of the highway network is the street lighting which directly impacts on many aspects of social wellbeing including road safety, personal safety and crime. This also ties in with the aim set out under the Being Active Citizens section of Ambitious for Sutton to “invest in transport infrastructure across the borough”.
1.3The proposal requires significant capital funding but in turn brings significant savings in energy and maintenance costs which is particularly relevant at this time of high energy prices. There are also significant carbon savings identified.
2.1To approve the proposed plan and capital investment of £4,085,468 (in addition to the current budget) to complete the column replacement programme, LED rollout and introduction of Central Management System over 4 years, which will be subject to the further approval by the Council’s Strategy and Resources committee when it considers the Council’s proposed capital programme later this year.
3 Background and Key Information
3.1There are currently 15,045 lighting columns in the borough of which 2,994 are still concrete. With regards to the street lights, 8,223 are already LED and 6,822 remain of the old style street lights.
3.2There is currently a rolling programme of £400k per annum in the capital programme to deliver street lighting and column replacement.This report sets out the proposal, costs and savings for completing the column replacement programme, converting old street lights to LED and introducing a Central Management System (CMS).
Concrete Column Replacement
3.3There are a significant number of obsolete concrete columns within the lighting stock in Sutton. Some of these columns are over 40 years old and have an increased risk of failure and risk to public safety. Street Lighting Columns often host a lot of other attachments such as road signs and the concrete columns will not be able to safely carry the additional weight. It is proposed that all concrete columns be replaced with modern steel columns on a 1-for-1 basis. Changing these columns would provide an asset life of at least 30 years for the new infrastructure. The total cost of replacing 2,994 concrete columns is £3,147,959.
3.4The rolling programme of £400k per annum currently in the capital programme has £1.913m for 22-23 to 25-26. It should be noted that delivery was delayed in 2021/22 due to the exceptional circumstances following the pandemic, including its impact on manufacturing and supply of materials. This was reported to the E & ST Committee in March 2022 and funding for 2021/22 has been rolled into the 2022/23 programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Sustainable Transport Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.