1) That the Sheppey Area Committee take on responsibility for agreeing and implementing any future discretionary changes to the illumination schedule. The Area Committee delegated the decisions on scheduling to the Director of Regeneration & Neighbourhoods.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1Sheerness Clock Tower was fully restored between 2021 and 2022, following the commitment of funds from Swale Borough Council’s (SBC) High Streets Fund.
2.2As part of these works, a coloured illumination schedule was introduced for the uplighters. Following internal SBC research and consideration, the schedule was set as per the attached Appendix I. Illumination takes place from half an hour before dusk through until midnight.
2.3Reprogramming the uplighter schedule requires input from the installation contractor, either via on-site attendance, or via remote programming support (with an officer on-site to upload changes).
2.4Given that this incurs costs, it was foreseen that the schedule would not be changed.
2.5Following the passing of the Queen Elizabeth II, the illumination will, however, need to be reprogrammed to no longer mark her official birthday and instead to mark King Charles’ birthday. This presents the opportunity to review whether other changes to the scheduling would be welcome.
2.6This reprogramming will be funded by SBC. 3 Proposal
3.1Sheppey Area Committee is invited to discuss and agree the updated static schedule of illumination of the Sheerness Clock Tower.
3.2These changes will need to be agreed in good time to align with the removal of the scheduling of the late Queen’s birthday illumination, and for the King’s birthday illumination to be programmed – i.e. latter part of May at the latest.
3.3Sheppey Area Committee is invited to take on responsibility for agreeing and implementing any future discretionary changes to the illumination schedule (noting that this will come at a cost).
Alternative options
4.1The illumination could be switched off, either now or if any of the future uplighting schedule becomes obsolete. This is not recommended, as this is a welcome feature of the refurbished Clock Tower.
4.2Reprogramming could potentially be undertaken independent of the installer’s support. This is not recommended, as this is a technical exercise, with potential reputational ramifications if the schedule is not delivered correctly. There is no identified in-house expertise within SBC to undertake the work.
4.3Agreement could be reached not to change the illumination schedule at any point other than when necessitated by external circumstance.
5 Consultation Undertaken 5.1 The initial uplighting schedule was determined following internal SBC consideration, and review of the lighting schedule of comparator landmarks across the county.
5.2These proposals have been considered by members of the administration.
6 Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Matters arising from previous meetingsIt was agreed to refer this matter to the Chair of the Environmental Services and Climate Change Committee for consid...
Matters arising from previous meetingsIt was agreed that representatives from the following organisations be invited to a future Sheppey Area Committee mee...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.