Resolved
RESOLVED that the application be accepted and that modification order be made.
Planning Committee decided this item on Tuesday 10 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the application be accepted and that modification order be made.
Report of the Interim Head of Legal and Democratic Services
Planning Committee – 10 January 2017
PUBLIC RIGHTS OF WAY – ALLEGED PUBLIC FOOTPATH ALONG HEOL RHYD, CRAIG CEFN PARC IN THE COMMUNITY OF MAWR
Purpose: To consider whether to accept or reject the application to make a Modification Order to record a public footpath on the Council’s Definitive Map and Statement of Public Rights of Way
Policy Framework: The Countryside Access Plan 2007-2017: Policy No.4.
Statutory Test: Section 53(2) and 53(3)(b) of the Wildlife and Countryside Act 1981
Reason for Decision: The evidence is considered sufficient to satisfy the statutory tests set out in this report and to make a modification order to record the claimed footpath on the Definitive Map and Statement
Consultations: Legal, Finance and Access to Services and all the statutory consultees, including local members, landowners and the prescribed organisations.
Recommendation: It is recommended that the application be accepted and that a modification order be made
Report Author: Kieran O’Carroll
Finance Officer: Paul Roach
Legal Officer: Sandie Richards
Access to Services Phil Couch Officer:
1. Introduction 1.1 An application was made on the 20th October 2010 by Mawr Community Council for a Modification Order to add a public footpath to the Authority’s Definitive Map and Statement at Heol Rhyd, Craig Cefn Parc between registered footpath numbers RN30B and RN31. A plan showing the route claimed A-B and the adjoining registered public footpaths is enclosed at Appendix 1. 1.2 At the time of submission, the application was not made in the correct form. Upon notifying the applicant of the deficiency in the application, the application was resubmitted in the proper manner on 15th April 2011.
1.3Seventeen users have submitted completed evidence questionnaires in support of the application.
1.4The purpose of this report is to establish whether the evidence submitted is sufficient to show that there has been dedication of the route claimed as a public footpath.
The Law 2.1 The application was made under the provisions of the Wildlife and Countryside Act 1981. Section 53(3)(b) requires the Council to modify the Definitive Map and Statement following the expiration of any period such that the enjoyment by the public of a way raises a presumption that the way has been dedicated as a public path.
2.2Section 31 of the Highways Act 1980 raises the presumption that a way has been dedicated as a highway if the route has been used by the public “as of right” (not by force nor stealth nor permission) and without interruption for a period of 20 years unless there is sufficient evidence that there was no intention during that period to dedicate it. This is known as “statutory dedication”.
2.3If the tests for “statutory dedication” are not satisfied, it may be appropriate to consider whether there has been “common law dedication”. This would require consideration of three issues; whether any current or previous owners of the land had the capacity to dedicate, whether there was express or implied dedication and whether there was acceptance of the highway by the public.
2.4For “common law dedication” the landowner would need to have not just acquiesced to public use but in some way facilitated or encouraged that use and a lesser period than twenty years may be sufficient. Evidence of use by the public ‘as of right’ may support an inference of dedication and may also show acceptance by the public.
Preliminary Considerations 3.1 Heol Rhyd is not a highway that is adopted by this Authority. However, the northern and southern sections of Heol Rhyd are recorded as forming part of the public footpath network for the area. This claim is for that section of Heol Rhyd not currently registered as a highway of any description linking those sections recorded with footpath status. To establish a public right of way use must be from one highway to another. This claim easily satisfies this requirement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public Rights of Way: Alleged Public Footpath Along Heol Rhyd, Craig Cefn Parc in the Community of Mawr.Report | 81 KB | DownloadRead as text |
PDF |
R of W APPENDIXAppendix | 1 MB | Download |
PDF |
R of W APPENDIX 1AAppendix | 2.3 MB | Download |
Follow Planning Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Disclosures of Personal and Prejudicial Interests.None | Decided | Open |
| 8 Sep 2026 | Items for deferral/withdrawal.None | Decided | Open |
| 8 Sep 2026 | Determination of Planning Applications under the Town and Country Planning Act 1990.2025/0189/FUL - Approved | Approved | Open |
| 4 Aug 2026 | Disclosures of Personal and Prejudicial Interests.None | Decided | Open |
| 4 Aug 2026 | Minutes.Approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.