Resolved
Resolved that: 1) The net under spending of the approved budget of £26.019m be carried forward to 2018-2019; 2) The main reasons for the under spend as outlined within Appendix C of the report be noted.
Cabinet approved this item on Thursday 19 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) The net under spending of the approved budget of £26.019m be carried forward to 2018-2019; 2) The main reasons for the under spend as outlined within Appendix C of the report be noted.
1.1The original capital budget approved by Council in February 2017 for 2017/18 totalled £106.944m (excluding the waste provision). During 2017/18 this figure was increased by £5.289m to give a revised budget of £112.233m (excluding waste provision), which represented one of the largest capital programmes approved by Swansea Council.
The net increase in the capital budget was the result of: a) The addition of both grant funded and Council funded schemes after Council approved the original programme, b) Delayed spending from 2016/17 carried forward into 2017/18. 2. Outturn 2017/2018
2.1Capital outturn in 2017/18 on the approved budget was £86.214m, an under spend of £26.019m which is detailed in Appendix A. Apart from a small number of exceptions, the under spends in the capital budget represent delayed spending on approved schemes. As such, the unspent budget will need to be carried forward to 2018/19 in order to complete schemes in progress. 2.2 It should be recognised that capital schemes are complex projects which are often faced with a host of issues including legal issues (planning, procurement, lease terms etc.) and operational issues (budget, ground conditions, weather, supply chain), which can offer challenges to the delivery timetable. The main underspends are set out in Appendix C. 2.3 Appendix A shows the breakdown of Capital Expenditure and variances in respect of individual Directorates and highlights the sum of £45.835m spent on HRA properties during the year. 2.4 Notwithstanding the under spending mentioned above, the capital outturn represents a significant expenditure on a number of major projects. Appendix B lists projects with expenditure in excess of £0.5m.
3.12017/2018 capital expenditure will be financed as follows:-
Financing Requirement £'000 Unfinanced sundry creditors 2016/17 3,153 2017/18 ledger capital spend 86,214 To be financed sundry creditors 2018/19 -3,096 Spend to be funded in 2017/18 86,271
Financing 2017/18 £'000 Supported Borrowing 8,747 Unsupported Borrowing (GF plus HRA) 2017-18 19,220 GF capital receipts 5,145 Grants and Contributions 23,103 Revenue contributions to capital 29,742 Earmarked capital receipts 314 Total financing 2017/18 86,271
4.1There are no legal implications. 5. Equality & Engagement Implications
5.1There are no equalities implications arising from this report. A full analysis of equalities implications is carried out as part of the annual budget process and any expenditure detailed in this report is on approved schemes.
Background Papers: None
Appendices: Appendix A - 2017/18 Capital Programme Outturn Summary Appendix B - Capital Projects Appendix C - Capital Projects Underspent 2017/18 Capital Programme Outturn Summary Appendix A
Directorate Comparison Original Revised Outturn Net Over Budget Budget 2017/18 / (Under) 2017/18 2017/18 spending £'000 £'000 £'000 £'000
Resources 1,142 3,608 1,742 (1,866)
People 17,838 11,928 10,534 (1,394)
Place 87,964 96,697 73,938 (22,759)
Total 106,944 112,233 86,214 (26,019)
Budget Book Comparison Original Revised Outturn Net Over Budget Budget 2017/18 / (Under) 2017/18 2017/18 spending £'000 £'000 £'000 £'000
21st Century Schools 11,988 9,073 7,944 (1,129)
General Fund Services 35,697 51,274 32,435 (18,839)
HRA 59,259 51,886 45,835 (6,051)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Outturn and Financing 2017/18Report | 144 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.