Resolved that: 1) The Capital Maintenance Schemes for Building Services, as listed in Appendix A, be approved; 2) The Director and Cabinet Member be granted delegated authority to approve individual Social Services schemes; 3) The financial implications identified in Appendix C and D be approved and included in the Capital Programme.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Business Transformation & Performance
Cabinet – 21 March 2019
Building Capital Maintenance Programme 2019/2020 Purpose: To agree the schemes to be funded through the Capital Maintenance programme
Policy Framework: Financial Procedure Rule No.7 (Capital Programming and Appraisals) The Revenue and Capital Budget as reported to and approved by Council on the 28th February 2019
Consultation: Access to Services, Finance, Legal, Education, Social Services
Recommendation(s): It is recommended that Cabinet:
1) Approves the proposed capital maintenance schemes for Building Services, as listed in Appendix A. 2) Delegates authority to the Director and Cabinet Member to approve individual Social Services schemes. 3) Authorises the financial implications identified in Appendix C & D to be included in the capital programme.
Report Author: Nigel Williams
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Catherine Window
1.0Introduction
Cabinet has previously approved the Council’s Asset Management Plan for Property Assets which sets out a series of measures to improve the management and performance of the property portfolio. This Report sets out the way in which the Capital Maintenance resources for 2019/20 will be deployed. 2.0 Capital Programme Process
On 28th February 2019, Council approved a Capital Maintenance allocation of £4m for the Authority’s building portfolio plus a further £700k for the Social Services asset portfolio.
3.0Objectives of Scheme
3.1The proposals set out will directly support the corporate objectives of the Authority, in relation to the maintenance and improvement of the Authority’s building portfolio.
3.2This maintains the previous commitment to address the significant backlog of maintenance and minimise the potential effect of unforeseen breakdowns of building elements.
3.3As was reported in previous building maintenance programme reports, attention needs to be drawn to the fact that the Authority still has a significant backlog of maintenance and whilst there have been some reductions in this backlog, the limited programme contained within the 2019/20 budget, whilst being very important, will not remedy the immediate backlog.
Notwithstanding the current financial pressures, further budget provisions will therefore need to be made in subsequent years to maintain this investment and minimise the risks of failure and unplanned closures.
3.4The list of identified schemes (Appendix A) has been selected on a priority basis. The criteria for selection (unless otherwise stated) was based upon Condition rating as independently determined by the recently completed, externally commissioned, condition surveys, Legislative compliance, Health and Safety implications, likelihood of failure and business continuity. Whilst all schemes have been selected on these criteria there are a number of similar priorities which we are unable to progress within the budgets available.
4.0Description of Schemes
4.1The recommended list of schemes is included in Appendix A and to assist, a brief summary of the planned works have been included as follows:-
1a) Statutory Compliance - Electrical The schemes listed consist of total rewires, partial rewires or upgrades to ensure safety and compliance with electrical regulations and maintained operation of the premises. 1b) Mechanical/Heating Schemes The schemes listed in this section deal with the avoidance of heating failures within our establishments on a prioritised basis.
1c&1d) Statutory Compliance - Legionella and Asbestos As a result of the existing policy to enable compliance with the legionella and asbestos legislation, capital repairs arising out of risk assessments and surveys need to be carried out to maintain compliance. These upgrades are actioned throughout the year and therefore a list of schemes cannot be prepared in advance. Separate revenue monies have been set aside to deal with the ongoing management process and minor repairs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.