Cabinet, Thursday 16 July 2026 at 10.00am

Capital Outturn and Financing 2025/2026.

Decided Executive 1 paper

AI summarySwansea Council Cabinet agrees to carry forward £47.745 million net capital underspend and slippage from 2025/2026 into 2026/2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNet underspend and slippage moved to 2026/2027
Money£47.745mNet underspend or slippage on 2025/2026 capital programme
What happens nextBudget carried into 2026/2027Unspent balances to be reviewed and reprofiled
Who it affectsCapital projects across all directoratesMajor slippage in Place and HRA Capital

What was decided

The net underspend and slippage of £47.745 million on the 2025/2026 capital programme is to be carried forward into 2026/2027.

Why

Major projects such as City Centre Acquisitions (Debenhams), Skyline, Lower Swansea Valley and 71-72 Kingsway Offices had contractual or design delays. Report P22, P24, P25

What happens next

Unspent project balances, including retention payments on 71-72 Kingsway, Castle Square and City Centre Acquisitions, will be carried forward and reviewed during 2026/2027. Report P22, P23, P24

Several budgets, including Lower Swansea Valley and Universal Primary Free School Meals, are to be reprofiled after further cabinet reports or funding negotiations. Report P16, P25

The money

  • £47.745m Net underspend and slippage on 2025/2026 capital programme carried forward Report P9, P14

Options considered

  • Chosen: Carry forward the £47.745 million net underspend and slippage into 2026/2027. Allows delayed projects and reprofiled budgets to continue into the next financial year

Implications

  • Risk: Several major regeneration projects (Skyline, City Centre Acquisitions, Lower Swansea Valley) carry significant slippage and depend on further contractual or funding progress. Report P24, P25
  • Other: City Centre Acquisitions value of £13.351m was overstated by £7m, which has been moved to Finance as contingency. Report P24

Who and where

  • Place directorate, accounting for the largest share of slippage Report P8
  • General Fund Services capital programme Report P12
  • HRA Capital programme, including housing maintenance and More Homes Report P13, P26, P27
  • Education directorate, including 21st Century Schools Report P6, P11
  • Major regeneration projects including Swansea Central, 71-72 Kingsway, Castle Square, City Centre Acquisitions, Skyline and Lower Swansea Valley Report P15, P22, P23, P24, P25

Timeline

  • July 2026: Tenant fit-out for 71-72 Kingsway Flex operator scheduled for completion Report P22
  • 2026-07-16: Cabinet decision to carry forward the net underspend
  • 2026/2027: Unspent balances and reprofiled budgets to be used, with a further cabinet report on Gowerton Comp expected in July 2026 Report P16

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account for council housing
  • MAG: Minor Adaptations Grant, small housing adaptations for disabled residents
  • DFG: Disabled Facilities Grant, mandatory grants for home adaptations
  • MSCP: Multi-Storey Car Park
  • 3G Pitch: Third Generation artificial sports pitch
  • LTF: Local Transport Fund, Welsh Government transport funding stream
  • WG: Welsh Government
  • RIBA: Royal Institute of British Architects (used here to denote design stage)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42

Resolved

Resolved that: 1) The net underspend / slippage of budget of £47.745m be carried forward to 2026/2027.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Director of Finance & S151 Officer

Cabinet – 16 July 2026

Capital Outturn and Financing 2025/2026 Executive Summary Purpose of Report: To report on the detailed capital outturn and financing for 2025/26

Recommendation(s). It is recommended that: 1) Cabinet approves the net underspend / slippage of budget of £47.745m is carried forward to 2026/2027.

Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution.

Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☒ Not Applicable

Relevance to Corporate Plan Wellbeing Objectives: This report details the capital outturn of the Council as a whole, detailing the spend against key projects that are intended to support a wide variety of the priority objectives in the Corporate Plan. The report summarises how the expenditure in the year is financed across the programme.

Reviewed and approved by: Access to Services, Finance, Legal, Relevant Cabinet Member.

Report Author & Job Title: Simon Arthurs, Interim Head of Finance / Deputy S151 Officer 1. Introduction

2. The original capital budget for 2025/2026 totalled £154.645m and was approved by Council on 6 March 2025. During 2024/2025 this figure was increased by £46.094m to give a revised budget of £200.739m. These figures exclude the Waste Provision.

3. The net increase in the capital budget was mainly the result of:

• The addition of both grant funded and Council funded schemes after Council approved the original programme. • Delayed or reprofiled spending from 2024/2025 carried forward into 2025/2026.

4. Outturn 2025/2026

5. Capital outturn in 2025/2026 total £152.994m based on the revised approved budget of £200.739m. This represents a significant amount of expenditure aimed at meeting the Councils ambitious Corporate Plan priorities.

6. The expenditure analysed by spend is show in the table below.

Budget Comparison Original Revised Outturn Net Over / Budget Budget 2025/26 (Under) 2025/26 2025/26 spending £'000 £'000 £'000 £'000

Education (including 21st Century Schools) 7,471 10,788 7,326 (3,462)

General Fund Services 91,125 135,922 100,357 (35,565)

HRA Capital 56,048 54,029 45,311 (8,718)

Total 154,645 200,739 152,994 (47,745)

7. Appendix A shows the summary of expenditure across the fund and by Directorate. Noting the finance director holds programme contingency which whilst allocated has not been drawn yet.

8. Net underspending represents a combination of underspending/overspending and slippage. As this forms part of the capital programme already approved by Council and approved projects added to the programme the balances will be assessed so that projects in progress can continue or capital contingency increased to meet any unavoidable cost pressures in the current programme. Project budgets will then be subject to reprofiling and reported in the 2026/27 formal quarterly reporting. £7m savings on the Debenhams scheme have been moved back to programme contingency within Finance for future consideration once the Q1 position is known. With the inclusion of £7million variation from Debenhams, the target of 80% is met.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn and Financing 2025/2026.Report 215 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 28 attended
CA
Cyril AndersonCommittee Member, present, as expected, virtual
AA
Alyson AnthonyCommittee Member, present, as expected, virtual
SA
Simon ArthursOfficer, expected
HE
Huw EvansOfficer, present, as expected, virtual
PF
Patrick FletcherOfficer, expected
RF
Rebecca FogartyCommittee Member, present, as expected, virtual
HG
Hayley GwilliamCommittee Member, present, as expected, virtual
AH
Andrea HarringtonCommittee Member, present, as expected, virtual
DH
David HopkinsCommittee Member, present, as expected, virtual
DH
David HowesOfficer, expected
RJ
Rhodri JonesOfficer, expected
EK
Elliott KingCommittee Member, present, as expected, virtual

All 28 on the meeting page

On this subject at Swansea

Search all
  1. Capital Outturn and Financing 2025/2026.This decision
  2. Capital Outturn and Financing 2022/23.Decided
  3. Capital Outturn and Financing 2021/22.Decided
  4. Capital Outturn and Financing 2020/21.Noted
  5. Capital Outturn and Financing 2018/19.Approved
  6. Capital Outturn and Financing 2017/18Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open