Sittingbourne Town Centre Regeneration Project - variations to the development agreement

Agreed Executive 1 paper

Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 1 February 2017. Below is the council's own wording, with the papers it was decided on.

Item1164

Resolved

(1) That delegated authority be given to the Interim Director of Regeneration, in consultation with the Leader and the Cabinet Member for Regeneration to agree a Third Deed of Variation to the Development Agreement to: (i) amend the Developer’s Phase 1 Conditions; (ii) remove the Council’s obligation to pay section 106 costs; (iii) remove the Council’s obligation to pay a contribution from the multi-storey car park budget; (iv) allow the Developer to vary the Developer’s minimum percentage profit margin; (v) allow for construction works to elements funded by the Council to be carried out under an access licence rather than a building lease.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Cabinet - Decommissioned 18.05.2022

Background

2.1The Council’s corporate priority for the regeneration of Sittingbourne is to deliver the highway works, cinema, restaurants and retail units. Significant work has been undertaken to ensure that these are viable and fully funded and ready to be built out, subject to the Development Agreement (DA) between the Council and Spirit of Sittingbourne going unconditional.

2.2The DA contains a number of conditions that have to be satisfied in order that it can go unconditional. Substantial progress has been made in meeting the conditions of the current DA for Phase 1 of the project. Phase 1 incorporates the Big Box retail, Leisure (cinema, Travelodge, MSCP, public realm) and residential. However, some conditions which are not capable of being performed under the DA as it is currently drafted are delaying the DA going unconditional and hence work starting on site.

2.3In terms of progress made, planning consent has been granted at Committee for the whole of Phase 1, and two additional planning permissions for a hotel and the retail park. Final determination of planning matters is imminent, subject to signing of the section 106 agreement that is now agreed by all parties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sittingbourne Town Centre Regeneration Project: variations to the development agreementReport 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 27 attended
AB
Andy BoothVisiting Councillor, in attendance
AB
Councillor Andrew BowlesChair, present
MC
Councillor Mike CosgroveCommittee Member, present
DD
Councillor Duncan Dewar-WhalleyCommittee Member, present
PF
Councillor Paul FlemingVisiting Councillor, in attendance
JF
James FreemanOfficer, in attendance
MG
Martin GoodhewOfficer, in attendance
VH
Victoria HadfieldOfficer, in attendance
NH
Nicholas HampshireGuest, in attendance
MH
Councillor Mike HendersonGuest, in attendance
AH
Councillor Alan HortonCommittee Member, apologies
JH
James HuntVisiting Councillor, in attendance

All 27 on the meeting page

On this subject at Swale

Search all
  1. Sittingbourne Town Centre Regeneration Project - variations to the development agreementThis decision
  2. Sittingbourne Town Centre UpdateNoted
  3. Sittingbourne Town Centre Regeneration UpdateNoted
  4. Sittingbourne Town Centre UpdateNoted
  5. Sittingbourne Town Centre Update ReportNoted
  6. Sittingbourne Town Centre Regeneration UpdateNoted

More from Swale Cabinet - Decommissioned 18.05.2022

All decisions
MeetingDecisionOutcome
13 Apr 2022 Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I... Noted Open
13 Apr 2022 Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro... Noted Open
13 Apr 2022 Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ... Agreed Open
13 Apr 2022 Beam Partnership - Housing and Employment Support(1) That a spend and save pilot in partnership with Beam be entered into. Decided Open
13 Apr 2022 Project Funding(1) That the schemes funded from the Improvement & Resilience Fund, the Special Projects Fund and the High Street Fun... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies