RESOLVED that 1. The Public Path Diversion Order made on the 26 th July 2016 be withdrawn; 2. A new Public Path Diversion Order be made on the same terms as the previous order; and 3. Should formal objections be made to any such order made and the Council becomes unable to confirm the order, to refer the order to the Planning Inspectorate for determination.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Purpose: To determine whether to withdraw the existing Public Path Diversion Order made on the 26th July 2016 and make a new Public Path Diversion Order
Policy Framework: Countryside Access Plan 2007-2017
Statutory Test: Section 119 Highways Act 1980
Reason for Decision: Whilst this Committee previously determined to make a Public Path Diversion Order, it appears that at the informal consultation stage some consultees were provided a different and incorrect version of the Diversion Order Plan. The consultations have now been conducted properly with the correct plan sent to all consultees. All consultees have now had the opportunity to comment on the proposed diversion and the objections received are not considered sufficiently cogent to warrant the complete abandonment of the order. Therefore, it is proposed that a new diversion order be made
Consultations: Legal, Finance and Access to Services and all the statutory consultees, including local members, landowners and the prescribed organisations. Recommendation: It is recommended that: -
(1) The Public Path Diversion Order made on the 26th July 2016 be withdrawn; (2) A new Public Path Diversion Order be made on the same terms as the previous order; and (3) Should formal objections be made to any such order made and the Council becomes unable to confirm the order, to refer the order to the Planning Inspectorate for determination
Report Author: Kieran O’Carroll
Finance Officer: James Moore
Legal Officer: Sandie Richards
Access to Services Phil Couch Officer:
Background
1.1The Council previously discovered evidence suggesting that an error existed on the Council’s Definitive Map of public rights of way in relation to the alignment of footpath number 35.
1.2The current definitive line of the footpath is shown A-B-C-D-E on the plan attached to this report at Appendix 1
1.3It was claimed by some of the local residents that no public footpath existed at this location and that it should never have been recorded as a public right of way.
1.4A report was submitted to the Rights of Way and Commons Sub Committee of the Planning Committee on the 10th October 2012 (“the 2012 report”) in order to determine:
(a) whether the evidence submitted by the local residents was sufficient to show that no public footpath existed and whether it should therefore be deleted from the Definitive Map; and (b) if that evidence was insufficient to show that the path should be deleted, whether the current alignment was incorrect and whether there was sufficient evidence to realign the path along another route.
1.5The evidence considered in relation to these issues is set out fully in the 2012 report at Appendix 2 of this report and can be viewed as background information only given that these issues are not the subject of this report.
1.6At the Committee of the 10th October 2012, it was determined that the evidence of local residents was not sufficient to show the path did not exist; therefore the legal presumption that the definitive map is correct in showing a path could not be rebutted and the path was to remain on the Definitive Map.
1.7Whilst Members decided that the current alignment was an error, it was considered that the evidence available was not sufficient to determine the correct alignment. Hence, no modification order could be made for the realignment of the footpath.
1.8Despite the fact that the anomaly could not be rectified based on the available evidence, The Council has a legal duty under the Highways Act 1980 to assert and protect public paths and to ensure they are available for public use. Therein lay a problem as the definitive line of the path was already known to be incorrect or at least very likely to be incorrect.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.