Highway and Traffic TfL Funded Programme for 2026/2027
ApprovedCommittee2 papers
AI summarySutton's Environment and Sustainable Transport Committee approved the 2026/27 highways and transport programme, with TfL borough funding projected at about £1,072,000 for road safety, cycling, bus and school travel schemes.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£1,072,000 projectedTfL Safer Corridors and Neighbourhood allocation for 2026/27, same level as 2025/26
What happens nextMayor approval required
Who it affectsSutton road users and schoolsRoad safety, cycling, bus and school travel improvements across the borough
What was decided
The committee approved the highways and transport programme for 2026/27 set out in Appendix A.
Future changes to the 2026/27 programme were delegated to the Strategic Director of Environment, Housing and Neighbourhoods, in consultation with the committee chair.
Why
The Local Implementation Plan is a statutory requirement under section 145 of the Greater London Authority Act 1999, and the Mayor must approve it as consistent with the Mayor's Transport Strategy. Report P11
The programme aims to offer modal choice through cycling, bus and school travel improvements, reducing vehicular travel and associated emissions, alongside road safety work. Report P1, P3
What happens next
The plan must be submitted to the Mayor for approval before it can take effect. Report P11
Funding levels for the Cycle Network Development programme for 2026/27 are still unknown; the borough has submitted proposals covering two key corridors. Report P7
TfL allocates some funding streams on a needs basis, so submitted bids do not guarantee the funding levels received. Report P9
The money
£1,072,000 TfL borough allocation for Safer Corridors and Neighbourhood programme for 2025/2026, with a similar amount projected for 2026/27 Report P6
£872,000 Capital element of the projected 2026/27 Safer Corridors and Neighbourhood funding Report P6
£200,000 Revenue element of the projected 2026/27 funding, covering School Travel planning and cycle training Report P6
Options considered
Chosen: Approve the 2026/27 highways and transport programme at Appendix A and delegate future changes to the Strategic Director. Allows delivery within the statutory LIP process while retaining flexibility for in-year changes Report P11
Implications
Legal: The LIP must be approved by the Mayor as consistent with the Mayor's Transport Strategy before it can take effect; under section 159 of the GLA Act 1999, TfL financial assistance must support safe, integrated, efficient and economic transport in Greater London. No legal risks were identified. Report P11, P12, P13
Financial: TfL funding for some workstreams is allocated on a needs basis, so submitted bids do not guarantee the level of funding actually received. Report P9
Climate: Cycling, bus and area-wide school improvements are designed to reduce vehicular travel and emissions, although road safety elements are expected to have relatively little direct climate impact. Report P1, P3
Equalities: An Equalities Impact Assessment was completed by the Director of Highways, Transport and Regulatory Services on 25/09/2025. Report P26
Who and where
Sutton residents and road users benefiting from road safety and traffic speed measures Report P1, P3
School communities receiving School Travel planning and cycle training Report P6
Cyclists using the two key corridors proposed under the Cycle Network Development programme Report P7
Bus passengers using corridors targeted for bus improvements Report P1, P3
Timeline
03/09/2025: Legal comments provided by Allison Letts, SLLP Report P25
25/09/2025: Equalities Impact Assessment and Climate Impact Assessment completed by the Director of Highways, Transport and Regulatory Services Report P26, P27
26/09/2025: Finance comments provided by the Strategic Director of Resources Report P24
2026/27: Delivery period for the approved highways and transport programme Report P6
Plain English for the jargon
LIP: Local Implementation Plan, the statutory borough transport plan required under section 145 of the GLA Act 1999
TfL: Transport for London, which provides borough funding for transport schemes
MTS: Mayor's Transport Strategy, the framework the LIP must be consistent with
GLA Act 1999: Greater London Authority Act 1999, which sets out the legal basis for the LIP and TfL funding
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
To approve the highways and transport programme for 2026/27 included at Appendix A. To delegate any necessary future actions, which result in a change to the 2026/27 programme as set out in Appendix A, to the Strategic Director of Environment, Housing and Neighbourhoods in consultation with the Chair of the Environment and Sustainable Transport Committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Environment and Sustainable Transport Committee
Page 155 Agenda Item 11 Highways and Transport TfL-Funded Programme for 2026/2027
Report Title Highways and Transport TfL-Funded Programme for 2026/2027
Committee Environment and Sustainable Transport Committee
Meeting Date 9 October 2025
Chair Councillor Christopher Woolmer
Report From Spencer Palmer, Strategic Director, Environment, Housing & Neighbourhoods
Report Author Ian Price, Team Manager Sustainable Transport and Commissioning
Ward(s) Affected All Wards
Ambitious for Sutton Action on climate change priorities An inclusive place for everyone
Open/Exempt Open
Signed Date 26/09/2025
1 Summary
1.1 The highways and transport programmes support the delivery of the council’s Ambitious for Sutton priorities, and in particular to take action on climate change and make Sutton an inclusive place for everyone. There are key ambitions to make it easier for people to make sustainable transport choices, and to keep Sutton a great place to live, enhancing the natural environment by caring for landscapes and wildlife.
1.2 This report sets out the draft programmes to be submitted to Transport for London (TfL) to secure funding. This committee considered a report in January 2025, which outlined a three year programme for the TfL-funded programmes, with the main focus on the delivery year of 2025/2026.
1.3 Appendix D to the January 2025 report included indicative programmes for 2026/2027 and 2027/2028. This report provides an update on the 2026/2027 programme, highlighting any changes, supported by a brief explanation of each scheme element and is seeking approval to submit to TfL.
Report page 1 Agenda Item 11 Page 156 Highways and Transport TfL-Funded Programme for 2026/2027
2 Recommendations
2.1 To approve the highways and transport programme for 2026/27 included at Appendix A.
2.2 To delegate any necessary future actions, which result in a change to the 2026/27 programme as set out in Appendix A, to the Strategic Director of Environment, Housing and Neighbourhoods in consultation with the Chair of the Environment and Sustainable Transport Committee.
3 Background and Key Information
3.1 The TfL-funded programmes are considered and approved by this Committee on an annual basis, and as highlighted above a report on the current three year spending plan was considered and approved by this committee in January 2025. The report included a full programme for the current year’s projects and an outline programme for the following two years in 2026/2027 and 2027/2028.
3.2 This report includes a revised programme for 2026/2027, and highlights where there has been a change to the three year plan.
1. Two schemes have been brought forward from year three (2027/28) of the programme. The schemes are both Safer Schools Projects - Avenue Road school street and the Alma Road/Shorts Road pedestrian improvements, and both meet the TfL scheme requirements for inclusion on the LIP programme. 2. One scheme from the 2026/27 programme has been accelerated and is being delivered in 2025/26 - Seaton House School Crossing. 3. One scheme from the 2026/27 programme has been dropped as the criteria to progress has not been met (not supported by the school) - Greenshaw School Street.
3.3 In previous years the programme of schemes has been taken to the cycle of Local committee meetings prior to approval at the Environment and Sustainable Transport Committee. However, in this instance there is insufficient time to follow this process, TfL contacted all of the boroughs at the end of July asking boroughs to submit their 2026/2027 programmes for year two of the current spending plan, with a submission date of the end of October.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Sustainable Transport Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.