Resolved
RESOLVED that the revised capital budget for 2014-2015 and a capital budget for 2015-2016 to 2018-2019 as detailed in Appendices A, B, C, D, E and F be approved.
Council approved this item on Tuesday 24 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revised capital budget for 2014-2015 and a capital budget for 2015-2016 to 2018-2019 as detailed in Appendices A, B, C, D, E and F be approved.
Report of the Section 151 Officer
Council – 24 February 2015
CAPITAL BUDGET & PROGRAMME 2014/15 – 2018/19
Purpose: This report proposes a revised capital budget for 2014/15 and a capital budget for 2015/16 - 2018/19
Policy framework: None
Reason for decision: To agree a revised budget for 2014/15 and a budget for 2015/16 – 2018/19
Consultation: Cabinet Members & Executive Board
Recommendation: The revised capital budget for 2014/15 and a capital budget for 2015/16 – 2018/19 as detailed in appendices A, B C, D, E and F is approved.
Report Author: M.Hawes
Finance Officer: M.Hawes
Legal Officer: Patrick Arran
Access to Services Officer: Euros Owen
1. Introduction 1.1 This report details:
• Revised capital expenditure and financing proposals in 2014/15 • Capital expenditure and financing proposals in 2015/16 – 2018/19
1.2Capital spending and funding proposals in relation to the Housing Revenue Account (HRA) are detailed in a separate report to be considered.
1.3The budget proposals are detailed in appendices to this report as follows: Appendix A Summary of General Fund Capital Expenditure and Financing 2014/15 – 2018/19
Appendix B Schools Programme Capital Expenditure and Financing 2014/15 – 2018/19
Appendix C Material changes to the original 2014/15 budget
Appendix D Material changes to the Capital Programme agreed in February 2014
Appendix E General Fund Capital Budget 2014/15 – 2018/19
Appendix F Education surplus land sites identified for sale 1.4 The key message arising from this report is that the overall programme deficit, encompassing both the General Fund Programme and Schools programme, amounts to some £57.038m over the lifetime of the programme.
Given the anticipated Revenue Budget contained within the Medium Term Financial Plan, it would not be prudent to assume any increase in borrowing to meet this shortfall, which should be met by:-
- Increased Capital receipts - reduction in the planned Capital programme.
2. Capital Budget 2014/15 2.1 Spending in the current year will be £89.202m – an increase of £34.359m compared to the original estimate of £54.843m.
This increase is due to the following: - the addition of grant funded schemes after Council approved the capital budget in February 2014. - Revised forecast for Equal Pay claims resulting in an additional cost of - £9m, to be funded by borrowing allowed by a capitalisation directive of £6.7 million and the balance of £2.3 million to be funded by capital receipts. - The net balance of schemes carried over from 2013/14 into 2014/15 and schemes carried over from 2014/15 into 2015/16.
Material changes to the 2014/15 budget are summarised in Appendix C.
3. Capital Programme and Financing 2014/15 to 2017/18
3.1The proposed programme and financing is set out below.
Paragraphs 3.2 to 3.7 detail the material changes to the General Fund Programme and Financing.
Paragraphs 3.8 to 3.12 detail the Schools Programme and Financing.
GENERAL FUND PROGRAMME AND FINANCING
3.2The General Fund programme is summarised in Appendix A and detailed in appendix E. The attached proposals exclude the Housing Revenue Account capital budget which is detailed elsewhere on the agenda.
3.3The Capital Budget report considered by Council on 18th February 2014 highlighted a forecast shortfall in the four year forward programme of £31.276m for the 21st Century Schools programme and £28.977m for the rest of the General Fund capital programme. The report contained the following in respect of both the general fund and Schools programme shortfalls:- ‘If required, it will be necessary to finance the forecast shortfall in 2014/15 by temporary unsupported borrowing pending the identification of a funding solution in relation to the four year programme’.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget & Programme 2015/16: 2018/19.Report | 74 KB | DownloadRead as text |
PDF |
Capital Budget Appendix AAppendix | 6 KB | Download |
PDF |
Capital Budget Appendix BAppendix | 6 KB | Download |
PDF |
Capital Budget Appendix CAppendix | 8 KB | Download |
PDF |
Capital Budget Appendix DAppendix | 5 KB | Download |
PDF |
Capital Budget Appendix EAppendix | 16 KB | Download |
PDF |
Capital Budget Appendix FAppendix | 4 KB | Download |
Follow Council at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors C M J Evans, B Hopkins, D H Hopkins, N L Matthews & S J Rice – item 15 – personal & prejudicial Councillo... | Decided | Open |
| 3 Sep 2026 | Minutes.Approved | Approved | Open |
| 3 Sep 2026 | Written Responses to Questions asked at the Last Ordinary Meeting of Council.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Presiding Member.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Leader of the Council.For Information | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.