Housing Revenue Account – Capital Budget and Programme 2025/26 – 2029/30.
ApprovedExecutive1 paper
AI summarySwansea Council Cabinet approves revised 2025/26 and new 2026/27 to 2029/30 Housing Revenue Account capital programme totalling 321,806 (in £000s) for council housing repairs, fire safety, decarbonisation and new builds.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRecommended to full Council for approval
Money321,806 (£'000s) over five yearsFunded by MRA, RCCO, borrowing, SHG and other grants
What happens nextRecommend to Council for approvalFull Council to consider the budget proposals
Who it affectsCouncil housing tenants and applicantsExisting stock upgrades and new council homes in Swansea
What was decided
The Cabinet approved transfers between schemes and revised budgets for 2025/2026, along with budget proposals for 2026/2027 to 2029/2030.
Individual schemes in Appendix B programmed over the 4 year period were approved, with their financial implications for funding over four years.
The Cabinet resolved to recommend the budget proposals to full Council for approval.
Why
The HRA capital programme funds repairs, maintenance and improvement to council housing to meet the Welsh Housing Quality Standard 2023, which is a legal requirement and strategic target for the council. Report P21, P22
The programme supports fire safety upgrades, energy efficiency works and the creation of new council homes, contributing to decarbonisation of the housing stock and affordable warmth for tenants. Report P2, P25, P88
The Authority is under a duty to make arrangements for the proper administration of its financial affairs. Report P4
What happens next
Budget proposals to be recommended to full Council for approval.
Schemes are ongoing over the four year programme period, with some projects such as the Wimpey No Fines regeneration and highrise refurbishment expected to extend beyond the four years covered in this report. Report P45, P53
Where schemes are subject to planning permission requirements, officers will submit planning applications as necessary. Report P39, P40, P45, P53, P88
The money
321,806 Total HRA capital programme 2025/26 to 2029/30 in £'000s Report P15, P17
54,029 Revised 2025/26 budget in £'000s Report P15, P17
69,523 2026/27 original budget in £'000s Report P15, P17
73,262 2027/28 original budget in £'000s Report P15, P17
58,570 2028/29 original budget in £'000s Report P15, P17
66,422 2029/30 original budget in £'000s Report P15, P17
47,144 Major Repair Allowance total 2025/26 to 2029/30 in £'000 Report P16
132,641 Revenue Contribution to Capital total in £'000 Report P16
30,102 Social Housing Grant total in £'000 Report P16
Options considered
Chosen: Approve revised 2025/26 budgets and 2026/27 to 2029/30 budget proposals. Needed to fund HRA capital works and meet WHQS 2023 Report P22
Chosen: Commit individual schemes in Appendix B over the 4 year period. To allow programme delivery and funding approval over four years
Chosen: Recommend budget proposals to Council for approval. Required for proper administration of financial affairs Report P4
Implications
Financial: Expenditure is ringfenced to the HRA and will be fully funded by MRA grant from Welsh Government, revenue contributions from the HRA, HRA borrowing, Social Housing Grant, capital receipts and other grants, with no impact on the General Fund. Report P1
Financial: If capital receipts are not achieved, additional borrowing would be required. Report P1
Legal: The Authority is under a duty to make arrangements for the proper administration of its financial affairs, and failure to do so would be a breach of that duty. Report P4
Climate: Some work streams are supported with grant funding that will contribute to reducing occupancy related carbon emissions, though the scale is small relative to full decarbonisation which is assessed as unaffordable within the HRA business plan without further Welsh Government support. Report P2
Staffing: Schemes may engage partners such as academic bodies and specialists in delivery and monitoring, with contracts operating over the period of the four year programme. Report P39, P41
Who and where
Tenants of Swansea Council housing receiving upgrades to their homes Report P91
Applicants on the housing waiting list through new council home provision Report P88
Residents in regeneration areas including Heol Emrys, Tudno Place, Dyfatty highrise and Sketty Report P42, P46
Tenants with medical conditions or disabilities receiving adaptations Report P86
Tenants in older person or sheltered accommodation through warden call and lift improvements Report P69, P85
Timeline
2025/26 (revised): Capital budget of 54,029 (in £'000s) including scheme transfers Report P8, P15
2026/27: Original capital budget of 69,523 (in £'000s) Report P15
2027/28: Original capital budget of 73,262 (in £'000s) Report P15
2028/29: Original capital budget of 58,570 (in £'000s) Report P15
2029/30: Original capital budget of 66,422 (in £'000s) Report P15
Beyond 2029/30: Some schemes such as Wimpey No Fines regeneration and highrise refurbishment will continue beyond the four year reporting period Report P45, P53
Plain English for the jargon
HRA: Housing Revenue Account, the ringfenced account that records income and expenditure relating to council housing
WHQS 2023: Welsh Housing Quality Standard 2023, the legal standard social landlords in Wales are expected to meet
MRA: Major Repair Allowance, grant funding from Welsh Government for housing repairs
RCCO: Revenue Contribution to Capital, transfer of revenue income to fund capital spending
SHG: Social Housing Grant, Welsh Government funding to support new affordable housing
ORP: Optimised Retrofit Programme, Welsh Government support for energy efficiency refurbishment
HAPS: Homes as Power Stations, an approach using renewable technologies in homes
SAP 92: Standard Assessment Procedure energy efficiency rating target of 92
PAS2035: British Standard for retrofitting dwellings to improve energy efficiency
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item130
Resolved
Resolved that: 1) The transfers between schemes and the revised budgets for schemes in 2025/2026 be approved. 2) Budget proposals for 2026/2027-2029/2030 be approved. 3) Individual schemes in Appendix B which are programmed over the 4-year period as described in this report, be committed and that their financial implications for funding over 4 years be approved. 4) Budget proposals be recommended to Council for approval.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Housing Revenue Account – Capital Budget and Programme 2025/26 – 2029/30 Executive Summary Purpose of Report:
To seek approval for the revised capital budget for 2025/26 and a new capital budget and programme for 2026/27 – 2029/30
Recommendation(s). It is recommended that: 1) The transfers between schemes and the revised budgets for schemes in 2025/26 are approved.
2) Budget proposals for 2026/27 – 2029/30 are approved.
3) Individual schemes in Appendix B which are programmed over the 4-year period as described in this report, are committed and that their financial implications for funding over 4 years are approved.
4) Budget proposals are approved by Council
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☒ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☒ Tackling Poverty & Enabling Communities ☒ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☐ Not Applicable
Relevance to Corporate Plan Wellbeing Objectives:
The HRA capital investment programme links directly to the Economy and Infrastructure and Tackling Poverty and Enabling Communities wellbeing objectives. The recommendations within this report will make existing council homes more efficient and affordable to help minimise household costs. The More Homes Transformation Programme increases the supply of affordable housing, delivers the capital programme to agreed standards, and progresses strategic plans and partnerships to meet local housing need, increasing the number of properties.
Reviewed and approved by:
Access to Services, Finance, Legal & Cabinet Member.
Report Authors & Job Dave Bratley Housing Programme Planning and Titles: Delivery Manager Hannah Smith Housing Asset Manager
1. Introduction
2. This report is to meet financial procedure rules and sets out the revised Housing Revenue Account (HRA) capital expenditure and financing arrangements for 2025/26 and the HRA Capital budgets and financing proposals in 2026/27 – 2029/30.
3. The budget proposals are further detailed in the appendices to the report as follows:
• Appendix A: Summary of the revised budget for 2025/26 and a budget for 2026/27 – 2029/30
• Appendix B: Detailed breakdown of the revised budget for 2025/26 and a budget for 2026/27 – 2029/30
• Appendix C: Welsh Housing Quality Standard (WHQS) and More Homes scheme descriptions
4. Capital Budget
5. The revised programme for the current year is £54m from an original budget of £56m. The projected outturn is £51.3m with £2.7m slippage into 2026/27 against the revised budget.
6. Capital investment over the next 4 years is £268m.
7. Slippage from 2025/26 into 2026/27 has occurred in some work areas due to the following issues; the need to secure specialist design resources, the impact from Natural Resource Wales instruction on marine nitrates affecting More Homes Projects, high-value highrise project requiring additional time for contract negotiations and complex projects requiring in-depth investigation and design leading to the schemes taking longer to reach the delivery stage. Also, some projects have encountered on-site delays due to managing ecology issues as well as performance by statutory bodies leading to contracts having to extend into the new financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.