RESOLVED that: 1) The capital scheme as detailed together with the financial implications set out in Appendix A of the report be approved, subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government; 2) The 1 st Stage Contract for the design of refurbishment, remodelling and extension works for Pentrehafod Comprehensive School be awarded to Tender No. 1 under the agreement that following the contract award the contractor must obtain planning approval and all risks associated with not achieving planning approval are those of the contractor, and subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government; 3) The Cabinet Member for Education be authorised to approve the award of the stage 2 construction contract for the new school Pentrehafod School, subject to the granting of planning permission for the main works, and subject to confirmation of grant and contract with Welsh Government; 4) The Head of Legal and Democratic Services be authorised to enter into any necessary documentation required to complete the contract and achieve the scheme; 5) A detailed Cabinet Report on the total costs for the scheme and outcomes of the Equality Impact Assessment (EIA) report be submitted in late 2016 for information prior to any construction works being carried out.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
CONTRACT AWARD AND CAPITAL PROGRAMME AUTHORISATION FOR THE DESIGN AND REFURBISHMENT OF PENTREHAFOD COMPREHENSIVE SCHOOLS EXISTING SCHOOL BUILDINGS
Purpose: To approve and commit to the Capital Programme the scheme for the refurbishment of Pentrehafod Comprehensive School subject to confirmation of the grant and entering into a contract with Welsh Government (subject to planning approval). To seek authorisation to award a contract for the works to Tender No 1, under the agreement that following the contract award the contractor must obtain planning approval and all risks associated with not achieving planning approval are those of the contractor, and subject to confirmation of the grant and entering into a contract with Welsh Government (subject to planning approval).
Policy Framework: One Swansea Plan. The Revenue and Capital Budget as reported to and approved by Council on the 10th February 2015. QEd 2020 programme. Corporate Priority – Safeguarding vulnerable young people Corporate Priority – Improving pupil attainment Corporate Priority – Tackling poverty Corporate Priority – Building sustainable communities
Reason for Decision: To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals) – to commit and authorise a new scheme onto the Capital Programme To comply with Contract Procedure Rule 13, the award of contract.
Consultation: Education, Finance, Legal and Democratic Services, Corporate Building and Property Services. Recommendation(s): It is recommended that;
1) a. The capital scheme as detailed together with the financial implications set out in Appendix A is approved, subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government and, b. The 1st Stage Contract for the design of refurbishment, remodelling and extension works for Pentrehafod Comprehensive School be awarded to Tender No. 1 under the agreement that following the contract award the contractor must obtain planning approval and all risks associated with not achieving planning approval are those of the contractor, and subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government and, c. That the Cabinet Member for Education be authorised to approve the award of the stage 2 construction contract for the new school Pentrehafod School, subject to the granting of planning permission for the main works, and subject to confirmation of grant and contract with Welsh Government. d. The Head of Legal and Democratic Services is authorised to enter into any necessary documentation required to complete the contract and achieve the scheme.
2) A detailed Cabinet Report on the total costs for the scheme and outcomes of the EIA report will be submitted in late 2016 for information prior to any construction works being carried out.
Report Author: Sarah Weir
Finance Officer: Jayne James/Jeff Dong
Legal Officer: Debbie Smith
Access to Services Sherill Hopkins Officer: 1.0 Introduction / Background
1.1The Strategic Outline Programme (SOP) detailing the re-organisation and investment need for Schools across Swansea was submitted to the Welsh Government in 2010.
1.2In December 2011 further approval in principle was granted by the Welsh Government to proceed with the schemes outlined within “Band A” of the programme subject to contract and a Local Authority contribution of 50% towards the overall costs.
1.3In line with Welsh Government programme requirements the Capital Budget and Programme 2013/14 to 2019/20 provides an outline spending profile for the early priority schemes, totalling £51m. Included within this first phase of priority projects are refurbishment and remodelling works for Pentrehafod School, with a provisional budget of £12.720 million.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
21st Century Schools Programme: Contract Award and Capital Programme Authorisation for the Design and Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings. 21st Century Schools Update: FPR 7: Pentrehafod Comprehensive.Report
15121st Century Schools Programme - Contract Award and Capital Programme Authorisation for the Design and Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings. 21st Century Schools Update - FPR 7 - Pentrehafod Comprehensive.This decision
21st Century Schools Programme - Contract Award and Capital Programme Authorisation for the Design and Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings. 21st Century Schools Update - FPR 7 - Pentrehafod Comprehensive.This decision
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.