Sittingbourne Town Centre Regeneration Project - variations to the development agreement
AgreedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 1 February 2017. Below is the council's own wording, with the papers it was decided on.
(1) That delegated authority be given to the Interim Director of Regeneration, in consultation with the Leader and the Cabinet Member for Regeneration to agree a Third Deed of Variation to the Development Agreement to: (i) amend the Developer’s Phase 1 Conditions; (ii) remove the Council’s obligation to pay section 106 costs; (iii) remove the Council’s obligation to pay a contribution from the multi-storey car park budget; (iv) allow the Developer to vary the Developer’s minimum percentage profit margin; (v) allow for construction works to elements funded by the Council to be carried out under an access licence rather than a building lease.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1The Council’s corporate priority for the regeneration of Sittingbourne is to deliver the highway works, cinema, restaurants and retail units. Significant work has been undertaken to ensure that these are viable and fully funded and ready to be built out, subject to the Development Agreement (DA) between the Council and Spirit of Sittingbourne going unconditional.
2.2The DA contains a number of conditions that have to be satisfied in order that it can go unconditional. Substantial progress has been made in meeting the conditions of the current DA for Phase 1 of the project. Phase 1 incorporates the Big Box retail, Leisure (cinema, Travelodge, MSCP, public realm) and residential. However, some conditions which are not capable of being performed under the DA as it is currently drafted are delaying the DA going unconditional and hence work starting on site.
2.3In terms of progress made, planning consent has been granted at Committee for the whole of Phase 1, and two additional planning permissions for a hotel and the retail park. Final determination of planning matters is imminent, subject to signing of the section 106 agreement that is now agreed by all parties.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.