Capital Maintenance Report 2017/18.

Approved Executive 3 papers

Cabinet approved this item on Thursday 16 March 2017. Below is the council's own wording, with the papers it was decided on.

Item182

Resolved

RESOLVED that Cabinet: 1. Approved the proposed capital maintenance schemes as listed in Appendix A; 2. Authorised the financial implications identified in Appendix B to be included in the Capital Programme.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Next Generation Services

Cabinet – 16 March 2017

CAPITAL MAINTENANCE REPORT 2017/18

Purpose: To agree the schemes to be funded through the Capital Maintenance programme

Policy Framework: The Revenue and Capital Budget as reported to and approved by Council on the 23 February 2017

Reason for Decision: To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals) to commit and authorise schemes as per the Capital programme.

Consultation: Finance Legal Access to Services Education Recommendations that Cabinet: 1) Approves the proposed capital maintenance schemes as listed in Appendix A.

2) Authorises the financial implications identified in Appendix B to be included in the capital programme.

Report Author: Andrew Shaw

Finance Officer: Paul Roach (Revenue) Jayne James (Capital)

Legal Officer: Debbie Smith

Access to Services Officer: Phil Couch

1.0Introduction

Cabinet has previously approved the Council’s Asset Management Plan for Property Assets which sets out a series of measures to improve the management and performance of the property portfolio. This Report sets out the way in which the Capital Maintenance resources for 2017/18 will be deployed. 2.0 Capital Programme Process

On 23 February 2017, Council approved a Capital Maintenance allocation of £4 Million for the financial year 2017/2018, together with an additional £1 Million for further Schools Capital Maintenance. The priority list of projects allocated against the £4 Million budget is identified within this report. The priority list of projects allocated against the additional £1 Million budget will be subject to a separate report to Cabinet.

3.0Objectives of Scheme

3.1The proposals set out will directly support the corporate objectives of the Authority, in relation to the maintenance and improvement of the Authority’s building portfolio.

3.2This maintains the previous commitment to address the significant backlog of maintenance and minimise the potential effect of unforeseen breakdowns of building elements.

3.3As was reported in previous building maintenance programme reports, attention needs to be drawn to the fact that the Authority still has a significant backlog of maintenance and whilst there have been some reductions in this backlog, the limited programme contained within the 2017/18 budget, whilst being very important, will not remedy the immediate backlog which still amounts to in excess of £234m.

Notwithstanding the current financial pressures, further budget provisions will therefore need to be made in subsequent years to maintain this investment and minimise the risks of failure and unplanned closures.

3.4The list of identified schemes (Appendix A) has been selected on a priority basis. The criteria for selection (unless otherwise stated) was based upon Condition rating, Legislative compliance, Health and Safety implications, likelihood of failure and business continuity. Whilst all schemes have been selected on these criteria there are a number of similar priorities which we are unable to progress within the budgets available.

4.0Description of Schemes

4.1The recommended list of schemes is included in Appendix A and to assist, a brief summary of the planned works have been included as follows:-

1a) Statutory Compliance - Electrical The schemes listed consist of total rewires, partial rewires or upgrades to ensure safety and compliance with electrical regulations and maintained operation of the premises.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23 (2 of 3): Appendix AAppendix 12 KB Download
PDF
23 (3 of 3): Appendix BAppendix 52 KB Download
PDF
Capital Maintenance Report 2017/18.Report 96 KB DownloadRead as text

At this meeting

Whole meeting
162Minutes.Approved 167Swansea City Centre Regeneration – Delivery and Funding Strategy.Approved 169Castle Square Development and Public Realm Opportunity.Noted 171Family Support Services Commissioning Review – Options Appraisal Report (Gateway 2) for the Under 11’s Cluster of the Commissioning Review.Decided 173Family Support Services Commissioning Review – Options Appraisal Report (Gateway 2) for the Over 11’s Cluster of the Commissioning Review.Decided 174Quarter 3 2016/17 Performance Monitoring Report.Noted 175Well-Being Objectives & Statement 2017/18.Approved 176Cam Nesa - European Social Fund - Grant Acceptance.Approved 177Free Childcare for 3 and 4 Year Olds Pilot.Approved 178Housing General Fund (HGF) Disabled Facilities and Improvement Grant Programme 2017/18.Approved 179Annual Review of Charges (To Apply 2017/18) - Social Services.Decided 180Report on the Western Bay Principles of Prevention Framework and the Prevention Strategy for Swansea.Approved 181FPR7 - Capital Allocation to Highway Infrastructure Assets 2017-18.Approved
182Capital Maintenance Report 2017/18.This decision
183Local Authority Governor Appointments.Approved 184Tackling Poverty Scrutiny Inquiry.Decided 185A Revised Tackling Poverty Strategy for Swansea.Approved 186FPR7 – The Kingsway Infrastructure Project.Noted 187Exclusion of the Public.Decided 188Acquisition of Property to Facilitate City Centre Regeneration.Private 189FPR7 Amendment – Vibrant and Viable Places Programme, Swansea City Centre.Private

Who was there

8 of 24 attended
RS
Rob StewartChair, present
CR
Christine RichardsCommittee Member, present
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, present
JH
Jane HarrisCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, apologies
CL
Clive LloydCommittee Member, apologies
JR
Jennifer RaynorCommittee Member, present
CS
Chris SiversOfficer, expected
MN
Martin NichollsOfficer, expected

All 24 on the meeting page

On this subject at Swansea

Search all
  1. Capital Maintenance Report 2017/18.This decision
  2. Buildings Capital Maintenance Programme 2026/27.Approved
  3. Building Capital Maintenance Programme 2025/26.Approved
  4. Financial Procedure Rule 7 – Additional Capital Maintenance Grant (Schools) 2024/25.Approved
  5. Building Capital Maintenance Programme 2024/25.Approved
  6. Building Capital Maintenance Programme 2023/24.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open