To: Swale Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 24th June 2019
Subject: Highway Forward Works Programme – 2019/20 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Integrated Transport Schemes Externally Funded Schemes
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion 1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent Alan Blackburn Swale District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
To be reviewed once Spirit of Forum to Crown A2 St Michael’s Rd Sittingbourne Sittingbourne Quay Lane works are completed Millennium Way to To be A250 High St Sheerness junction with programmed Victoria Street November 2019 To be 50m each approach A250 Millennium Way Sheerness programmed to High Street November 2019 The Billet PH for a distance of 100m To be A2 London Road Sittingbourne easterly towards programmed Sittingbourne Town November 2019 Centre Between Adelaide To be A2 London Road Sittingbourne Drive and Lydbrook programmed Close November 2019 To be Junction with Stone Bank Street Faversham programmed Street to car park November 2019 To be Bus layby to A2 High Street Newington programmed Church Lane November 2019 Full length of To be Sittingbourne High High Street Sittingbourne programmed Street and Central early 2020 Avenue
Footway Improvement - Contact Officer Neil Tree
Extent and Road Name Parish Description of Current Status Works Entire length. Wickham Close Newington (Footway Protection Completed Treatment) Exact sections to In Design be determined. New Road Sheerness To be (Footway programmed Reconstruction) Tonge Road to Great East Hall To be designed Oak Road Sittingbourne road. and (Footway programmed Reconstruction)
Exact sections to be determined. To be designed Broom Road Sittingbourne (Footway and Reconstruction) programmed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Work ProgrammeReport | 136 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.