Resolved that: 1) The overall Capital Development principles be approved together with their financial implications; 2) Authority is given to draw down the Capital borrowing and to authorise the schemes contained within the Capital Development principles; 3) A Project monitoring mechanism be developed to manage the individual schemes with appropriate officer representation and sign off process; 4) Grant funding opportunities be explored in partnership with Parkwood Leisure to reduce the amount of capital borrowed and repayment costs to the Council.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Investment, Regeneration and Tourism
Cabinet - 20 December 2018
FPR 7 Capital Development Proposals for Plantasia in Partnership with Parkwood Leisure Purpose: To confirm level of funding for the Plantasia capital development proposals in partnership with Parkwood Leisure To comply with Financial Procedure Rule No 7 (Capital Programming and Appraisals) to commit and authorise the schemes, as set out in the Tender from Parkwood Leisure, within the Council’s Capital programme.
Policy Framework: Sustainable Swansea – fit for the future.
Consultation: Legal, Finance, Access to Services
Recommendation(s): It is recommended that: 1) The overall Capital Development principles are approved together with their financial implications.
2) Authority is given to draw down the Capital borrowing and to authorise the schemes contained within the Capital Development principles.
3) A Project monitoring mechanism is developed to manage the individual schemes with appropriate officer representation and sign off process.
4) Grant funding opportunities are explored in partnership with Parkwood Leisure to reduce the amount of capital borrowed and repayment costs to the Council.
Report Author: Jamie Rewbridge
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Rhian Millar
1. Introduction and background
1.1As a culmination of the Cultural services commissioning review and subsequent procurement exercise, a decision to appoint Parkwood Leisure as preferred bidder for Plantasia, under a 15 year contract, was made by Cabinet on 21 June 2018.
1.2Plantasia has been operating on a reduced budget since 2014/15, when previous management put forward closure and alternative operating options which were subsequently rejected by Members, but which led to a reduction of £100k of its operating budget nonetheless.
1.3Current and previous performance of the facility shows an outturn of £190k cost to the Council in 16/17, against a budget of £130k, therefore £60k overspend.
1.4At financial closing in 17/18 Plantasia showed an outturn of £275k cost to the Council, against a budget of £149k, a £126k overspend. These costs were higher than expected due to the ongoing delays in relation to the café and general site disruptions, causing loss of income.
1.5Despite strict adherence to budget controls, the costs of operating the facility and providing adequate customer care and animal welfare are unable to be met by the current budget provision. In order to deliver a balanced budget, this necessitates reduced spend in other parts of the Service accordingly, creating further risk to adequate service provision.
1.6Through the various stages of the procurement process it was evidenced that no option would deliver a nil cost revenue outcome in the medium term. This was noted and accepted, along with the knowledge that there are likely to be significant costs of £500k-£1m to close the facility.
1.7At Final Tender stage, the affordability limit was increased to £150k per annum cost to the Council and further savings targets removed from the MTFP.
1.8There was only one submission for Plantasia, from Parkwood Leisure who presented a bid which improved the existing position to £149,891 cost per annum to CCS, just below the affordability position of £150k. However, this was on the basis that they were successful in Lot 1, which they were not. The submission was based upon an average management fee of £79,891, plus capital repayments of £70,000 on prudential borrowing of £1M to invest into the facilities and attractions.
1.9Through dialogue and clarification, the capital investment requirement has now increased to £1.1M. Whilst actual borrowing costs will depend on the interest rate on the day of borrowing, the use of 7% is to provide a ball-park figure for comparison purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.