Page 23 Agenda Item 8 Governance and Risk Update
Report Title Governance and Risk Update
Committee Pension Committee
Meeting Date 9 December 2025
Chair Councillor Cryss Mennaceur
Report From Richard Simpson, Strategic Director of Resources
Report Author Victoria Goddard, Director of Finance
Wards Affected Council Business
Ambitious for Sutton An efficient and well run Council priorities
Open/Exempt Open
Signed Date 21 November 2025
1 Summary
1.1 To provide an update on the key governance activities and to review the Fund’s risk register.
2 Recommendation
2.1 To note the update and risk register.
3 Background and Key Information
Review of the Risk Register
3.1 Risk management is the practice of identifying, analysing and controlling in the most effective manner all threats to the achievement of the strategic objectives and operational activities of the Fund. It is not a process for avoiding or eliminating risks. A certain level of risk is inevitable in achieving the Fund objectives, but it must be controlled.
3.2 The Risk Register overview report is included as Appendix A. All risks have been categorised under one of three main themes - Administration, Funding and Investments, and Governance. Each individual risk is assessed as red (high risk), amber (medium risk) or green (low risk) and these are summarised into an overall rating for that group. As at the time of writing this report the Administration risks are rated amber overall, with one
Report page 1 Agenda Item 8 Page 24 Governance and Risk Update
red and two amber risks. Both the Funding and Investments group and Governance group are rated green. This is summarised in the table below.
Risk Category Direction Overall Ratings of Individual Risks of Travel Rating
Administration ⬌ AMBER
Funding & ⬌ GREEN Investments
Governance ⬌ GREEN
3.3 Officers have continued to maintain and review the full Risk Register to ensure all appropriate risks and mitigations have been identified for each individual risk. There is currently one red rated risk to bring to the Committee’s attention:
■ Risk 27 (Administration) - Failure by software provider (Civica) to provide software compliant with LGPS Regulations. Officers have reviewed this risk and, despite some recent progress, recommend its red rating remains unchanged. As noted in the Pension Administration Projects Update, Civica has delivered initial software patches to address the McCloud Remedy; however, outstanding issues with the software remain, and further patches are still expected. The core risk is that until a fully compliant and tested solution is delivered, the Fund lacks a guaranteed operational
Report page 2 Page 25 Agenda Item 8 Governance and Risk Update
system compliant with LGPS regulations, which could lead to the incorrect payment of member benefits. Therefore, the view of Officers is that this risk must remain red until fully compliant software is received and verified. Mitigations remain in place, with Officers addressing issues directly with Civica's client manager and working closely with the national Civica Client User Group to apply collective pressure for a timely resolution.
3.4 Officers have also reviewed the existing 5 amber risks and summarise these as follows:
■ Risk 1 (Administration) - Incomplete or inaccurate member data. The risk of holding incomplete or inaccurate member data remains a key focus. This could lead to the incorrect payment of benefits, non-compliance with regulations, and member complaints. To mitigate this, Officers continue to implement the Fund's Data Improvement Plan through ongoing validation and employer engagement. As anticipated in the Autumn report, the Fund's annual scheme return has been received from the Pensions Regulator (tPR). Officers are processing this return and will ensure it is submitted by the 3 December 2025 deadline. The risk rating remains amber and will be carefully reviewed following the completion of the scheme return.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8. Governance and Risk Update (R) _ Pension Committee _ 20251209Report | 441 KB | DownloadRead as text |
PDF |
Governance & Risk UpdateAppendix A | 224 KB | Download |
Follow Pension Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 17 March 2026 be agreed as an accurate record. | Agreed | Open |
| 30 Jun 2026 | Report on Work of Pension Board 2025-26RESOLVED : 1. To note the report | Noted | Open |
| 30 Jun 2026 | Pension Administration Performance UpdateRESOLVED : 1. To note the update | Noted | Open |
| 30 Jun 2026 | Pension Administration Projects UpdateRESOLVED : 1. To note the update. | Noted | Open |
| 30 Jun 2026 | Governance and Risk UpdateRESOLVED : 1. To note the update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.