RESOLVED that: 1) The transfers between schemes and the revised budget for schemes in 2015-2016 be approved; 2) The budget proposals for 2016-2017 to 2019-2020 be approved; 3) Where individual schemes in Appendix B of the report are programmed over the 4 year period described in the report, then these be committed and approved and that their financial implications for funding over subsequent years be approved; 4) Authorisation be granted to Officers to submit planning applications in relation to Capital Repair Schemes on Council owned land where planning permission is considered necessary.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Purpose This report proposes a revised capital budget for 2015/16 and a capital budget for 2016/17 – 2019/20
Policy Framework: None
Reason for Decision: To agree a revised capital budget for 2015/16 and a budget for 2016/17 – 2019/20
Consultation: Legal, Finance & Access to Services
Recommendation(s): It is recommended that:
1) The transfers between schemes and the revised budgets for schemes in 2015/16 are approved.
2) The budget proposals for 2016/17 – 2019/20 be approved.
3) That, where individual schemes in Appendix B are programmed over the 4 year period described in this report, then these are committed and approved and that their financial implications for funding over subsequent years are approved.
4) Authorisation is granted to officers to submit planning applications in relation to capital repair schemes on Council owned land where planning permission is considered necessary.
Report Author: Mike Hawes / David Evans
Finance Officer: Jeff Dong / Jayne James
Legal Officer: T Meredith
Access to Services Officer Phil Couch
1.0Introduction
1.1This report details:
Revised Housing Revenue Account (HRA) capital expenditure and financing proposals in 2015/16 HRA Capital expenditure and financing proposals in 2016/17 – 2019/20 1.2 The budget proposals are further detailed in appendices to this report as follows:
Appendix A: Summary of the revised budget for 2015/16 and a budget for 2016/17 – 2019/20 Appendix B: Detailed breakdown of the revised budget for 2015/16 and a budget for 2016/17 – 2019/20 Appendix C: Scheme descriptions
2.0Capital Budget 2015/16 – 2019/20
2.1As outlined in report approved by Council on 2nd Dec 2014 entitled “Reform of the Housing Revenue Account Subsidy System” the Authority entered into a Voluntary Agreement to exit the HRA subsidy system. Exiting the HRA subsidy system required a cash settlement which was arranged with HM Treasury via formulae agreed in the Voluntary Agreement between the 11 local housing authorities and the Welsh Government. The final settlement figure for Swansea was £73.6m and was fully funded by additional borrowing at an average interest rate of 4.25%.
2.2The total programme for this current year is £47.65m i.e. an original budget of £49.29m plus carryforward from 2014/15 of £2.33m plus additional works of £2.48m plus £0.4m from revenue less slippage into 2016/17 of £6.85m. Slippage from this current year into 2016/17 is principally to fund the refurbishment of highrise blocks of flats in the Sketty area. Total spending in this current year is projected to remain at £47.65m. Notwithstanding the high rise projects, the majority of all other projects are complete in 2015/16, although a small element of under spend may exist due to a range of reasons including retentions retained for the defects liability period and some under spends on completed projects. Any projects not currently complete will be completed within the early part of the 2016/2017 financial year. The anticipated spend against profile for 15/16 will be in the region of 97% of the overall budget and where under spend has occurred officers have mitigated these by bringing other priority work forward to compensate. Transfers and changes to the 2015/16 budget are reflected and detailed in appendix B.
3.02016/17 – 2019/20
3.1The proposed four year capital programme and the priorities of the various schemes have been developed in line with the HRA Business Plan and reflect the results of a stock condition survey. In addition, the programme contributes towards the Council’s strategic aim of improving homes up to the Welsh Housing Quality Standard (WHQS) and provision has been made for the development of new council housing.
3.2Schemes detailed in Appendix C contribute towards the key components of the Welsh Housing Quality Standard as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.