Pension Committee, Tuesday 9 December 2025 at 7.00pm

Pension Administration Projects Update

Noted Finance 2 papers

AI summarySutton Pension Committee noted an update on pension administration projects, including a closure report on the Pension Dashboard Programme, with no financial, legal or climate implications identified.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted pension administration projects update
MoneyNone identifiedNo material financial implications reported
What happens nextPension Dashboard Programme closureAppendix A sets out a project closure report
Who it affectsPension fund administrationPension Committee oversight of administration projects

What was decided

The Pension Committee noted the update on pension administration projects, as set out in the report and its appendices. Report P13

Why

The report records that noting the update carries no material financial implications and no material climate implications. Report P1, P4

Legal and finance consultees confirmed no direct legal implications and no financial or legal risks arise from the recommendation. Report P7, P8, P19, P20

What happens next

No further action is set out beyond noting the update; the Pension Dashboard Programme closure report is included as Appendix A for information. Report P13, P16

Options considered

  • Chosen: Note the update on pension administration projects. Officers and consultees identified no financial, legal, climate or equalities implications Report P1, P4, P7, P23, P24

Implications

  • Financial: No material financial implications and no financial risks arise from noting the update. Report P4, P6
  • Legal: No direct legal implications and no legal risks arise from noting the update. Report P7, P8
  • Climate: No material climate implications arise from the recommendation. Report P1
  • Equalities: No Equalities Impact Assessment was carried out for this update. Report P23

Who and where

  • The Pension Committee, which oversees pension administration at the council Report P9, P13
  • Finance consultees (Director of Finance) who confirmed the position on 13/11/2025 Report P19
  • Legal consultees (Head of Law, Property, Planning and Employment, South London Legal Partnership) who confirmed the position on 10/11/2025 Report P20

Timeline

  • 10/11/2025: Head of Law provided legal comments on the report Report P20
  • 13/11/2025: Director of Finance provided finance comments on the report Report P19
  • 2025-12-09: Pension Committee noted the pension administration projects update

Plain English for the jargon

  • Pension Dashboard Programme: A national initiative connecting pension schemes to a government-backed dashboard, covered here by a project closure report at Appendix A.
  • EQIA: Equalities Impact Assessment, which was not carried out for this update.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item90

Resolved

To note the update.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Pension Committee

Page 15 Agenda Item 7 Pension Administration Projects Update

Report Title Pension Administration Projects Update

Committee Pension Committee

Meeting Date 9 December 2025

Chair Councillor Cryss Mennaceur

Report From Richard Simpson, Strategic Director of Resources

Report Author Victoria Goddard, Director of Finance

Wards Affected Council Business

Ambitious for Sutton An efficient and well run Council priorities

Open/Exempt Open

Signed Date 21 November 2025

1​ Summary​

1.1​ To provide an update on the key administration projects of the Shared Pensions Administration Service.​

2​ Recommendation​

2.1​ To note the update.

3​ Background and Key Information

Pensions Dashboard update

3.1​ The Pensions Dashboard project was completed on time, and the final Project Closure Report from our Integrated Service Provider (ISP) is included in Appendix A.

3.2​ The Fund successfully connected by the guidance staging date of 31 October 2025. This implementation, managed by our chosen provider, Heywood Pension Technologies, was completed £10,517 under budget.

3.3​ The Dashboards Available Point (DAP), when the dashboard will be available to the public, has not yet been confirmed by the Pensions Dashboards Programme. Officers understand the current estimated timeline for this is Autumn 2026.

Report page 1 Agenda Item 7 Page 16 Pension Administration Projects Update

McCloud Remedy update

3.4​ As reported at the Autumn committee, a revised project plan was established with a new target completion date of 30 June 2026, after the Fund missed the statutory implementation deadline.

3.5​ Officers have progressed against this new plan. Communications to all 3,544 in-scope members, explaining the delay and revised timeline, were issued in November 2025.

3.6​ Progress has also been made on the key software dependency. Civica installed an initial McCloud patch on 21 October 2025. A further patch has been announced by the provider, expected to be available from 20 November 2025; Officers are awaiting confirmation of the delivery date for the Fund.

3.7​ In the interim, manual processes remain in place to ensure any member retiring or leaving the scheme has their benefits calculated correctly. The team continues to work through the project plan, and Officers are pleased to report that the project remains on track to meet the 30 June 2026 completion date.

3.8​ The primary risk remains the timely delivery of the final software patches from Civica. This is being actively managed through continuous dialogue with the provider.

Other key updates

3.9​ Pension savings statements (PSS): The Fund is required to issue Pension Savings Statements (PSS) by 6 October each year to any scheme member whose pension growth exceeded the HMRC annual allowance in the previous tax year. Officers can confirm that all required statements for the 2024/2025 tax year were successfully issued to the relevant members ahead of the statutory deadline of 6 October 2025. This provides impacted members with the information they need to declare any potential tax liability to HMRC by 31 January 2026.

3.10​ Overseas Life Certificates: As a safeguard to the Fund, Officers write to overseas pensioners annually asking them to complete and return a life certificate. This measure was introduced following an internal audit recommendation to mitigate against fraudulent payment of pension benefits. The purpose is to ask members to prove they are still entitled to receive payment of their pension benefits and that the address information held is correct. Officers have written to overseas pensioners and the deadline for members to complete and return certificates this year is 31 January 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pension Administration Projects UpdateAppendix A 177 KB Download
PDF
Pension Administration Projects UpdateReport 235 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
CM
Councillor Cryss MennaceurChair, present
SM
Councillor Sam MartinVice-Chair, present
RC
Councillor Richard ChoiCommittee Member, apologies
PC
Councillor Paul ColeCommittee Member, present
JS
Councillor Jake ShortCommittee Member, present
TD
Councillor Tom DrummondCommittee Member, present
PM
Councillor Patrick MagnusCommittee Member, apologies
JR
Jeremy RandallCo-Optee, present
V(
Vacancy (Co-Optee)Co-Optee, expected

On this subject at Sutton

Search all
  1. Pension Administration Projects UpdateThis decision
  2. Pension Administration Performance UpdateNoted
  3. Pension Administration Projects UpdateNoted
  4. Pension Administration Performance UpdateNoted
  5. Pension Administration Projects UpdateNoted
  6. Pension Administration Performance UpdateNoted

More from Sutton Pension Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 17 March 2026 be agreed as an accurate record. Agreed Open
30 Jun 2026 Report on Work of Pension Board 2025-26RESOLVED : 1. To note the report Noted Open
30 Jun 2026 Pension Administration Performance UpdateRESOLVED : 1. To note the update Noted Open
30 Jun 2026 Pension Administration Projects UpdateRESOLVED : 1. To note the update. Noted Open
30 Jun 2026 Governance and Risk UpdateRESOLVED : 1. To note the update. Noted Open