Resolved that: 1) The transfers between schemes and the revised budgets for schemes in 2018/19 be approved . 2) The budget proposals for 2019/20 – 2022/23 be approved. 3) That, where individual schemes in Appendix B to the report are programmed over the 4 year period described in this report, then these are committed and approved and that their financial implications for funding over subsequent years be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Section 151 Officer & the Director of Place
Council – 28 February 2019
Housing Revenue Account (HRA) - Capital Budget and Programme 2018/19 – 2022/23
Purpose: This report proposes a revised capital budget for 2018/19 and a capital budget for 2019/20 – 2022/23
Policy Framework: None
Consultation: Legal, Finance & Access to Services
Recommendation(s): It is recommended that:
1) The transfers between schemes and the revised budgets for schemes in 2018/19 are approved.
2) The budget proposals for 2019/20 – 2022/23 be approved.
3) That, where individual schemes in Appendix B are programmed over the 4 year period described in this report, then these are committed and approved and that their financial implications for funding over subsequent years are approved.
Report Authors: Ben Smith / Mark Wade
Finance Officer: Ben Smith
Legal Officer: Tracey Meredith
Access to Services Officer: Catherine Window
1.0Introduction
1.1This report details: Revised Housing Revenue Account (HRA) capital expenditure and financing proposals in 2018/19 HRA Capital expenditure and financing proposals in 2019/20 – 2022/23
1.2The budget proposals are further detailed in appendices to this report as follows: Appendix A: Summary of the revised budget for 2018/19 and a budget for 2019/20 – 2022/23 Appendix B: Detailed breakdown of the revised budget for 2018/19 and a budget for 2019/20 – 2022/23 Appendix C: WHQS and More Homes scheme descriptions
2.0Capital Budget 2018/19
2.1The revised programme for the current year is £47.705m i.e. an original budget of £57.893m plus carry-forward from 2017/18 of £6.049m less slippage into 2019/20 of £16.237m. Slippage from this current year into 2019/20 is mainly to fund the external facilities scheme, kitchen and bathroom renewal and More Homes scheme at Parc Y Helig.
2.2The majority of all other projects for 2018/19 are complete although a small element of under spend may exist due to a range of reasons including retentions for the defects liability period and some under spends on completed projects. Any projects not currently complete will be completed within the early part of the 2019/20 financial year and where underspend has occurred, officers have mitigated these by bringing other priority work forward to compensate. Transfers and changes to the 2018/19 budget are reflected and detailed in appendix B.
3.02019/20 – 2022/23
3.1The proposed four year capital programme and the priorities of the various schemes have been developed in line with the HRA Business Plan and contributes to the Council’s strategic aim of meeting the Welsh Housing Quality Standard and provision has also been made for the continuing supply of new council housing.
3.2Investment over the next two years is set out to provide an even profile of spend. The programme will be challenging due to its size, scope and complexity; however, this has been developed to be deliverable and to achieve WHQS compliance by the end of December 2020.
3.3The main areas of work include kitchen and bathroom renewal; wind and weatherproofing; the start of a refurbishment programme for highrise flats; as well as environmental improvements and regeneration to gardens and the wider housing owned areas. These schemes are reported in detail in Appendix C and contribute towards the following components of the Welsh Housing Quality Standard:
In a Good State of Repair Dwellings must be structurally stable; free from damp and disrepair with key building components being in good condition – roofs, walls, windows, doors and chimneys.
Safe and Secure Dwellings should be free from risks that could cause serious harm and should be secure in key areas of the home. Heating and electrical systems to be up to date and safe; doors and windows to provide good levels of security; risk of falls from height to be prevented; fire safety measures to be in good condition and well designed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.