Levelling Up Fund Sheerness Revival
Sheppey Area Committee Meeting 20th February 2024
Sheerness Revival Levelling Up Project Update
Comms:
Work on a LUF specific website is nearing completion that will host updates concerning each of the 3 projects along with partner information and a subscription for newsletters. A Facebook page has also been created to allow updates to be shared via a social media channel. External partners have been asked to sign post to both the website and Facebook to ensure that residents have the most up to date and relevant information regarding the projects.
The design teams for the 3 projects are currently pulling together ways in which they can support the local community during the delivery of the projects. This includes ways in which stakeholders can be included, along with work experience opportunities.
SBC’s Officers and EKC’s delivery and comms team continue to work collaboratively to ensure the most relevant and up to date information is shared.
Project 1: Beachfields:
The initial design team meeting and site visit took place on 21 st September 2023 and since then the design team have been focused on developing the RIBA Stage 2 concept design.
The design team have now developed design options which included alternative layouts and revised entrance positions to the centre from that submitted at bid stage. These were presented to the current occupiers of the building during week commencing 15 th January 2024 for their initial comments. Layout modifications are still ongoing based on stakeholder and member feedback. Further consultation will take place as plans develop and progress to allow for member (both SBC and STC) and resident feedback. Opportunities for engagement will also take place when designing the outside landscaping and new activities being introduced to the site.
Willmott Dixon have now completed a series of building and site surveys to better inform the designers regarding the current conditions of the site. These commenced on 27 th November 2023 and concluded on week commencing 27th January 2024. Levelling Up Fund Sheerness Revival
The design team are planning to submit the pre-application report to the planning team towards the end of February.
A revised programme has now been received from Willmott Dixon. The current programme shows construction starting in autumn / winter 2024 and completing in winter 2025.
Project 2: Sheppey College:
EKC continue to work with Architects (Lee Evans Partnership) and Project Managers/Quantity Surveyors (MGAC). The RIBA Stage 2 drawings and cost plan have been completed and shared with EKC’s internal governance Property Committee, the Sheppey College Local Board. The Architects and SBC had the pre-application planning meeting on 16th October and the report was received back from SBC during week commencing 13th November 2023.
RIBA Stage 3 designs are now underway with a slight amendment to the plans being necessary in late December to ensure sufficient space around the building for vehicle movements. EKC are working towards submitting the planning application in February 2024 following the member and public consultation event that took place on 5th and 6th February 2024.
Development of the tender for works has begun and EKC has now shortlisted four contractors to tender for the main works.
EKC are currently reporting that the works will be completed by June 2025 so that the fit out and recruitment can take place ahead of the provision that opens in September 2025.
Project 3: Masters House:
Consultants ig9 were appointed and contracted on 28th September 2023 to provide Project Management, Quantity Surveying and Employers Agent Services for the Phase 2 works at Masters House. As of 15th January 2024, ig9 has now also agreed to carry out the Principal Designer role for the project at no additional cost.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sheerness Revival Project updateReport | 165 KB | DownloadRead as text |
Follow Sheppey Area Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Feb 2026 | Matters arising from previous meetingsIt was agreed to refer this matter to the Chair of the Environmental Services and Climate Change Committee for consid... | Agreed | Open |
| 3 Feb 2026 | Matters referred to Service Committee Chairs for considerationIt was agreed to refer the following matters to the relevant Service Committee Chairs for consideration: · The instal... | Agreed | Open |
| 2 Dec 2025 | Matters arising from previous meetingsIt was agreed that representatives from the following organisations be invited to a future Sheppey Area Committee mee... | Agreed | Open |
| 18 Sep 2025 | Public Forum1) That a representative from the National Health Service be invited to a future Sheppey Area Committee meeting to re... | Decided | Open |
| 18 Sep 2025 | Isle of Sheppey Growth Board1) That the Sheppey Area Committee referred the proposal to set up a Sheppey Growth Board to the Economy and Property... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.