First Stage (Construction) Contract Award and Associated Capital Programme Authorisation for the Remodelling and Refurbishment Project at Bishopston Comprehensive School.

Approved Executive 3 papers

Cabinet approved this item on Thursday 21 March 2019. Below is the council's own wording, with the papers it was decided on.

Item176

Resolved

Resolved that: 1) Contractor 4 be appointed to carry out the pre-construction service to the sum of £392,000 subject to the completion of appropriate financial due dilligence . Contractor 4 is considered to represent the most economically advantageous tender and that which gives best value for the Authority; 2) £554,469 be committed to the Capital Programme to fund the pre-construction phase costs, including the pre-construction contractor service and internal fees; 3) The Chief Legal Officer be authorised to enter into and necessary documentation to complete the contract and achieve the project; 4) A further report be submitted in late 2019 to consider the approval of the Stage Two contract award and subject to confirmation and acceptability of construction costs to commit the project cost to the Capital Programme prior to any physical works being carried out.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Education Improvement, Learning and Skills

Cabinet – 21 March 2019

First Stage (Construction) Contract Award and Associated Capital Programme Authorisation for the Remodelling and Refurbishment Project at Bishopston Comprehensive School Purpose:  To seek authorisation to award the Stage One contract for the works to Tender 4.  To seek authorisation to commit a total of £551,469 to the capital programme to fund the pre-construction phase costs. To comply with Financial Procedure Rule 7 – to commit and authorise a new scheme to the Capital Programme.  The Revenue Budget 2018/2019 and the Capital Budget 2017-2018 to 2023-24 was approved by Council on 6 March 2018.

Policy Framework:  QEd Programme and Strategic Outline Programme for Band B of the 21st Century Schools Programme  Asset Management Plan  Contract and Financial Procurement Rules

Consultation: Access to Services, Finance, Legal, Corporate Building and Property Services.

Recommendation(s): It is recommended that:

1) That Contractor 4 be appointed to carry out the pre-construction service to the sum of £392,000. Contractor 4 is considered to represent the most economically advantageous tender and that which gives best value to the authority. 2) That £551,469 is committed to the capital programme to fund the pre- construction phase costs, including the pre-construction contractor service and internal fees.

3) The Chief Legal Officer is authorised to enter into any necessary documentation to complete the contract and achieve the project.

4) That a further report is submitted in late 2019 to consider the approval of the Stage Two contract award and subject to confirmation and acceptability of construction costs to commit the project cost to the capital programme prior to any physical works being carried out.

Report Author: Louise Herbert-Evans

Finance Officer: Ben Smith

Legal Officer: Debbie Smith

Access to Services Officer: Catherine Window

1. Introduction

1.1The Welsh Government formally confirmed on the 7 December 2017 that the envelope for Band B of the Council’s 21st Century Schools / QEd Programme was approved in principle with an estimated programme envelope cost of £149.7 million. This is subject to the approval of individual project business cases.

1.2The approval in principle of the Strategic Outline Programme for Band B does not commit the Council, since the final approval of any capital allocation from the Welsh Government is subject to the submission of further detailed business cases in respect of each specific project.

1.3Swansea Council’s Quality in Education (QEd) / 21st Century Schools Band B Programme focuses on an investment need which reflects the challenges remaining across our schools. The Band B programme remains consistent with local policies, priorities and commitments, as well as the priorities and specific criteria set down by the Welsh Government as follows:

 To provide an efficient and effective educational infrastructure that will meet current and future demand for places by 2024  Ensuring the right size schools in the right location, with enough places to deliver Welsh and English medium education, whilst ensuring effective and efficient use of the educational estate  Reducing backlog maintenance costs by at least 50% whilst improving any category C or D condition buildings to A or B

1.4The Council’s 21st Century Schools Programme Capital Expenditure & Financing 2017/18 - 2023/24 provides an outline spending profile for the priority projects. Included within this phase of priority projects is English - medium secondary schools, which aims to address the significant condition and suitability needs across a number of sites which are well beyond the scope of the Council’s annual structural maintenance programme. Works will need to be phased across Bands B,C and D reflecting the level of funding available, prioritising the areas of greatest need.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12 (2 of 3) BISHOPSTON FINANCIAL IMPLICATIONS APP A FPR7 Feb 2019 v0.5: Appendix 1Appendix 23 KB Download
PDF
12 (3 of 3) EIA Report_Bishopston Comprehensive v0.7: Appendix 2Appendix 170 KB Download
PDF
First Stage (Construction) Contract Award and Associated Capital Programme Authorisation for the Remodelling and Refurbishment Project at Bishopston Comprehensive School.Report 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 23 attended
RS
Rob StewartChair, present
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, present
CL
Clive LloydCommittee Member, present
AH
Adam HillOfficer, in attendance
JR
Jennifer RaynorCommittee Member, present
MS
Mary SherwoodCommittee Member, present
MT
Mark ThomasCommittee Member, present
MN
Martin NichollsOfficer, expected

All 23 on the meeting page

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies