RESOLVED that: 1) The site as indicated on plans attached being approximately 3.54 acres be declared as surplus to requirements, 2) Notice be served and the required consultation of communities and other interested parties, about the proposed disposal of land consisting, or forming part, of a playing field, be undertaken in accordance with The Playing Fields (Community Involvement in Disposal Decisions) (Wales) Regulations 2015; 3) If responses / objections to the proposed disposal are received, that a report is brought back to Cabinet to consider those responses / objections; 4) If no responses / objections are received that the Interim Director of Place be authorised to proceed to market the land identified for disposal and report back to Cabinet in due course upon completion of that exercise; 5) The incentive scheme be applied in accordance with the policy. Vacancy
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
The report to Council on the 25 February 2016, Capital Budget and Programme 2015/2016 - 2019/2020 explained there is an ambitious programme of Council asset disposals which shall be used to support not only the 21st Century Schools programme but the General Fund capital programme as a whole.
1.1In the case of land which forms part of school premises, a disposal will only proceed on the basis of agreement with the governing body and then the support of Cabinet on a case by case basis.
1.2The criteria to be applied is as follows;
Primary School Sites more than 4.5 acres based on a generous interpretation of Building Bulletin (BB)99 guidance for a two form entry school; the parcel of land is physically capable of being separated and developed; advice from Planning and Highways indicating that the land has development potential, so identifying the sites which offer the greatest potential capital receipts; confirmation of any legal constraints on the title; other constraints/issues eg current educational and school organisation strategies. Primary School Sites evaluated on an individual basis rather than a generic filter based on site acreage; there are fewer sites to consider and each case is very different; the parcel of land is physically capable of being separated and developed.
1.3The process is as follows:
1.3.1 a formal approach to the governing body to obtain written consent to proceed;
1.3.2 where consent is obtained, proceed to formal evaluation;
1.3.3 the criteria will then be applied fully with the benefit where necessary of more intrusive site surveys. If any shortfall is identified in educational facilities then there would be no further consideration unless the school were supportive of the disposal for security or other practical educational reasons. If no shortfall is identified then the review would proceed to Cabinet;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.