Resolved
RESOLVED that: 1) The overall outturn position be noted and the net under spend of the approved budget of £30.555m be carried forward to 2016-2017.
Cabinet noted this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: 1) The overall outturn position be noted and the net under spend of the approved budget of £30.555m be carried forward to 2016-2017.
1.1The original capital budget approved by Council in February 2015 for 2015/16 totalled £93.195m. During 2015/16 this figure was increased by £26.456m to make a revised budget of £119.651m.
The net increase was the result of:
a) The addition of grant funded schemes after Council approved the original programme, b) Delayed spending from 2014/15. 2. Outturn 2015/2016
2.1Capital outturn in 2015/16 on the approved budget was £89.096m, an in-year under spend (slippage) of £30.555m which is detailed in Appendix A. Apart from a small number of exceptions, the under spends in the capital budget represent delayed spending on approved schemes, which are anticipated to be spent in future years. As such, the unspent budget will need to be carried forward to 2016/17. The main underspends are set out in Appendix C. 2.2 Appendix A shows the breakdown of Capital Expenditure and variances in respect of individual Directorates and highlights the sum of £41.417m spent on Housing Revenue Account properties during the year. 2.3 Notwithstanding the under spending mentioned above, the capital outturn represents a significant expenditure on a number of major projects. Appendix B lists projects with expenditure in excess of £0.5m. 2.4 In addition to the normal Capital programme, during the year 2015/16 the Authority paid a settlement of £73.58m to Welsh Government for the Housing Revenue Account Subsidy System buyout, in line with all other Welsh local authorities who still directly have their own housing stock, and therefore maintain a Housing Revenue Account. This capital spending was funded by access to special rate borrowing facilities from the Public Works Loan Board for this express purpose.
3.12015/2016 expenditure will be financed as follows:-
Financing Requirement £'000 Unfinanced sundry creditors 2014/15 3,114 2015/16 Spend per ledger 89,096 Sundry creditors to be financed in 2016/17 -4,042 Spend to be funded in 2015/16 88,168
Financing 2015/16 £'000 Supported Borrowing 6,356 Unsupported Borrowing 2015-16 2,813 Grants and Contributions 39,761 Revenue contributions 26,787 Capital receipts 12,451 Total financing 2015/16 88,168
4.1There are no legal implications contained within this report 5. Equality and Engagement Implications
5.1There are no equalities implications arising from this report. A full analysis of equalities implications is carried out as part of the annual budget process and any expenditure detailed in this report is on approved schemes.
Background Papers: None.
Appendix: Appendix A - 2015/16 Capital Programme Outturn Summary Appendix B - Capital Projects with spending in excess of £0.5m Appendix C - Capital Projects Underspent in excess of £0.25m 2015/16 Capital Programme Outturn Summary Appendix A
Directorate Comparison Original Revised Outturn Net Over Budget Budget 2015/16 / (Under) 2015/16 2015/16 spending £'000 £'000 £'000 £'000
Resources 2,388 2,321 209 (2,112)
People 15,453 12,951 10,351 (2,600)
Place 75,354 104,379 78,536 (25,843)
Total 93,195 119,651 89,096 (30,555)
Budget Book Comparison Original Revised Outturn Net Over Budget Budget 2015/16 / (Under) 2015/16 2015/16 spending £'000 £'000 £'000 £'000
21st Century Schools 15,173 11,014 9,509 (1,505)
General Fund Services 28,729 60,989 38,170 (22,819)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
08 (2 of ): Appendix BAppendix | 7 KB | Download |
PDF |
08 (3 of 3): Appendix CAppendix | 10 KB | Download |
PDF |
Capital Outturn and Financing 2015/16.Report | 64 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.