(1) That delegated authority be granted to the Head of Planning, in consultation with the Head of Mid Kent Legal Services, to progress a suitable indemnity agreement(s) with the owners of land outlined in red on the plan attached to the agenda, in order that the Council can ultimately progress to compulsorily acquire the land pursuant to section 226(1)(b) of the Town and Country Planning Act 1990. (2) That confirmation of the CPO, including the associated back-to-back indemnity agreement with prospective developer(s), be reported back to the Cabinet for decision.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Report Title Crown Quay Lane Compulsory Purchase Order
Cabinet Member Cllr Gerry Lewin, Cabinet Member for Planning
SMT Lead Emma Wiggins, Interim Director of Regeneration
Head of Service James Freeman
Lead Officer James Freeman
Key Decision No
Classification Open
Forward Plan Reference number:
Recommendations 1. That Members grant delegated authority to the Head of Planning, in consultation with the Head of Mid Kent Legal Services, to progress a suitable indemnity agreement(s) with the owners of land outlined in red on the attached plan, in order that the Council can ultimately progress to compulsorily acquire the land pursuant to section 226(1)(b) of the Town and Country Planning Act 1990; and 2. The confirmation of the CPO, including the associated back-to-back indemnity agreement with prospective developer(s), be reported back to the Cabinet for decision.
1 Purpose of Report and Executive Summary
1.1This report seeks Members’ ‘minded to’ decision to compulsorily acquire land at Crown Quay Lane, Sittingbourne, subject to suitable back-to-back indemnity agreements being entered into, to enable it to be comprehensively developed in accordance with Policy A9 of the emerging Swale Local Plan. Any final decision to serve a Compulsory Purchase Order (CPO) would come back to the Cabinet for agreement.
1.2The land is in multiple ownership, and without intervention by the Council it is considered unlikely that a comprehensive development will come forward in the foreseeable future. 2. Background 2.1 This report is concerned with Land at Crown Quay Lane, Sittingbourne, which is allocated for residential development – Policy A9 of the emerging Local Plan currently subject to a Local Plan Examination. The site Allocation is 18.2 ha, and provides for a minimum of 650 dwellings, open space and habitat creation.
2.2A major component of the allocation is to create public access to the Creekside and to enhance connectivity between the site and the northern bank of the Creek by providing a footbridge link to the Saxon Shore Way footpath. The development would also be required to contribute financially to education, library, social services and health facilities.
2.3The allocated site is integral to meeting the housing needs of the Borough, and for contributing towards the five-year housing land supply. The principle of the development of the site was agreed by the Local Plan inspector in her Interim Report to the emerging Local Plan. Whilst the Plan is subject to further main modifications, the Inspector does not expect to discuss the principle of the sites allocation within the Plan.
2.4In order to achieve all the planning components for the site, it was anticipated that a planning application covering the whole site would be submitted to ensure, either through direct works related to the site or through planning obligations, a comprehensive approach to infrastructure provision. The planning application would be expected to accord with an agreed development brief for the site, as required by the Policy.
The site 2.5 Appendix I attached sets out the emerging Local Plan allocation site and associated development concepts, and Appendix II sets out the various land owners within the allocation.
2.6The allocation site as a whole extends to roughly 18.4ha (measuring a maximum of approximately 510m wide W-E by 530m N-S) and sits to the north of Eurolink Way, west of the Eurolink industrial estate, east of the existing Sittingbourne retail park, and south of Milton Creek. Land levels change dramatically from Eurolink Way down to the site, with a step of roughly 10m at the western end, gradually reducing to the east as Eurolink Way slopes down eastwards towards the roundabout. From this point onwards the allocation site is generally flat.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.