RESOLVED that: 1) The transfers between schemes and the revised budget for schemes in 2014-2015 be approved; 2) The budget proposals for 2015-2016 to 2018-2019 be approved; 3) Where individual schemes in Appendix B of the report are programmed over 2, 3 or 4 years, then these be committed and approved and that their financial implications for funding over subsequent years be approved; 4) Authorisation be granted to Officers to submit planning applications in relation to Capital Repair Schemes on Council owned land where planning permission is considered necessary.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Purpose This report proposes a capital budget for 2015/16 – 2018/19
Policy Framework: None
Reason for Decision: To agree a revised budget for 2014/15 and a budget for 2015/16 – 2018/19
Consultation: Legal, Finance & Access to Services
Recommendation(s): It is recommended that:
1) The transfers between schemes and the revised budgets for schemes in 2014/15 are approved.
2) The budget proposals for 2015/16 – 2018/19 be approved.
3) That, where individual schemes in Appendix B are programmed over 2, 3 or 4 years, then these are committed and approved and that their financial implications for funding over subsequent years are approved.
4) Authorisation is granted to officers to submit planning applications in relation to capital repair schemes on Council owned land where planning permission is considered necessary.
Report Author: Jeff Dong
Finance Officer: Jayne James
Legal Officer: T Meredith
Access to Services Officer Phil Couch
1.0Introduction
1.1This report details:
• Revised Housing Revenue Account (HRA) capital expenditure and financing proposals in 2014/15 • HRA Capital expenditure and financing proposals in 2015/16 – 2018/19 1.2 The budget proposals are further detailed in appendices to this report as follows:
• Appendix A: Summary of capital expenditure and financing 2014/15 - 2018/19 • Appendix B: Detailed breakdown of the capital budget for 2014/15 – 2018/19 • Appendix C: Scheme descriptions
2.0Capital Budget 2014/15 – 2018/19
2.1The total programme for this current year is £26.907m i.e. an original budget of £38.5m less slippage into 2015/16 of £12.293m plus additional works of £0.7m . Slippage from this current year into 2015/16 is principally to fund the refurbishment of six highrise blocks of flats in the Town Centre, Penlan and Sketty areas. Total spending in this current year is projected to remain at £26.907m. Notwithstanding the high rise projects, the majority of all other projects are complete in 2014/15, although a small element of under spend may exist due to a range of reasons including retentions retained for the defects liability period and some under spends on completed projects. Any projects not currently complete will be completed within the early part of the 2015/2016 financial year. The anticipated spend against profile for 14/15 (excluding high rise) will be in the region of 95% of the overall budget and where under spend has occurred officers have mitigated these by bringing other priority work forward to compensate. Transfers and changes to the 2014/15 budget are reflected and detailed in appendix B.
3.02015/16 – 2018/19
3.1The proposed four year capital programme and the priorities of the various schemes have been developed in line with the HRA Business Plan and reflect the results of a stock condition survey. In addition, the programme contributes towards the Council’s strategic aim of improving homes up to the Welsh Housing Quality Standard (WHQS).
3.2Schemes detailed in Appendix C contribute towards the key components of the Welsh Housing Quality Standard as follows:
In a Good State of Repair Dwellings must be structurally stable; free from damp and disrepair with key building components being in good condition – roofs, walls, windows, doors and chimneys.
Safe and Secure Dwellings should be free from risks that could cause serious harm and should be secure in key areas of the home. Heating and electrical systems to be up to date and safe; doors and windows to provide good levels of security; risk of falls from height to be prevented; fire safety measures to be in good condition and well designed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.