Resolved
Resolved that: 1) The Local Transport (LTF) schemes, together with their financial implications be approved.
Cabinet approved this item on Thursday 15 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) The Local Transport (LTF) schemes, together with their financial implications be approved.
Report of the Cabinet Member for Environment Services
Cabinet – 15 February 2018
Financial Procedure Rule 7 Local Transport Fund Grant 2017/18 Purpose: To confirm the bid for Local Transport Fund (LTF) Grant and seek approval for expenditure on the proposed schemes and projects in 2017/18.
To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals): to commit and authorise schemes in the Capital Programme.
Policy Framework: Local Transport Plan 2015 – 2020
Consultation: Access to Services, Finance, Legal.
Recommendation(s): It is recommended that: -
1) The LTF schemes, together with their financial implications, are approved.
Report Author: Ben George
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Catherine Window 1. Introduction
1.1A funding bid for the Local Transport Fund (LTF) was submitted to the Welsh Government on 17th February 2017 in accordance with guidance from the Welsh Government. The guidance stated that there was a total funding pot of £19.8m and this would be allocated to schemes across Wales.
1.2The City & County of Swansea submitted bids totalling £4.4million and the Welsh Government ultimately awarded funding amounting to £1.2million. This allocation was committed to the capital programme following approval by Cabinet on 20th July 2017.
1.3The Welsh Government subsequently made a mid-year allocation to the City & County of Swansea’s Local Transport Fund 2017/18.
1.4This report seeks approval to commit these additional funds to the capital programme in accordance with the Financial Procedure Rules.
2. Submitted Bids
2.1A total of £4,313,000 was bid for by the City & County of Swansea and the Welsh Government has subsequently allocated £1,110,440 spread across four schemes for 2017/18. The bid schemes and the successful funding allocations are shown in the tables below:
Table One – Summary of LTF Bids 2017/18 Match Total Total Scheme funding project LTF (£k) (£k) cost (£k) Baldwins Bridge Interchange 1541 0 1541 Links to NCN 1267 0 1267 Strategic Bus Corridors 1432 110 1542 Kingsbridge Cycle Link 73 0 73 Active Travel Mapping (see 3.3) 18 0 18 Total 4331 110 4441 Table Two – Summary of Allocations for Successful LTF Bids 2017/18 Match Total Total Scheme funding project LTF (£k) (£k) cost (£k) Baldwins Bridge Interchange 541 0 541 Links to NCN 364 0 364 Strategic Bus Corridors 115 110 225 Kingsbridge Cycle Link 73 0 73 Active Travel Mapping (see 3.3) 18 0 18 Total 1111 110 1221
2.2The match funding requirement shown above is from a contribution from Revenue in 2016/17. This funding is revenue underspend from 2016/17 which has been capitalised to support the delivery of these capital assets in 2017/18. (See also the attached appendices).
2.3Following these initial bids and allocations, which were made in February and March 2017 respectively, a further mid-year allocation was received from the Welsh Government in service of Swansea Urban Connections. This project will deliver improvements to the walking and cycling infrastructure. This additional allocation amounted to £200,000. The table below therefore summarises the final Welsh Government allocation for the Local Transport Fund 2017/18.
Table Three – Summary of Allocations for LTF 2017/18 Match Total Total Scheme funding project LTF (£k) (£k) cost (£k) Baldwins Bridge Interchange 541 0 541 Links to NCN 364 0 364 Strategic Bus Corridors 115 110 225 Kingsbridge Cycle Link 73 0 73 Active Travel Mapping 18 0 18 Swansea Urban Connections 200 0 200 Total 1311 110 1421
3. Details of Approved Schemes
3.1The projects approved for funding are summarised below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Procedure Rule 7 Local Transport Fund Grant 2017/18.Report | 233 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.