Resolved that 1) the a new Section 106 Planning Obligation be entered into to provide the public realm / public open space together with a children’s play area on the three identified areas within the SA1 Swansea Development area subject to the receipt of the financial payment from Welsh Government to the sum of £1,000,000.00 to cover the design, laying out and future maintenance costs of the provision. 2) the approach cited above be agreed by Planning Committee and delegated powers be given to the Head of Planning and City Regeneration to agree the details of the Section 106 Planning Obligation with Welsh Government.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
1.1The Section 106 Agreement dated 19 August, 2003 (ref:2002/1000), entered into between the Council of the City and County of Swansea and the former Welsh Development Agency (predecessor to the Welsh Ministers), requires (at clause 6 of the Third Schedule):
The provision of five Children’s Play Areas to equate to a standard of 0.8 hectares per 1000 persons of populations within the Development or agreed equivalent within the Development and the future maintenance of the same by way of a commuted sum to be agreed with the Council as part of the Reserved Matters (such approval not to be unreasonably withheld or delayed) in accordance with Condition 1. Before the occupation of the final unit on the Development the Developer shall transfer and dedicate to the Council the said Children’s Play Areas in perpetuity without any encumbrances and at a nil consideration.
1.2The Welsh Government (Welsh Ministers) would now like to conclude this matter, and as an alternative to the Welsh Government designing, laying out and providing these public open spaces, the Welsh Government has instead offered to:
To dedicate at nil cost three identified areas of proposed public open space to the Council To make a payment to the Council for an appropriate sum of money to be used by the Council for the purposes of designing, laying out and maintaining the three areas of public open space.
2.0Context
2.1The development of the SA1 Swansea Waterfront area has been a key element in the Council’s Strategy for the regeneration of Swansea as a vibrant and distinctive Waterfront City. A robust and comprehensive policy context for considering proposals within the SA1 development area is set out within the Port Tawe Swansea Docks SPG (Sept. 2002), which was augmented by the Outline Planning Permission (Ref: 2002/1000) and the approved Design and Development Framework (August 2004 Version 5) and the Masterplan contained therein established the comprehensive land use and urban design guidance for the purpose of considering planning applications and reserved matters applications.
2.2The outline planning permission has been implemented and there has been significant development within the area which has been supported by a large investment in the site’s infrastructure. In terms of public open space / public realm provision, this has resulted in the following:
Technium Square incorporating the Merchant’s Seamen’s War Memorial; Ice House Square – adjacent to the Sailbridge; Market Square – adjacent to the Premier Inn / Waterfront Restaurant; and Provision of the 6m wide public walkway around Prince of Wales Dock
2.3Since the original permission was granted, due to the success of the development and market changes led to pressure to alter the proposed land use mix and a Section 73 permission was granted in 2010 (Ref: 2008/0996) which revised the approved Land Use Masterplan (Figure A2.1) which has been used to guide development since then. In terms of the provision of the public open space, the following changes are relevant:
The reduction in plot densities at the eastern end of the site along Langdon Road to provide residential / townhouses with gardens are now proposed on plots D9, D10, E4 & E5; The relocation of the largest area of open space from the north of Langdon Road to the south of the road. A new area of open space is now provided between plots E5 and E6.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.