Resolved that the following be recommended to Council for approval: 1) The transfers between schemes and the revised budgets for schemes in 2019-2020 be approved; 2) The budget proposals for 2020-2021 – 2023-2024 be approved; 3) Where individual schemes as shown in Appendix B are programmed over the 4 year period described in the report, then these be committed and approved and their financial implications for funding over the 4 years also be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Purpose: This report proposes a revised capital budget for 2019/20 and a capital budget for 2020/21 – 2023/24.
Policy Framework: None.
Consultation: Cabinet Member, Legal, Finance & Access to Services
Recommendation(s): It is recommended that:
1) The transfers between schemes and the revised budgets for schemes in 2019/20 are approved;
2) The budget proposals for 2020/21 – 2023/24 are approved;
3) That, where individual schemes in Appendix B are programmed over the 4 year period described in this report, then these are committed and approved and that their financial implications for funding over the 4 years are approved.
Report Authors: Ben Smith / Mark Wade
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Rhian Millar
1.0Introduction
1.1This report details:
Revised Housing Revenue Account (HRA) capital expenditure and financing proposals in 2019/20 HRA Capital expenditure and financing proposals in 2020/21 – 2023/24
1.2The budget proposals are further detailed in appendices to this report as follows: Appendix A: Summary of the revised budget for 2019/20 and a budget for 2020/21 – 2023/24 Appendix B: Detailed breakdown of the revised budget for 2019/20 and a budget for 2020/21 – 2023/24 Appendix C: Welsh Housing Quality Standard (WHQS) and More Homes scheme descriptions
2.0Capital Budget 2019/20
2.1The revised programme for the current year is £53.36m i.e. an original budget of £67.313m plus carry-forward from 2018/19 of £4.676m less slippage into 2020/21 of £12.810m. Slippage from this current year into 2020/21 has occurred in high value schemes due to factors which have not been in the Council’s control including insufficient private contractor resource to fully deliver the external facilities scheme; the contractor for the wind and weatherproofing scheme at West Cross entered into administration mid-way through the contract requiring a second contractor to be engaged to deliver the remainder of the project. The contractor selected to deliver the wind and weatherproofing scheme at Waunarlwydd withdrew resulting in a delayed scheme start whereas slippage for the More Homes scheme at Colliers Way arose due to the time required to investigate and design suitable drainage arrangements for the site. In addition, £5.919m which was carried forward for kitchen and bathroom renewal (where tenants had declined to participate in the scheme) has now been set aside for use post 2020/21.
2.2The majority of all other projects for 2019/20 are complete although a small element of under spend may exist due to a range of reasons including retentions for the defects liability period and some under spends on completed projects. Any projects not currently complete will be completed within the early part of the 2020/21 financial year and where underspend has occurred, officers have mitigated these by bringing other priority work forward to compensate. Transfers and changes to the 2019/20 budget are reflected and detailed in appendix B.
3.02020/21 – 2023/24
3.1The proposed four year capital programme and the priorities of the various schemes have been developed in line with the HRA Business Plan and designed to achieve the Council’s strategic aim of meeting and maintaining the Welsh Housing Quality Standard as well as other key Housing Service aims. The programme also sets out proposals for increasing the supply of council housing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.