Highways Work Programme

Noted Committee 1 paper

Swale Joint Transportation Board noted this item on Monday 13 January 2020. Below is the council's own wording, with the papers it was decided on.

Item443

Resolved

(1) That the report be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Swale Joint Transportation Board

To: Swale Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 13th January 2020

Subject: Highway Forward Works Programme – 2019/20 onwards

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2019/20.

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D  Casualty Reduction Measures  Externally funded schemes  Local Growth Fund

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

PROW – see Appendix H

Combined Member Fund – see Appendix I Conclusion

1. This report is for Members’ information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Kirstie Williams Highway Manager Mid Kent Alan Blackburn Swale District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer Byron Lovell

Current Road Name Parish Extent of Works Status Full length of Sittingbourne High High Street Sittingbourne Completed Street and Central Avenue Forum to Crown Quay A2 St Michael’s Rd Sittingbourne Completed Lane Rescheduled due to 50m each approach to A250 Millennium Way Sheerness weather. High Street Programmed 9th April 2020 North of High Street A250 Bridge Road Sheerness Completed Junction Rescheduled The Billet PH for a due to distance of 100m weather. A2 London Road Sittingbourne easterly towards Programmed Sittingbourne Town 14th April Centre 2020 Junction with Stone Bank Street Faversham Completed Street to car park Rescheduled due to Millennium Way to weather. A250 High St Sheerness junction with Victoria Programmed Street 15th April 2020 A250 Halfway Programmed A250 Halfway Road Minster Road/B2008 Minster 8th April 2020 Junction Postponed Bus layby to Church A2 High Street Newington due to gas Lane works

Footway Improvement - Contact Officer Neil Tree

Extent and Current Road Name Parish Description of Works Status Exact sections to be determined. Currently on New Road Sheerness (Footway site Reconstruction)

Tonge Road to Great To be Oak Road Sittingbourne East Hall road. designed (Footway and Reconstruction) programmed

Exact sections to be To be determined. Broom Road Sittingbourne designed (Footway and Reconstruction) programmed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Work ProgrammeReport 143 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 30 attended
MB
Councillor Mike BaldockCommittee Member, present
CA
Cameron Andrew BeartParish Councillor, present
AB
Alan BlackburnOfficer, in attendance
AB
Mr Andy BoothKent County Councillor, present
AB
Mr Andrew BowlesVice-Chair, present
SC
Councillor Simon ClarkCommittee Member, apologies, sent representative
JC
Mr Jason Clinch - please see Kent County Council websiteKent County Councillor, present
SD
Steve DaveyVisiting Councillor, in attendance
MD
Mike DendorVisiting Councillor, in attendance
TG
Tim GibsonVisiting Councillor, in attendance
AG
Councillor Alastair GouldCommittee Member, present
JH
James HallVisiting Councillor, in attendance

All 30 on the meeting page

On this subject at Swale

Search all
  1. Highways Work ProgrammeThis decision
  2. Highways Work ProgrammeNoted
  3. Highways Work ProgrammeNoted
  4. Highways Work ProgrammeNoted
  5. Verbal update from National Highways on the M2 Junction 5 Stockbury WorksNoted
  6. Highways Work ProgrammeNoted

More from Swale Swale Joint Transportation Board

All decisions
MeetingDecisionOutcome
29 Jun 2026 Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... Decided Open
29 Jun 2026 Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. Noted Open
6 Oct 2025 Highways Work Programme(1) That the report be noted. Noted Open
6 Oct 2025 Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. Noted Open
30 Jun 2025 Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. Noted Open