21st Century Schools Programme - Purchase Order Variation to include Summer Programme of Works – Refurbishment and Remodelling of Pentrehafod School’s Existing Buildings.

Approved Executive 2 papers

Cabinet approved this item on Thursday 16 June 2016. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED that: 1) The summer programme of capital works as detailed in the report together with the financial implications set out in Appendix A be approved, subject to planning approval and prior to the confirmation of the grant and entering into a contract with Welsh Government; 2) The first-stage purchase order for the design of refurbishment, remodelling and extension works for Pentrehafod School be varied to include the summer programme works (subject to planning approval); 3) The Head of Legal and Democratic Services be authorised to enter into any necessary documentation required to vary the purchase order and achieve the summer programme; 4) A detailed contract award report detailing the total costs for the project and an equality impact assessment will be submitted to Cabinet in September 2016 prior to the major construction works being carried out.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Education

Cabinet – 16 June 2016

21st CENTURY SCHOOLS PROGRAMME

PURCHASE ORDER VARIATION TO INCLUDE A SUMMER PROGRAMME OF WORKS – REFURBISHMENT AND REMODELLING OF PENTREHAFOD SCHOOL’S EXISTING BUILDINGS

Purpose:  To approve pre-construction works of car park to the front of Pentrehafod School prior to Welsh Government approval of the full business case and contract and subject to planning approval  To approve pre-construction works of boundary fencing prior to Welsh Government approval of the full business case and contract and subject to planning approval

Policy Framework:  One Swansea Plan  The revenue and capital budget as reported to and approved by Council on 10 February 2015.  QEd 2020 Programme  Corporate priority to review the overall provision of schools.  Corporate priority to improve opportunities for children and young people.  Corporate priority to improve school performance.  Corporate priority to ensure effective corporate and strategic management of assets.

Reason for decision: To progress enabling and external works during July/August 2016, prior to Welsh Government approval of the full business case and contract, and prior to award of second-stage contract for construction. To obtain authorisation for spend against City and County of Swansea’s 50% contribution for the project prior to Welsh Government final approval of its 50% funding contribution.

Consultation: Education, Finance, Legal and Democratic Services, Corporate Building and Property Services. Recommendation(s):

It is recommended that;

1) the summer programme of capital works as detailed together with the financial implications set out in Appendix A is approved, subject to planning approval and prior to the confirmation of the grant and entering into a contract with Welsh Government;

2) the first-stage purchase order for the design of refurbishment, remodelling and extension works for Pentrehafod School is varied to include the summer programme works (subject to planning approval);

3) the Head of Legal and Democratic Services is authorised to enter into any necessary documentation required to vary the purchase order and achieve the summer programme; and

4) a detailed contract award report detailing the total costs for the project and an equality impact assessment will be submitted to Cabinet in September 2016 prior to the major construction works being carried out.

Report Author: Sarah Weir

Finance Officer: Jayne James/Jeff Dong

Legal Officer: Deborah Howell

Access to Services Officer: Sherill Hopkins

1. Introduction/Background

1.1The Strategic Outline Programme (SOP) detailing the re-organisation and investment need for schools across Swansea was submitted to the Welsh Government (WG) in 2010.

1.2In December 2011, further approval in principle was granted by the WG subject to contract and a local authority contribution of 50% towards the overall costs.

1.3In line with WG programme requirements, the Capital Budget Programme 2013- 2014 to 2019-2020 provides an outline spending profile for the early priority projects, totalling £51million. Included within this first phase of priority projects are refurbishment and remodelling works for Pentrehafod School, with a provisional budget of £12.720 million, to be funded 50% by City and County of Swansea (CCS) and 50% by Welsh Government.

1.4WG approval of the Strategic Outline and Outline Business Cases was granted in February 2015. This was then followed by the appointment of Morgan Sindall in February 2016. 1.5 Subject to the successful approval of the full business case which is to be submitted July 2016, the local authority will enter into a formal contract with the WG which will form a binding agreement with the CCS.

2. Description of works at Pentrehafod School

Major refurbishment and remodelling works

2.1The project aims to provide the pupils and staff of Pentrehafod School with a safe, sound and fit-for-purpose school environment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12 (2 of 2): Appendix AAppendix 8 KB Download
PDF
21st Century Schools Programme: Purchase Order Variation to include Summer Programme of Works: Refurbishment and Remodelling of Pentrehafod School’s Existing Buildings.Report 83 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
RS
Rob StewartLeader of the Council, present
CR
Christine RichardsDeputy Leader of the Council, present
MC
Mark ChildCommittee Member, apologies
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, apologies
JH
Jane HarrisCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, present
CL
Clive LloydCommittee Member, apologies
JR
Jennifer RaynorCommittee Member, present
PR
Phil RobertsOfficer, in attendance
MN
Martin NichollsOfficer, expected

All 21 on the meeting page

On this subject at Swansea

Search all
  1. 21st Century Schools Programme - Purchase Order Variation to include Summer Programme of Works – Refurbishment and Remodelling of Pentrehafod School’s Existing Buildings.This decision
  2. Call-In of Cabinet Decision on 21 February 2019 - Item 9 - 21st Century Schools Programme - New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).Agreed
  3. 21st Century Schools Programme - New Build for Gorseinon Primary School.Approved
  4. 21st Century Schools - Voluntary Aided Schools Major Works Funding - Expression of Interest.Approved
  5. 21st Century Schools Programme – Contract Award and Capital Programme Authorisation for New Build for Education Other Than At School (EOTAS) at Cockett.Approved
  6. 21st Century Schools Programme - New Build for Gorseinon Primary School at Parc Y Werin, Gorseinon, Swansea.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies