Procurement of Build Contract for CCTV Control Room Expansion
ApprovedCommittee1 paper
AI summarySwale councillors approved Company A to build the CCTV Control Centre expansion at a fixed price of £196,348.39, subject to planning permission expected by end of May 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to planning permission being granted
Money£196,348.39 fixed priceExclusive of VAT, additional equipment ~£30,000
What happens nextAwait planning permissionExpected by end of May 2026
Who it affectsCCTV Control Centre operationsService growth and income generation
What was decided
The Committee approved appointing Company A as supplier for the CCTV Control Centre Expansion Build, subject to planning permission. Report 3.1
Delegated authority was given to the Director of Resources to agree increased costs if an inflationary uplift is needed because of any delay in planning permission. Report 3.2
Delegated authority was given to the Head of Legal Partnership and the S151 Officer to handle the legal and financial requirements, and to the Head of Legal Partnership to negotiate and complete the contract and ancillary documents. Report 3.3, P12
Why
Only Company A submitted a fully compliant tender after a further one stage tendering process that closed on 23 March 2026; three other tenders failed the required financial checks. Report 2.6, 2.7
Airey Miller recommended entering into a contract with Company A following a review of quality and suitability. Report 2.7, 2.8
The Control Centre is now operating at capacity, and without expansion growth of services and income will be limited. Report 4.1
What happens next
A JCT contract is to be entered into with the approved contractor, including agreed social value outcomes. Report P19
Tender prices are currently held until the end of June 2026 and could be subject to inflationary uplift if planning permission is not in place by 30 June 2026. Report 2.8
Planning permission is currently being considered and is anticipated to be in place by the end of May 2026. Report 2.8
The money
£282,900 Capital budget agreed by Policy and Resources Committee on 12 June 2025 Report 2.1
£196,348.39 Fixed price recommended by Airey Miller, exclusive of VAT Report 2.8
approximately £30,000 Additional costs for project including additional equipment for the Control Centre Report P18
c£11,000 per year Forecast increase in income to the Control Centre to pay back capital costs Report P19
Options considered
Rejected: Do not award the contract and do not expand the CCTV Control Centre. Without expansion, growth of services managed by the Control Centre and the income it generates would be limited because the Control Centre is operating at capacity. Report 4.1
Implications
Financial: Capital payback is expected from forecast increase in Control Centre income of around £11,000 per year; revenue costs to be met from within current budget framework. Report 2.1, P19
Legal: The tender is compliant with Contract Standing Orders and procurement legislation; a JCT contract will be used. Report P19
Risk: Prices are held until end of June 2026 and could rise if planning permission is delayed beyond 30 June 2026; the project has a risk management plan and CDM and health and safety requirements have been considered. Report 2.8, P21
Climate: Environmental standards have been agreed as part of the procurement and contract process for the build. Report P21
Other: Expanding the Control Centre will enable it to provide services as part of a future unitary council once established, and allows external contracts that may not monitor Swale based cameras. Report P20, P23
Who and where
Swale Borough Council's CCTV Control Centre service Report P18, P23
Residents and town centre users, through continued and expanded CCTV and radio coverage Report P18, P20
Vulnerable members of the community, including those who go missing, who are supported by the Control Centre Report P21
Timeline
12 June 2025: Policy and Resources Committee added Control Centre Growth project to Capital Programme with £282,900 budget Report 2.1
October 2025: Initial tendering process via Southeast Consortium DPS held; no submissions suitable to progress Report 2.4
2 March 2026: Two companies submitted formal tenders under two-stage process; concerns over financial viability Report 2.5
23 March 2026: Further one stage tendering process closed; only Company A fully compliant Report 2.6
21 April 2026: Housing, Health and Communities Committee decision to appoint Company A subject to planning permission Report 3.1
End of May 2026 (anticipated): Planning permission expected to be in place Report 2.8
End of June 2026: Tender prices held until this date; inflationary uplift possible if planning permission not in place by 30 June 2026 Report 2.8
Plain English for the jargon
DPS: Dynamic Purchasing System, a procurement route used by the Southeast Consortium
JCT contract: A standard form of building contract issued by the Joint Contracts Tribunal
S151 Officer: The council officer with statutory responsibility for financial administration under section 151 of the Local Government Act 1972
CDM: Construction Design and Management regulations covering health and safety on construction projects
ASB: Anti-social behaviour
Company A: The sole fully compliant tenderer whose identity is redacted in the papers
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item882
Resolved
Resolved : (1) That the Committee approves the appointment of Company A as supplier for the CCTV Control Centre Expansion Build, subject to Planning Permission. (2) That the Committee gives delegated authority to the Director of Resources to agree increased costs should an inflationary uplift become necessary due to any delay in planning permission being granted. (3) That the Committee give delegated authority to the Head of Legal Partnership and S151 Officer to undertake all legal and financial requirements necessary to complete the CCTV Control Centre Expansion Build, subject to Planning Permission. (4) That the Head of Legal Partnership has delegated authority to negotiate and complete the contract and all ancillary documents as may be necessary.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Report to Housing, Health and Communities Committee
Background
2.1On the 12th June 2025, Policy and Resources Committee agreed the addition of the Control Centre Growth project to the Capital Programme for 2025/26, with a capital budget of £282,900, with the revenue costs of the proposal to be met from within the current budget framework.
2.2Consultants Airey Miller were appointed to develop the detailed Tender Specification and designs. 2.3 Planning permission is also being sought as follows for this project - Change of Use of the existing building from a multi-storey car park to a mixed use comprised of a multi-storey car park and a non-ancillary CCTV control room. This is due to the increased size and commercial nature of the control room. At the time of contract award, the planning permission is still being considered.
2.4An initial tendering process took place in October 2025 utilising the Southeast Consortium Dynamic Purchasing System (DPS). Although a number of compliant tenders were submitted, quality scores were low, and it was not felt by the consultant or officers that any of the submissions were suitable to progress.
2.5After detailed discussions with Procurement and Legal, it was agreed to follow a two-stage competitive flexible process. Two companies were invited to progress to stage 2 and submit a formal tender. Tenders were received on the 2nd March 2026, however there were concerns regarding the financial viability of those companies.
2.6A further one stage tendering process was followed and this closed on the 23rd March 2026. Four tenders were submitted, however three were not compliant with the financial checks required. Only company A submitted a fully compliant tender.
2.7A review has been completed of the tender submitted by Company A followed by discussions with Airey Miller as to the quality and suitability of Company A.
2.8Airey Miller recommend SBC consider entering into contract with Company A with a fixed price of £196,348.39 exclusive of VAT. These prices are currently held until the end of June 2026 and could be subject to an inflationary uplift if SBC do not have the agreed planning permissions in place by 30 June 2026. It is currently anticipated planning permission may be in place by the end of May 2026.
Proposals
3.1That the Committee approves the appointment of Company A as supplier for the CCTV Control Centre Expansion Build, subject to Planning Permission.
3.2That the Committee gives delegated authority to the Director of Resources to agree increased costs should an inflationary uplift become necessary due to any delay in planning permission being granted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.