Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.
ApprovedExecutive3 papers
AI summarySwansea Council Cabinet approved the 2025-26 Corporate Transformation Plan Annual Report for publication, noting consolidation of programmes from thirteen to twelve and endorsing continued focus for 2026-27.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgress and risks noted, 2026-27 focus endorsed
MoneyNo additional financial implicationsProgramme costs already in MTFP
What happens nextContinue embedding in 2026-27Focus on operating models, benefits, MTFP alignment
Who it affectsCouncil's transformation portfolioReduced from thirteen to twelve programmes
What was decided
The Cabinet approved the Corporate Transformation Plan Annual Report 2025-26 for publication.
Members noted progress including the consolidation from thirteen to twelve programmes, with the Future Community Hub Model absorbed into the revised Enabling Communities Programme and the Future Waste Strategy Programme moving to business-as-usual.
Members noted the key risks and delivery issues set out in the report, covering demand pressures, capital affordability, market conditions, workforce capacity and reliance on short-term external funding in some areas.
Why
The report is part of the agreed governance framework for the Corporate Transformation Plan and is presented annually for Cabinet approval and publication. Report P3
Individual programme financial implications are already incorporated into the Medium Term Financial Plan, so no new financial decisions arise from this report. Report P1
What happens next
Publication of the approved Annual Report, attached as Appendix A. Report P4
In 2026-27, continued focus on embedding new operating models, sustaining benefits, strengthening benefits realisation and maintaining alignment with the Medium Term Financial Plan.
Risks around demand, capital affordability, market conditions, workforce capacity and short-term external funding to be monitored through the portfolio's existing governance. Report P3
Implications
Financial: No new financial implications for the Council; programme costs already in the Medium Term Financial Plan. Report P1
Legal: No legal or governance implications beyond those identified in the report; the Annual Report forms part of the agreed governance framework. Report P3
Risk: Reported risks include demand pressures, capital affordability, market conditions, workforce capacity and reliance on short-term external funding in some areas.
Other: Programme portfolio consolidated from thirteen to twelve, with Future Community Hub Model absorbed into the revised Enabling Communities Programme and Future Waste Strategy Programme moving to business-as-usual.
Who and where
Swansea Council Cabinet and officers responsible for the Corporate Transformation Programme Report P3
Services and communities covered by the Future Community Hub Model, now within the revised Enabling Communities Programme
Waste services, now managed under business-as-usual following the transition of the Future Waste Strategy Programme
Timeline
2025-26: Period covered by the Annual Report, including portfolio reduction from thirteen to twelve programmes.
2026-07-16: Cabinet meeting at which the Annual Report was approved for publication.
2026-27: Forward year for embedding operating models, sustaining benefits and strengthening benefits realisation.
Plain English for the jargon
MTFP: Medium Term Financial Plan, the Council's multi-year financial planning document.
Corporate Transformation Plan: Swansea Council's portfolio of change programmes designed to deliver savings and service change.
Business-as-usual: Activities that have moved out of a dedicated change programme into standard, ongoing service management.
IIA: Integrated Impact Assessment, referenced as Appendix B.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item45
Resolved
Resolved that: 1) The Corporate Transformation Plan Annual Report 2025–2026, attached at Appendix A of the report be approved for publication. 2) The progress made during 2025–2026 across the transformation portfolio, including the consolidation from thirteen to twelve programmes following the absorption of the Future Community Hub Model into the revised Enabling Communities Programme, and the transition of the Future Waste Strategy Programme into business-as-usual management arrangements be noted. 3) The key risks and delivery issues identified in the Annual Report, including demand pressures, capital affordability, market conditions, workforce capacity and reliance on short-term external funding in some areas be noted. 4) The continued focus during 2026–2027 on embedding new operating models, sustaining benefits, strengthening benefits realisation and maintaining alignment with the Medium-Term Financial Plan be endorsed.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26. Executive Summary Purpose of Report: To seek Cabinet approval of the Corporate Transformation Plan Annual Report 2025–26 (Appendix A), which provides assurance on delivery of the Corporate Transformation Plan 2023–28, confirms alignment with the Council’s Corporate Plan and Medium-Term Financial Plan, and sets out progress, risks and delivery priorities for 2026–27.
Recommendation(s). It is recommended that Cabinet: 1) Approves the Corporate Transformation Plan Annual Report 2025–26, attached at Appendix A, for publication. 2) Notes the progress made during 2025–26 across the transformation portfolio, including the consolidation from thirteen to twelve programmes following the absorption of the Future Community Hub Model into the revised Enabling Communities Programme, and the transition of the Future Waste Strategy Programme into business-as-usual management arrangements. 3) Notes the key risks and delivery issues identified in the Annual Report, including demand pressures, capital affordability, market conditions, workforce capacity and reliance on short-term external funding in some areas. 4) Endorses the continued focus during 2026–27 on embedding new operating models, sustaining benefits, strengthening benefits realisation and maintaining alignment with the Medium-Term Financial Plan.
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☐ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☒ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution.
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☒ Education & Skills ☒ Tackling Poverty & Enabling Communities ☒ Economy & Infrastructure ☒ Transformation & Financial Resilience ☒ Nature Recovery & Climate Change ☒ All ☒ Safeguarding ☐ Not Applicable
Relevance to Corporate Plan Wellbeing Objectives: The Corporate Transformation Plan is a cross-council programme that directly supports delivery of all Corporate Plan Wellbeing Objectives. It brings together service transformation and organisational enablers across social care, education, housing, homelessness, regeneration, waste, climate, workforce, digital and community services.
The Annual Report provides Cabinet with whole-Council assurance on progress, risks and interdependencies. All relevant service areas have contributed to the report through programme and corporate governance arrangements and are in agreement with its content and recommendations.
Reviewed and approved by: Access to Services, Finance, Legal & Cabinet Member.
Report Author & Job Title: Ness Young, Director of Corporate Services
1. Introduction
2. The purpose of this report is to present the Corporate Transformation Plan Annual Report 2025–26 to Cabinet for approval. This is the third Annual Report on the Council’s Corporate Transformation Plan (CTP) 2023–28 and provides a structured account of progress during year three of the programme.
3. The Corporate Transformation Plan translates the Council’s ambition for a Successful and Sustainable Swansea into a multi-year programme of change. It brings together major service transformation alongside the organisational, digital, workforce and environmental enablers required to support sustainable improvement and financial resilience.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.