Highways Lane Rental - A Proposal to Better Manage Road Works in the Borough
ApprovedCommittee4 papers
AI summarySutton's Environment and Sustainable Transport Committee approved joining Tranche 2 of the London-wide Lane Rental Scheme, expected to generate £484k a year in charges on works promoters, subject to Secretary of State approval.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSutton joins Tranche 2 of the London-wide scheme
Money£484k annuallyExpected charges from works promoters
What happens nextApply to Secretary of StateStrategic Director authorised to progress application
Who it affectsWorks promoters and road usersCharges apply to utilities and the council itself
What was decided
The committee approved the implementation of a Lane Rental Scheme in the borough as part of Tranche 2 of the London Wide Scheme.
Authority to take any necessary future actions on the application was delegated to the Strategic Director of Environment, Housing and Neighbourhoods, in consultation with the committee chair.
The scheme requires approval from the Secretary of State before it can take effect. Report P16, P18
Why
Under the Traffic Management Act 2004 the council has a statutory duty to secure the expeditious movement of traffic on its road network. Report P15
The scheme is expected to raise £484k a year in charges applied to works promoters, including the council itself, based on permitted works last year on the proposed lane rental network. Report P5
Running costs of the scheme, such as additional highways officer inspections, can be met from the charges collected. Report P7
What happens next
Carry out a full consultation with utilities and other works promoters and submit a robust application to the Department for Transport for the Secretary of State's approval. Report P16
Complete a full climate impact assessment ahead of submitting the application and review it if the bid is successful. Report P2
If approved, the scheme will take effect by Order as a Statutory Instrument. Report P18
The money
£484k Expected annual charges from works promoters, including the council Report P5
Options considered
Chosen: Approve implementation of the Lane Rental Scheme as part of Tranche 2 of the London Wide Scheme. Expected to raise £484k a year to fund operation and to reduce congestion and emissions from road works Report P5, P7, P2
Implications
Financial: Surplus funds after costs must be used in line with regulations, with at least 50% expected to be required by government for road maintenance, after consultation with works promoters. Report P8
Financial: Income from the existing permit scheme is expected to fall but would be replaced by lane rental scheme income. Report P11
Financial: If the scheme successfully changes promoter behaviour and reduces disruption, it may generate less income over time. Report P12
Legal: Officers report no legal risks associated with introducing the scheme; the power comes from the Traffic Management Act 2004 and the Street Works (Charges for Occupation of the Highway) (England) Regulations 2012. Report P14, P15
Equalities: The equalities assessment found mostly positive impacts across protected characteristics, with potential for some intersectional benefits. Report P1
Climate: No adverse environmental implications expected, with anticipated benefits including reduced idling emissions, better air quality, more reliable public transport and less congestion; a full climate impact assessment is still to be done. Report P2
Risk: Additional costs to evaluate and operate the scheme are recoverable from the fees received. Report P10
Who and where
Works promoters carrying out street works, including utility companies and the council itself Report P5, P8
Road users and public transport passengers on traffic-sensitive roads in the borough Report P2, P15
Highways inspection staff, with funding expected for additional officers Report P7
Timeline
03/09/2025: Legal consultee response received Report P31
25/09/2025: Equalities Impact Assessment and Climate Impact Assessment responses received Report P32, P33
26/9/2025: Finance consultee response received Report P30
2025-10-09: Committee decision to approve joining Tranche 2 of the London-wide scheme
Plain English for the jargon
Lane Rental Scheme: A scheme under which works promoters pay a daily charge for occupying traffic-sensitive road space during street works, designed to reduce disruption.
Tranche 2: The second phase of rollout of the London-wide Lane Rental Scheme, in which additional boroughs join.
TMA: Traffic Management Act 2004, which gives local highway authorities the duty to secure the expeditious movement of traffic.
DfT: Department for Transport, which issues guidance on Lane Rental Schemes and receives applications for Secretary of State approval.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18
Resolved
To approve the implementation of a Lane Rental Scheme in the Borough, as part of Tranche 2 of the London Wide Scheme. To delegate any necessary future actions required to progress the application to join the London wide lane rental scheme to the Strategic Director of Environment, Housing and Neighbourhoods in consultation with the Chair of the Environment and Sustainable Transport Committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Environment and Sustainable Transport Committee
Page 99 Agenda Item 10 London Lane Rental Scheme - A Proposal to Better Manage Road Works in the Borough
Report Title London Lane Rental Scheme - A Proposal to Better Manage Road Works in the Borough
Committee Environment and Sustainable Transport Committee
Meeting Date 9 October 2025
Chair Councillor Christopher Woolmer
Report From Spencer Palmer, Strategic Director of Environment, Housing and Neighbourhoods
Report Author(s) Sean Kemplay, Highways Operations Team Manager, Transport and Commissioning
Ward(s) Affected All Wards
Ambitious for Sutton Action on climate change priorities An inclusive place for everyone An efficient and well run council
Open/Exempt Open
Signed Date 29/09/2025
1 Summary
1.1 Managing the Council’s highways effectively is vital to the delivery of the council’s Ambitious for Sutton corporate plan priorities, in particular to take action on climate change, make Sutton an inclusive place for everyone and to be an efficient and well run council. The delivery of a lane rental scheme will help ensure the efficient management of the highways for the benefit of residents, road users and businesses alike.
1.2 The objective of the proposed lane rental scheme is to seek to limit the amount of disruption, caused by road works, to the Borough road network by encouraging the undertaking of works at the least disruptive time for road users and encouraging the early completion of work by charging a fee on a daily basis on identified priority roads.
1.3 This report seeks approval to implement the lane rental scheme as part of tranche 2 of the London wide scheme.
Report page 1 Agenda Item 10 Page 100 London Lane Rental Scheme - A Proposal to Better Manage Road Works in the Borough
2 Recommendations
2.1 To approve the implementation of a Lane Rental Scheme in the Borough, as part of Tranche 2 of the London Wide Scheme.
2.2 To delegate any necessary future actions required to progress the application to join the London wide lane rental scheme to the Strategic Director of Environment, Housing and Neighbourhoods in consultation with the Chair of the Environment and Sustainable Transport Committee.
3 Background and Key Information
3.1 The Council as Highway Authority has a statutory Network Management Duty to secure the expeditious movement of traffic on its road network, under the Traffic Management Act 2004 (TMA). The Council is successfully operating a Permit Scheme for works across the Borough, whereby any operator wishing to undertake works on the highway must apply to the council for a permit. This allows the council some control over coordination of works and a flat fee is charged for the permit, irrespective of the duration of the works. However, although existing permit charges can be levied where works are not completed on time, they do not incentivise reduced duration of works or reduced disruption to road users within the duration agreed as part of the permit application.
3.2 Lane Rental is a Department for Transport (DfT) regulated scheme that enables highway authorities to charge works promoters a daily occupancy fee for occupying the highway within the busiest times on the busiest streets. Implementing a Lane Rental Scheme will allow better control of works on traffic sensitive streets, reduce works durations, incentivise efficient work methodologies, and embed behavioural changes within streetworks and roadworks and will help the Council to meet its Network Management Duty by: ● Reducing the length of time taken to carry out the works; ● Improving planning, co-ordination and working methods; ● Identifying and taking forward opportunities for collaborative working with other works promoters; ● Carrying out more works outside of peak times, making greater use of off peak working where the local environmental impact is more acceptable; and ● Completing works to the required standard first time, reducing the need for the works promoter to return to the site to carry out remedial work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Muhammad SadiqCommittee Member, present
LT
Councillor Luke TaylorCommittee Member, present
SA
Councillor Steve AlvarezCommittee Member, present
JM
Councillor James McDermott-HillCommittee Member, present
TS
Councillor Tony ShieldsCommittee Member, present
NM
Councillor Nick MatteyCommittee Member, present
BL
Councillor Barry LewisEx Officio, expected
Hear about the next one first
Follow Environment and Sustainable Transport Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.