Resolved
(1) That the report be noted.
Swale Joint Transportation Board noted this item on Monday 17 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted.
To: Swale Joint Transportation Board
By: KCC Highways and Transportation
Date: 17th December 2018
Subject: Highway Works Programme 2018/19
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2018/19
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2018/19
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Traffic Systems – see Appendix D
Developer Funded Works – see Appendix E
Transportation and Safety Schemes – see Appendix F
Public Rights of Way – see Appendix G
Bridge Works – see Appendix H
Member Highway Fund – see Appendix I
Pothole Blitz – see Appendix J
Conclusion
1. This report is for Members information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager (Mid) Alan Blackburn Swale District Manager Alan Casson Road & Footway Asset Manager Earl Bourner Drainage and Structures Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Andrew Hutchinson Transportation, PROW and Safety Schemes Nick Abrahams Economic Development Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
To be reviewed once A2 St Michael’s Rd Sittingbourne Forum to Crown Quay Lane Spirit of Sittingbourne works are complete Millennium Way to junction with To be programmed early A250 High St Sheerness Victoria Street 2019
A250 Millennium 50m each approach to High To be programmed early Sheerness Way Street 2019 The Billet PH for a distance of To be programmed early A2 London Road Sittingbourne 100m easterly towards 2019 Sittingbourne Town Centre Between Adelaide Drive and To be programmed early A2 London Road Sittingbourne Lydbrook Close 2019
Footway Improvement - Contact Officer Neil Tree
Extent and Description of Road Name Parish Current Status Works
From No. 51 to Priory Row only. Reedland Crescent Faversham Completed (Footway Protection Treatment)
Surface Treatments - Contact Officer Clive Lambourne
Micro Surfacing
Road Name Parish Extent of Works Current Status
The Street Oare Oare Road to Cole Gates Road Completed
Selling Road Selling Monica Close to Sondes Court Completed
Between Kettle Hill Road and Otterden Road Eastling Completed Kettle Hill Road (Eastling) Extents Through junction to Halstow Lane Upchurch Completed Twinney Lane
From Grove Road to Selling Perry Wood Selling Completed Road
Between Napleton Road and South Road Faversham Completed Bridge Road
From Stockers Hill to Bottles Cheney Hill Rodmersham Completed Lane
From Belnor Avenue to Stickfast Parsonage Lane Bobbing Completed Lane
Hartlip M2 bridge to Old House Lane Completed Bull Lane
Postponed until 2019 Bank Street Faversham Whole Length
Surface Treatments - Contact Officer Clive Lambourne
Surface Dressing
Road Name Parish Extent of Works Current Status
New House Lane to Salters Ashford Road Sheldwich Completed Lane Whitstable Road (& Graveney Graveney Whole Length Completed Road) Bagshill Road to Shottenden Ashford Road Badlesmere Completed Road
School Lane Borden Whole Length Completed
Vicarage Lane to Crouch Selling Road Selling Completed Lane
Minister on Plough Road Whole Length Completed Sea Appendix B – Drainage Repairs & Improvements
Drainage Repairs & Improvements - Contact Officer Earl Bourner
Road Name Parish Description of Works Current Status Re-shape driveway, cleanse the Committed passed to Tunstall Swale system. Install new gullies at the contractor December school Road junction with Woodstock road break
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Work ProgrammeReport | 128 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.