(1) That the appointment of Company A as supplier for Cockleshell Walk Build Contract subject to appropriate levels of grant secured from Homes England be agreed. (2) That delegated authority be given to the Head of Service to award the next suitable alternative tenderer in the event that a contract cannot be executed with the highest scoring tenderer. (3) That the total spend of £13.763 million, including professional fees and contingency allowances be agreed and delegated authority be given to the Director of Resources to determine the most appropriate balance of funding sources for a viable scheme.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Policy and Resources Committee Meeting Date 10th September 2025 Report Title Procurement of Build Contract for Cockleshell Walk Housing Scheme EMT Lead Emma Wiggins, Director of Regeneration and Neighbourhoods Head of Service Charlotte Hudson, Head of Housing and Communities Lead Officer Charlotte Hudson, Head of Housing and Communities Classification Open with restricted appendices Recommendations 1. That the Committee approves the appointment of Company A as supplier for Cockleshell Walk Build Contract subject to appropriate levels of grant secured from Homes England.
2. That the committee allow delegated authority to the Head of Service to award to the next suitable alternative tenderer in the event that a contract cannot be executed with the highest scoring tenderer.
3. The total cost of the project is currently estimated at £13.763m when including professional fees and contingency allowances, it is proposed that this committee approve the total spend and allow delegated authority to the Director of Resources to determine the most appropriate balance of funding sources for a viable scheme.
1 Purpose of Report and Executive Summary 1.1 This report provides a background to the Cockleshell Walk funding model and summarises the procurement process undertaken for the Build Contract of the 51-unit scheme at Cockleshell Walk, Sittingbourne.
1.2The Southeast Consortium Framework was utilised to carry out a one stage tender process based on the most advantageous tender (MAT) which was evaluated on 60% price and 40% quality. The Contract is to provide the construction of the 51-unit scheme at Cockleshell Walk.
1.3This report seeks Committee approval of the recommended contractor and seeks delegated authority to finalise the scheme funding. 2 Background
2.1On 28th October 2020 Cabinet agreed to progress with the establishment of a Local Housing Company (LHC), loan the LHC up to £23m to fund the Capital development and provide three sites owned by the Council for development purposes. Consultants Counties and Capital Ltd were appointed to work on these proposals and develop the schemes. Early in the work external economic factors driven by COVID19, BREXIT and Ukraine war impacted interest rates and development costs significantly. It became apparent that the original ambition and modelling work were no longer viable. It was agreed however, to pursue one site and change the approach to secure additional grant funding to bridge the viability gap.
2.2Detailed design work was commissioned to secure planning consent for the site at Cockleshell Walk. Planning permission was granted by Planning Committee on 23rd May 2024. Work to finalise the Memorandum of Understanding (s.106 equivalent) was finalised on 18th March 2025.
2.3A revised model was developed by the Director of Resources (s.151 Officer) taking into consideration modelled build costs, current interest rates and the intended operating models. Different tenures and therefore rent levels were also considered as part of the modelling. This identified the shortfall in funding for the scheme and levels of external funding that needed to be secured. The model is shown in Appendix 1.
2.4A grant of £943k was secured from the Brownfields Land Release Fund (BLRF) and dialogue was entered into with Homes England regarding securing grant funding from the Affordable Homes Programme (AHP). To secure grant funding from Homes England, it was agreed by the Swale Rainbow Homes Shareholder Panel that the Council would be best placed to secure the funding and become an Investment Partner. Therefore, the build contract and grant would need to be entered into by the Council and not Swale Rainbow Homes Ltd.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Equality Scheme 2024-2028(1) That the update on progress against the Corporate Equality Scheme 2024 – 2028 be noted. (2) That the proposed cha...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.