CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Policy and Resources Committee, Wednesday 10 September 2025 at 7.00pm

New and Amended Fees for Applications made to the Planning Service

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.

Item294

Resolved

(1) That the introduction of charges for amendment to undetermined applications in accordance with the fee schedule as set out in paragraph 2.5 of the report be recommended to Full Council. (2) That the introduction of fees for monitoring biodiversity net gain (BNG) in accordance with the fee schedule as set out in paragraph 2.11 of the report be recommended to Full Council. (3) That the fee schedule for Planning Performance Agreements (PPAs) as set out in paragraph 2.10 of the report be recommended to Full Council. (4) That the revised pre-application and post-decision advice fee schedule as set out in Tables 1, 2 and 3 at paragraph 2.6 of the report be recommended to Full Council.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Policy and Resources Committee

Policy and Resources Committee Meeting Date 10 September 2025 Report Title New and Amended Fees for Applications made to the Planning Service EMT Lead Emma Wiggins Director of Regeneration and Neighbourhoods Head of Service Joanne Johnson Head of Place Lead Officer Carly Stoddart Continuous Improvement Lead Classification Open Recommendations 1. That members recommend to Full Council the introduction of charges for amendments to undetermined applications in accordance with the fee schedule as set out in paragraph 2.5 of this report. 2. That members recommend to Full Council the introduction of fees for monitoring biodiversity net gain (BNG) in accordance with the fee schedule as set out in paragraph 2.11 of this report. 3. That members recommend to Full Council the fee schedule for Planning Performance Agreements (PPAs) as set out at paragraph 2.10 of this report. 4. That members recommend to Full Council the revised pre-application and post-decision advice fee schedule as set out in Tables 1, 2 and 3 at paragraph 2.6 of this report.

1 Purpose of Report and Executive Summary

1.1This report provides an update to an item that was considered at the 12 June 2025 Policy and Resources Committee where it was deferred to allow for a Task and Finish Group to be set up to discuss the proposals in more detail. The Task and Finish Group met twice to discuss the proposals.

1.2At the 12 June 2025 Committee, the Planning Service proposed to make service improvements through the introduction of fee schedules to recover costs for services that it provides that are not part of the statutory provision. The proposals were for the introduction of charging applicants to amend their undetermined applications either through the alteration of previously submitted details or the submission of new supporting information. A fee schedule and related procedure to cover the process was set out.

1.3It was also proposed to introduce fees for the monitoring of biodiversity net gain (BNG). A separate fee schedule and related procedure was set out to cover this process. 1.4 Taking a holistic approach and review of the non-statutory services within the Planning Service, an explanation of the interplay with associated Planning Service fees such as pre-application and post-decision advice, and Planning Performance Agreements (PPAs) was given. New fees were proposed for PPAs and amendments proposed to existing pre-application advice fees.

1.5In reviewing and considering the proposals within the report it was decided at Policy and Resources Committee on 12 June 2025 to defer the item for further information and clarification to be discussed by a Task and Finish Group.

1.6This report summarises the outcome of the Task and Finish Group discussions and seeks Committee approval of the recommendations to introduce new fees and amend existing fees.

2 Background 2.1 The purpose of the Task and Finish Group was to discuss and provide clarification on the deferred Policy and Resources item New and Amended Fees for Applications made to the Planning Service with the outcome to reach agreement of appropriate fees to present back to Policy and Resources Committee.

2.2Each political party was invited to nominate a representative to be part of the Task and Finish Group. Subsequently, a total of two meetings were held to discuss the deferred item. Comparison tables of pre-application advice fees currently being applied by Kent Local Planning Authorities were sent out ahead of the first meeting at members’ request (Appendix I).

2.3At the Task and Finished meetings, those present summarised the queries and concerns their Groups had expressed following the item’s discussion at the 12 June Policy and Resources Committee meeting and the concerns expressed more widely by Committee members. The areas of clarification, the response and outcome are set out in the table below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New and Amended Fees for Applications made to the Planning ServiceReport 368 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 33 attended
BA
Billy AttawayOfficer, in attendance
MB
Mike BaldockCommittee Member, present
LB
Lloyd BowenVice-Chair, apologies, sent representative
MC
Martyn CassellOfficer, in attendance
SC
Steph CurtisOfficer, in attendance, virtual
JD
Janet DartOfficer, in attendance
LF
Lisa FilleryOfficer, in attendance
CG
Charles GibsonCommittee Member, present
TG
Tim GibsonChair, present
AG
Alastair GouldCommittee Member, present
RH
Robin HarrisOfficer, in attendance
AH
Angela HarrisonCommittee Member, present

All 33 on the meeting page

On this subject at Swale

Search all
  1. New and Amended Fees for Applications made to the Planning ServiceThis decision
  2. New and Amended Fees for Applications made to the Planning ServiceAgreed

More from Swale Policy and Resources Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Forward Decisions Plan(1) That the Forward Decisions Plan be noted. Noted Open
13 Jul 2026 Recommendations from the Swale Joint Transportation Board meeting held on 29 June 2026(1) That the recommendation under Minute 146 of the Swale Joint Transportation Board meeting held on 29 June 2026 be ... Noted Open
13 Jul 2026 Risk Management Update(1) That the updated Strategic Risk Register be noted and approved. Noted Open
13 Jul 2026 Community Governance Review Final Recommendations(1) That the Policy and Resources Committee agree and recommend to Council that the following CGR Recommendations are... Agreed Open
13 Jul 2026 Corporate Equality Scheme 2024-2028(1) That the update on progress against the Corporate Equality Scheme 2024 – 2028 be noted. (2) That the proposed cha... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies