To: Swale Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 7th September 2020
Subject: Highway Forward Works Programme – 2020/21 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2020/21 and 2021/22) and Year Three to Five (2022/23 to 2024/25) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2020/21, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
PROW- see Appendix H
Combined Member Fund – see Appendix I Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent Alan Blackburn Swale District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
Junction with Murston Programmed 17th A2 Canterbury Road Minster Road and Vincent September 2020 Road From the Billet Pub for a distance of 100m east towards Programmed 24th A2 London Road Sittingbourne Sittingbourne Town August 2020 Centre / Between Adelaide Drive and Lydbrook Close Norton, Buckland and To be completed A2 London Road Norton Crossroads Stone early 2021
From Laxton Way to To be completed Quinton/Vicarage Road Sittingbourne Knightsfield Road early 2021
From Victoria street to To be completed High Street Sheerness Bridge early 2021
Footway Improvement - Contact Officer Neil Tree
Extent and Road Name Parish Current Status Description of Works
Exact section to be determined. Eagles Close Sittingbourne Completed. (Footway Reconstruction)
Tonge Road to Great Works East Hall road. programmed to Oak Road Sittingbourne (Footway start on 24th Reconstruction) August 2020
Exact sections to be Works Broom Road Sittingbourne determined. programmed to (Footway start on 21st Reconstruction) September 2020
Full length (Including Linden Drive). Designed and to Queens Way (Phase 1) Sheerness (Footway be programmed. Reconstruction)
Entire Length Programmed to River View Queenborough (Footway Protection be completed in Treatment) August 2020.
Entire Length Programmed to Wellington Road Sittingbourne (Footway Protection be completed in Treatment) August 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Work ProgrammeReport | 206 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.