Resolved
RESOLVED that the revised capital budget for 2015-2016 and a capital budget for 2016-2017 to 2019-2020 as detailed in Appendices A, B, C, D and E be approved.
Council approved this item on Thursday 25 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revised capital budget for 2015-2016 and a capital budget for 2016-2017 to 2019-2020 as detailed in Appendices A, B, C, D and E be approved.
Report of the Section 151 Officer
Council – 25 February 2016
CAPITAL BUDGET & PROGRAMME 2015/16 – 2019/20
Purpose: This report proposes a revised capital budget for 2015/16 and a capital budget for 2016/17 - 2019/20
Policy framework: None
Reason for decision: To agree a revised capital budget for 2015/16 and a capital budget for 2016/17 – 2019/20
Consultation: Cabinet Members & Executive Board
Recommendation: The revised capital budget for 2015/16 and a capital budget for 2016/17 – 2019/20 as detailed in appendices A, B C, D, and E is approved.
Report Author: M.Hawes
Finance Officer: M.Hawes
Legal Officer: Patrick Arran
Access to Services Officer: Sherrill Hopkins
1. Introduction 1.1 This report details:
Revised capital expenditure and financing proposals in 2015/16 Capital expenditure and financing proposals in 2016/17 – 2019/20
1.2Capital spending and funding proposals in relation to the Housing Revenue Account (HRA) are detailed in a separate report to be considered.
1.3The budget proposals are detailed in appendices to this report as follows:
Appendix A Summary of General Fund Capital Expenditure and Financing 2015/16 – 2019/20
Appendix B Schools Programme Capital Expenditure and Financing 2015/16 – 2019/20
Appendix C Material changes to the original 2015/16 budget Appendix D Reconciliation of Capital programme shortfall
Appendix E General Fund Capital Budget 2015/16 – 2019/20
1.4The key message arising from this report is that the overall programme deficit, encompassing both the General Fund Programme and Schools programme, amounts to some £30.085 million over the lifetime of the programme.
Additional capital receipts will continue to be reviewed and brought onto the programme but in the absence of such further receipts it must be assumed that additional borrowing will need to be taken out to fund the capital programme.
2. Capital Budget 2015/16
2.1Spending in the current year is forecast to be £72.062m (GF £61.048 plus Schools programme £11.014m) – an increase of £28.16m compared with the original estimate of £43.902m.
This increase is due to the following: - the addition of grant funded schemes after Council approved the capital budget in February 2015. - The net balance of schemes carried over from 2014/15 into 2015/16 and schemes carried over from 2015/16 into 2016/17.
Material changes to the 2015/16 budget are summarised in Appendix C.
3. Capital Programme and Financing 2015/16 to 2019/20
3.1The proposed programme and financing is set out below.
Paragraphs 3.2 to 3.9 detail the General Fund Programme and Financing.
Paragraphs 3.10 to 3.13 detail the 21st Century Schools Programme and Financing.
GENERAL FUND PROGRAMME AND FINANCING
3.2The General Fund programme is summarised in Appendix A and detailed in appendix E. The attached proposals exclude the Housing Revenue Account capital budget which is detailed in a separate report.
The Capital Budget report considered by Council on 24th February 2015 highlighted a forecast shortfall in the four year forward programme of £57.038m made up of £30.884m for the 21st Century Schools programme and £26.154m for the rest of the General Fund capital programme. The report contained the following in respect of both the general fund and Schools programme shortfalls:- In order to address the shortfall Cabinet will need to consider the following options:-
- Identify and progress further additional Capital receipts over and above those already incorporated in this budget, - Reduce the expenditure contained within the Capital Programme primarily a reduction in proposed allocations as set out in 3.4, - Incur additional unsupported borrowing. This is a last resort given the known pressures on future revenue budgets within the Council and should only be considered on a temporary basis until such time as Capital Receipts are realised.
Whichever option(s) is pursued it is likely that there will have to be an increase in both temporary and overall borrowing limits in the short term.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13 (2 of 6): COUNCIL Capital budget: Appendix AAppendix | 7 KB | Download |
PDF |
13 (3 of 6): COUNCIL Capital budget: Appendix BAppendix | 9 KB | Download |
PDF |
13 (4 of 6): COUNCIL Capital budget: Appendix CAppendix | 8 KB | Download |
PDF |
13 (5 of 6): COUNCIL Capital budget: Appendix DAppendix | 7 KB | Download |
PDF |
13 (6 of 6): COUNCIL Capital budget: Appendix EAppendix | 15 KB | Download |
PDF |
Capital Budget & Programme 2015/16: 2019/20.Report | 95 KB | DownloadRead as text |
Follow Council at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors C M J Evans, B Hopkins, D H Hopkins, N L Matthews & S J Rice – item 15 – personal & prejudicial Councillo... | Decided | Open |
| 3 Sep 2026 | Minutes.Approved | Approved | Open |
| 3 Sep 2026 | Written Responses to Questions asked at the Last Ordinary Meeting of Council.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Presiding Member.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Leader of the Council.For Information | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.