RESOLVED that the revised Delivery Programme for Sustainable Swansea – Fit for the Future be noted. [ Note: The Leader of Council agreed to provide a glossary detailing the acronyms contained in the report and would provide a written reply regarding the circumstances which would require external advice to be procured].
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Appendix A – Change Plan (Extract) Appendix B – Efficiency Workstream Assessment Appendix C – New Models of Delivery Workstream Assessment Appendix D – Prevention Workstream Assessment Appendix E – Stopping Services Workstream Assessment Appendix F – Resourcing Statement Appendix G – Sustainable Swansea Governance Structure Appendix H – Sustainable Swansea Revised Programme VERSION 10
Background
This section sets out why the review was required, the issues addressed as agreed by the Executive Board and the review process. 2.1 Why a Review is Required
The Sustainable Swansea Delivery Programme was agreed by Cabinet on 29 July 2014 following a major review of the Workstreams and the projects to be included, with extensive engagement of managers and staff.
The overall aims and objectives of Sustainable Swansea are unlikely to change in the medium term, but they do need to be evaluated and reviewed in the light of new information and the changing internal and external environment.
The Delivery Programme also needs to be updated regularly and the Executive Board agreed in February 2015 that a review was required because of:
• the increased scale of the savings that we need to make • the lack of time we have to achieve this • the evident lack of traction and ownership in some areas • the risk that agreed projects will be changed or deferred, without appropriate governance • new knowledge / information as the programme progresses
2.2Issues Addressed in the Review
The review has addressed two key issues:
• Savings the allocation of the additional savings across the Programme to meet the three year £80m target in the Medium Term Financial Plan (MTFP) • Delivery what we have achieved so far and the future shape of the programme and the 4 Workstreams
For completeness, the review has also addressed the following:
• Resourcing the internal and external resources required to deliver the Programme, what these will achieve and how they will be deployed • Governance any changes required to the governance arrangements for Sustainable Swansea • Communications proposals for future internal and external communication and engagement on the programme • Risks and Issues assessment of the top risks and issues and how these will be managed and addressed VERSION 10
2.3Savings
The fundamental issue to be addressed is the allocation of the additional savings to meet the three year £80m target. The MTFP approved by Council in February 2015 includes the following two tables, showing the savings by Directorate (total):
Current Percentage Amount Service Budget Reduction/Increase Realised £m over 3 Years £m Schools & Education 159.5 -15 -23.9 Social Care – Child & 39.1 -15 -5.9 Families Social Care- Adults 65.6 -20 -13.1 Poverty & Prevention* 3.5 +5 +0.2 Place 54.0 -50 -26.5 Corporate Services 25.1 -50 -12.5 Total 346.8m -81.7m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.