Cabinet, Thursday 19 March 2026 at 10.00am

Buildings Capital Maintenance Programme 2026/27.

Approved Executive 2 papers

AI summaryCabinet approved the 2026/27 buildings capital maintenance programme with £4,308,000 of core funding and over £4m in Welsh Government education grants, retaining £500,000 for emergencies.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCore and grant-funded schemes approved
Money£4,308,000 core plus WG grants£4,214,000 2026-27 plus £94,000 carried forward
What happens nextDelivery of listed schemesHead of Service to agree scheme profiles
Who it affectsCouncil education and public estateBuilding maintenance backlog

What was decided

Cabinet approved the 2026-27 core capital allocation of £4,308,000 to the schemes listed in Appendix A, column I.

Cabinet approved accepting a £1,174,549 increase to the 2025-26 Welsh Government Education Repairs and Maintenance Grant, notified in February 2026, and a further £1,101,140 variation to support the Universal Free School Meals programme and further education maintenance.

Cabinet approved the list of 2026-27 education schemes funded by the confirmed Welsh Government grant of £1,777,438, and agreed to retain £500,000 of core funding as a rolling Building Maintenance Contingency for unforeseen emergency works.

Why

The education and public estate carries a significant backlog of maintenance, and the programme prioritises the buildings most at risk. Report P2

The council's core allocation does not always match the logistical profile of scheme planning and delivery, so flexibility is needed in how funds are deployed.

What happens next

The Head of Building Services and Waste, in consultation with the Cabinet Member for Service Transformation, will agree the profile of schemes within approved funding and keep Cabinet updated through existing governance and formal reporting.

Draw-downs from the £500,000 contingency will be agreed between the Head of Building Services and Waste and the Cabinet Member for Service Transformation.

The money

  • £4,308,000 Core capital funding allocation for 2026-27
  • £4,214,000 2026-27 core budget allocation
  • £94,000 Unallocated carry forward from 2025-26
  • £1,174,549 Welsh Government variation increase to 2025-26 Education Repairs and Maintenance Grant, notified February 2026
  • £1,101,140 Further Welsh Government variation to 2025-26 Education R&M Grant, supporting Universal Free School Meals and further education maintenance
  • £1,777,438 Confirmed Welsh Government 2026-27 education capital maintenance grant
  • £500,000 Retained from core funding as a rolling Building Maintenance Contingency
  • £5,279,946 Total value of programme of works laid out in Appendix A Report P1
  • £1,065,947 Carried forward against schemes from 2025-26, subject to out-turn Report P1
  • £2.2m-£4m Possible further Welsh Government grant funding subject to confirmation Report P1

Options considered

  • Chosen: Approve core 2026-27 capital maintenance programme and accept Welsh Government education grant variations and 2026-27 grant. Needed to fund priority schemes across the education and public estate and to access confirmed Welsh Government funding Report P1, P2

Implications

  • Financial: Total programme of works laid out in Appendix A is valued at £5,279,946, and may increase by a further £2.2m-£4m if additional Welsh Government grants are confirmed. Report P1
  • Risk: The education and public estate carries a significant backlog of maintenance; works have been prioritised to focus on the most at-risk buildings. Report P2
  • Other: There are no legal or governance implications beyond those identified in the report. Report P4

Who and where

  • Council education estate Report P2
  • Council public estate Report P2

Timeline

  • February 2026: Welsh Government increased the 2025-26 Education Repairs and Maintenance Allocation Grant by a further £1,174,549
  • 2026/27: Core capital maintenance programme and education schemes funded by the confirmed Welsh Government 2026-27 grant of £1,777,438 to be delivered

Plain English for the jargon

  • WG: Welsh Government
  • R&M (Repairs and Maintenance) Allocation Grant: Welsh Government grant funding for education buildings repairs and maintenance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item153

Resolved

Resolved that: 1) Cabinet approved the 2026-27 Council agreed allocation of the core capital funding of £4,308,000 (£4,214,000 from 2026-27 budget and £94,000 carried forward from 2025-26) to the schemes highlighted in red in column I of Appendix A. 2) Cabinet approved the receipt of all confirmed Welsh Government grant for education capital maintenance and to substitute the corresponding core funding back within the building maintenance programme due to the following: i) Increasing the building maintenance programme by accepting WG’s variation to the 2025-26 Education Repairs and Maintenance Allocation Grant which has been increased by a further £1,174,549 in February 2026 and approving the list of schemes in red in column D of Appendix A) to be funded from this expenditure. ii) Increasing the building maintenance programme by accepting a further variation of the 2025-26 Education Repairs and Maintenance Allocation Grant by £1,101,140, to be used to support the delivery of the Universal Free School Meals programme (which is primarily funded by WG ) and further education capital maintenance projects as appropriate (identified in red in column G of Appendix A) and in line with grant conditions. 3) Approving the list of education schemes in red in column H to be delivered against the WG 2026-27 grant which has been confirmed at £1,777,438 and will form part of the capital maintenance programme. 4) Cabinet acknowledged that schemes can only be delivered within the core building maintenance allocation and where additional funds are secured. Furthermore, that the use of the available resources does not always match the logistical profile of scheme planning and delivery but that the Head of Building Services and Waste in consultation with the Cabinet Member for Service Transformation will agree the profile of schemes within approved programme funding and keep cabinet updated as part of existing governance and formal reporting. As part of this it is proposed to retain and not allocate £500,000 of the core funding to specific projects, but to use as rolling Building Maintenance Contingency to cover unforeseen emergency works. The draw down of this contingency would be agreed between the Head of Building Service and Waste in consultation with the Cabinet Manager for Service Transformation.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Economy, Finance and Strategy

Cabinet – 19 March 2026

Buildings Capital Maintenance Programme 2026/7 Executive Summary Purpose of Report:

To approve schemes to be funded through the Buildings Capital Maintenance Programme 2026-27 and ensure compliance with Financial Procedure Rule No.7 (Capital Programming and Appraisals).

Recommendation(s). It is recommended that:

1) Cabinet approves the 2026-27 Council agreed allocation of the core capital funding of £4,308,000 (£4,214,000 from 2026-27 budget and £94,000 carried forward from 2025-26) to the schemes highlighted in red in column I of Appendix A. 2) Cabinet approves the receipt of all confirmed Welsh Government grant for education capital maintenance and to substitute the corresponding core funding back within the building maintenance programme due to the following:- i) Increasing the building maintenance programme by accepting WG’s variation to the 2025-26 Education Repairs and Maintenance Allocation Grant which has been increased by a further £1,174,549 in February 2026 and approving the list of schemes in red in column D of Appendix A) to be funded from this expenditure; ii) Increasing the building maintenance programme by accepting a further variation of the 2025-26 Education Repairs and Maintenance Allocation Grant by £1,101,140, to be used to support the delivery of the Universal Free School Meals programme (which is primarily funded by WG ) and further education capital maintenance projects as appropriate (identified in red in column G of Appendix A) and in line with grant conditions; 3) Approving the list of education schemes in red in column H to be delivered against the WG 2026-27 grant which has been confirmed at £1,777,438 and will form part of the capital maintenance programme; and 4) Cabinet acknowledges that schemes can only be delivered within the core building maintenance allocation and where additional funds are secured. Furthermore, that the use of the available resources does not always match the logistical profile of scheme planning and delivery but that the Head of Building Services and Waste in consultation with the Cabinet Member for Service Transformation will agree the profile of schemes within approved programme funding and keep cabinet updated as part of existing governance and formal reporting. As part of this it is proposed to retain and not allocate £500,000 of the core funding to specific projects, but to use as rolling Building Maintenance Contingency to cover unforeseen emergency works. The draw down of this contingency would be agreed between the Head of Building and Waste in consultation with the Cabinet Manager for Service Transformation.

Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why

Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☒ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☒ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☐ Not Applicable

Relevance to Corporate Plan Wellbeing Objectives: Having well-maintained buildings which are fit for purpose underpins all Council activity. A coordinated and proactive approach to building repairs ensures business and service continuity and ongoing statutory compliance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09: Appendix A: List of Schemes: Building Cap MaintAppendix 205 KB Download
PDF
Buildings Capital Maintenance Programme 2026/27.Report 169 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 28 attended
CA
Cyril AndersonCommittee Member, present, as expected, virtual
AA
Alyson AnthonyCommittee Member, apologies
JD
Jeffrey DongOfficer, expected
HE
Huw EvansOfficer, present
PF
Patrick FletcherOfficer, expected
RF
Rebecca FogartyCommittee Member, present, as expected, virtual
LG
Louise GibbardCommittee Member, present
HG
Hayley GwilliamCommittee Member, present, as expected, virtual
AH
Andrea HarringtonCommittee Member, present
DH
David HopkinsCommittee Member, present
DH
David HowesOfficer, expected
RJ
Rhodri JonesOfficer, expected

All 28 on the meeting page

On this subject at Swansea

Search all
  1. Buildings Capital Maintenance Programme 2026/27.This decision
  2. Contract Award and Capital Programme Authorisation for the Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings.Approved
  3. 21st Century Schools Programme - Contract Award and Capital Programme Authorisation for the Design and Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings. 21st Century Schools Update - FPR 7 - Pentrehafod Comprehensive.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies