RESOLVED that: (1) the rewording of the description of development to “retention and completion of 25 dwellings and associated works including underground pumping station and surface water attenuation pond” and the rewording of Conditions 4(5), 5(6), 6(7), 8(9), 9(10), 10(11), 11(12), 13(14), 14(15), 17(19), 19(21), 20(22), 21(23), 22(24), 23(27), 24(28) and 25(30) as shown in the revised Schedule of Conditions at Appendix B be approved; (2) the removal of Conditions 1, 16, 25, 26 and 29 as per paragraph 2.5 in the report be agreed; (3) the original requirements of the (original) Condition 16 be clearly incorporated into the original Condition 6 (Condition 5 of the new recommendation).
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
1.1This application was reported to the Planning Committee on the 20th January 2015, with the recommendation that planning permission be granted subject to the developer entering a Section 106 Obligation and conditions.
1.2The Committee resolved to accept the recommendation for approval and granted planning permission subject to a Section 106 Agreement and conditions. A copy of my report to the Planning Committee on the 20th January 2015 is attached as appendix A.
1.3A number of the planning conditions attached to the report required the submission & approval of the details PRIOR to the commencement of development.
2.0Main Issues
2.1Following the committee resolution referred to above, the Section 106 Agreement took some time to be completed due to legal matters, and as such, the formal planning permission has not yet been issued.
2.2During this time, a complaint has been received from a local resident that works have commenced on the site. Enforcement Officers have visited the site and have confirmed that the works being undertaken on the site are works that ‘constitute development’ and are not ‘enabling site works’.
2.3As works have started on site, the planning permission cannot be issued due to the inclusion of a number of ‘pre-commencement’ conditions. 2.4 Therefore the description of development requires to be re-worded to the following “Retention and completion of 25 residential dwellings and associated works including underground pumping station and surface water attenuation pond”, and a number of conditions require re-wording prior to the issuing of the permission, specifically the following conditions are required to be re-worded:
* Condition number in brackets ( ) refers to original condition number 4 (5), 5 (6), 6 (7), 8 (9), 9 (10), 10 (11), 11 (12), 13 (14), 14 (15), 17 (19), 19 (21), 20 (22), 21 (23), 22 (24), 23 (27), 24 (28), and 25 (30) 2.5 The following conditions can be removed as they no longer considered to be necessary. • Condition 1 – commencement within 5 years – the development has already commenced • Condition 16 - porous drive ways - this will be covered by the surface water drainage system required under condition 6 • Condition 25 – replacement tree planting – this is now covered under condition 21 • Condition 26 – replacement tree replacements – this is now covered under condition 21 • Condition 29 – Japanese Knotweed – no longer required as it has been confirmed that there is no knotweed on the site
2.6The applicant has submitted technical details in relation to condition • 11 (12) – Construction Pollution Management Plan (CPMP),
Response on the technical detail is currently pending from Pollution Control Officers.
2.7A full set of the amended conditions are attached at Appendix B to this report
Recommendation
3.1It is recommended that the Committee :
(i) Approve the rewording of the description of development to “Retention and completion of 25 residential dwellings and associated works including underground pumping station and surface water attenuation pond” and the rewording of conditions 4 (5), 5 (6), 6 (7), 8 (9), 9 (10), 10 (11), 11 (12), 13 (14), 14 (15), 17 (19), 19 (21), 20 (22), 21 (23), 22 (24), 23 (27), 24 (28), and 25 (30) as shown in the revised schedule of conditions at Appendix B.
(ii) Agree to the removal of conditions 1, 16, 25, 26, and 29 as per paragraph 2.5 above
(ii) Grant delegated authority to the Head of Economic Regeneration and Planning to amend the wording of condition 11 (12) pending confirmation from the Pollution Control Officers that the technical details are acceptable.
Background papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.