Cabinet, Thursday 20 December 2018 at 10.00am

FPR7 – Broadway Interchange - Local Transport Fund Grant 2018/19.

Approved Executive 1 paper

Cabinet approved this item on Thursday 20 December 2018. Below is the council's own wording, with the papers it was decided on.

Item124

Resolved

Resolved that the Broadway Interchange Project, together with its financial implications are approved.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Environment & Infrastructure Management

Cabinet – 20 December 2018

FPR 7 – Broadway Interchange Local Transport Fund Grant 2018/19 Purpose: To confirm the bid for additional Local Transport Fund (LTF) monies and seek approval for expenditure on the Broadway Interchange project in 2018/19.

To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals): to commit and authorise schemes in the Capital Programme.

Policy Framework: Local Transport Plan 2015 – 2020

Consultation: Access to Services, Finance, Legal.

Recommendation(s): It is recommended that.

1) the Broadway Interchange Project, together with its financial implications, are approved.

Report Author: Ben George

Finance Officer: Ben Smith

Legal Officer: Caritas Adere

Access to Services Officer: Catherine Window

1.0Introduction / Background

1.1A funding bid for the Local Transport Fund & Local Transport Network Fund (LTF & LTNF) was originally submitted to the Welsh Government on 25th January 2018 in accordance with guidance from the Welsh Government. The funding bid was ultimately approved by the External Funding Panel and the Council was successful in securing £1.856million for the development and delivery of four schemes.

1.2The Welsh Government ordinarily invite bids once per annum for Local Transport Fund, but additional funding has recently been announced and consequently a second invitation to bid was issued to Welsh Local Authorities on 3rd October 2018, with a closing deadline of 22nd October 2018.

1.3The guidance stated that there was a total funding pot of £78million for the Local Transport Fund (£26million per year for 2018/19 to 2020/21). This funding is available to all Welsh Local Authorities. Whilst match funding is not a requirement of the funding bids, it was made clear that those schemes that benefited from match funding would be more likely to receive an LTF allocation.

1.4The City & County of Swansea submitted bids totalling £85k, and the Welsh Government ultimately awarded funding amounting to £85k for FY2018/19.

1.5This report seeks approval to commit these funds to the capital programme in accordance with the Financial Procedure Rules.

2.0Submitted Bids

2.1A total of £85k was bid for by the City & County of Swansea and the Welsh Government has subsequently allocated £85k for the Broadway Interchange Scheme in 2018/19. The bid and the successful funding allocation are shown in the tables below.

Table One – Summary of Bids for Additional LTF 2018/19 Total Match Total project Fund funding Bid (£k) cost (£k) (£k) Broadway Interchange 85 0 85 Total 85 0 85

Table Two – Summary of Allocations for Additional LTF 2018/19 Total Match Total project Fund funding Bid (£k) cost (£k) (£k) Broadway Interchange 85 0 85 Total 85 0 85 3.0 Details of the Broadway Interchange Project

3.1The projects approved for funding are summarised below.

3.2The proposal for improvements at this interchange will deliver improvements to highway network efficiency for an area that is often congested by peak hour traffic. The improvements will involve the redesigning of the junction to ease congestion, introduce active travel accessibility, increase capacity and improve public transport journey time reliability and efficiency.

3.3This scheme has previously been awarded £10k of feasibility study funding from the Local Transport Network Fund (2018/19). The additional Local Transport Fund allocation will accelerate the project from feasibility to detailed design by the end of 2018/19.

3.4Further bids will be required in 2019/20 in order to secure funding for the delivery of the scheme.

4.0Equality and Engagement Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FPR7: Broadway Interchange: Local Transport Fund Grant 2018/19.Report 175 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 26 attended
RS
Rob StewartChair, present
JB
June BurtonshawCommittee Member, present
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, in attendance
RF
Robert Francis-DaviesCommittee Member, apologies
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, present
CL
Clive LloydCommittee Member, present
AH
Adam HillOfficer, in attendance
JR
Jennifer RaynorCommittee Member, present
MS
Mary SherwoodCommittee Member, in attendance
MT
Mark ThomasCommittee Member, present

All 26 on the meeting page

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies