Resolved
That an increase to the Belmont LUF Rail Project’s capital budget of £3.98 million be approved.
AI summarySutton Council approves £3.98 million extra for Belmont Station rail upgrade to keep December 2027 opening on track.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That an increase to the Belmont LUF Rail Project’s capital budget of £3.98 million be approved.
Page 13 Agenda Item 12 Belmont Station Rail Enhancement project - additional funding approval
_
Report Title Belmont Station Rail Enhancement project - additional funding approval
Committee Strategy and Resources Committee
Meeting Date 22 June 2026
Chair Councillor Barry Lewis, Leader of the Council
Report From Spencer Palmer, Strategic Director Environment Housing and Neighbourhoods
Report Author(s) Sarah Rye Director of Highways, Transportation and Regulatory Services
Ward(s) Affected Sutton South and Belmont Ward
Ambitious for Sutton Action on climate change priorities An inclusive place for everyone Strong and fair economic growth Campaign for quality local services
Open/Exempt Open
Signed Date 19 June 2026
1 Summary
1.1 This report relates to the Belmont Station rail enhancement project, backed by the Levelling Up Fund, which will double train frequencies to Belmont and support the London Cancer Hub. Delivery of this rail enhancement is a specific action under campaign for quality local services as part of the Ambitious for Sutton corporate plan. This scheme would also support delivery of action on climate change; an inclusive place for everyone; and strong and fair economic growth.
1.2 It has recently come to light that, due mainly to geopolitical inflationary pressures, the project faces a significant funding gap of £3.98 million. Options have been considered and this report seeks approval for the Council to provide funding to meet the gap, to secure a December 2027 delivery and mitigating the risk of further cost escalations or the potential failure to deliver the scheme. A lobbying strategy will be initiated to seek match funding and reduce the financial burden on the council.
1.3 This report is presented as a late and urgent item in accordance with S100B(4) of the Local Government Act 1972. The need for an urgent decision has arisen because of the
Report page 1 Agenda Item 12 Page 14 Belmont Station Rail Enhancement project - additional funding approval
late confirmation of the total cost increase and because of the significant risk of further cost increases if the project is delayed.
2 Recommendations
2.1 To approve an increase to the Belmont LUF Rail Project’s capital budget of £3.98 million.
Background and Key Information
2.2 The Belmont Station rail enhancement project is backed by the former UK Government's Levelling Up Fund. Designed to support the growing London Cancer Hub, the scheme will double train frequencies from 2 to 4 trains per hour to Belmont station.
2.3 Key Project Details ● Project Goal: Increase capacity and improve local transit access for commuters and patients. ● Core Infrastructure: Extension of the station platform to allow for 10 car trains and associated signals work. ● Station Upgrades: The project will introduce step-free access to the platform, improved lighting, and enhanced signage. ● Active Travel: Updates include new walking and cycling connections between the station and the London Cancer Hub.
2.4 The Council is responsible for the design and implementation of the active travel elements of the scheme, many of which are complete. Network Rail is responsible for the design and delivery of the rail enhancements.
2.5 The Council is responsible for the overall project management and meeting the cost of the project. The Council approved the scheme at the S&R committee on 19th June 2023.
2.6 The approved programme budget is £15.912m which combines the initial £14.1 million Levelling Up Fund grant with other grants. The scheme is currently nearing the end of the detailed design and contractor estimates in advance of the construction phase. The Anticipated Final Cost (AFC) now exceeds the available funding.
2.7 The AFC projected worst-case deficit is £3.98 million keeping to the current delivery timetable of December 2027.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Belmont Station Rail Enhancement project: additional fundingReport | 239 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | MinutesRESOLVED : that the minutes of the meeting held on 16 February 2026 be agreed as an accurate record. | Agreed | Open |
| 22 Jun 2026 | Strategy and Resources Committee: Policy and Strategy OverviewThat the role and remit of the Strategy and Resources Committee as set out in the report be noted. | Noted | Open |
| 22 Jun 2026 | Financial Performance and Outturn 2025/26That the general fund revenue outturn service overspend of £0.46m,which is offset by £2.00m use of contingency and a ... | Noted | Open |
| 22 Jun 2026 | Selection of tenant - Throwley YardThat the grant of a lease for up to 15 years to Bidder A, as identified in the accompanying Appendix A be approved. | Approved | Open |
| 22 Jun 2026 | Electric Vehicle Charging Point (EVCP) ProcurementThat the award of the contract for an electric vehicle charging supplier following the procurement process, be delega... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.